- PRM-050~042- - PETITION FOR RULEMAKING FROM GOVERNOR CUOMO, STATE OF NEW YORK, REQUESITNG AN EMERGENCY EVACUATION PLAN AS A.CONDITION TO LOW POWER TESTING PRM:.os0-042 RULEMAKING COMMENTS Document Sensitivity: \\ Non-sensitive - SUNSI ReviE?W Complete I
0 L
~r,n;r NtlMBmt
,ttoo. & UTIL PAC..:,fq-32: 2, __ o L-3 MARIO M CUOMO GovE:RNOR STATE OF NEW YORK EXECUTIVE CHAMBER ALBANY 12224 OOGKETEO USNRC 116 JI. -1 A9 :26 H"\\"KET NUMpyta,...,
OFFICE Of :::::.cRL :.i.1(Y IN\\,,
cc.l"f GI\\ 1/""t DOCKETING & SEPVICf.
PETITION RULE PRM.. ~T~une 26, 1986 BRANCH
!EIMD jUl 1 1986
Dear Dr. Palladino:
I respectfully request that the Nuclear Regulatory Commission (NRC) consider changing its regulations or the interpretation thereof so as to require an approved offsite emergency evacuation plan as a condition to low-power testing any nuclear facility.
at I also request that, pending completion of this re-evaluation of its regulations, the NRC stay low-power testing at the Shoreham nuclear facility and other nuclear facilities where a low-power license has been authorized and there is no approved offsite emergency evacuation plan.
As_you know, Chernobyl was operating at only six to seven percent of power when the April 29th accident occurred.
This rais~a nill!\\erius questions for the nuclear power industry and for the mic.
Amorlg the issues which I believe the NRC should consider in light of Chernobyl are:
- a.
Does Chernobyl indicate that low-power testing can pose far greater risks to surrounding populations than previously asserted?
- b.
Can a serious accident with widespread geographic effects occur even when a nuclear power plant is operating at low-power levels?
- c.
Should an offsite emergency evacuation plan be required for low~power testing?
- d.
What level of risk, if any, is considered acceptable by the NRC, even without an emergency evacuation plan?
Dr. Palladino Page 2 June 26, 1986
.I have previously suggested answers to several of these questions.
In particula~~ I proposed that low-power testing not be permitted without approval of an offsite emergency evacuation plan.
The Chernobyl incident only serves to strengthen the case for such a policy.
I ask that you reconsider it and require an approved offsite emergency evacuation plan as a condition to low-power testing.
I also request that you stay such testing at the Shoreham nuclear facility until such an evacuation plan has been approved.
Honorable Nunzio J. Palladino Chairman Nuclear Regulatory Commission Matomic Building 1717 H Street, N. W.
Washington, D. c.
20555 Sincerely,