ML23152A172

From kanterella
Jump to navigation Jump to search
26 - NRC - Aging Related Inspection Procedures
ML23152A172
Person / Time
Issue date: 06/14/2023
From: John Wise
NRC/NRR/DNRL
To:
References
Download: ML23152A172 (1)


Text

Aging Related Inspection Procedures John Wise Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Industry/NRC Materials Technical Exchange Meeting June 14-15, 2023

Recent & Impending Inspection Changes

Inspection Procedure (IP) 71002: License Renewal Inspection (revision - minor edits)

IP 71003: Post-Approval Site Inspection for License Renewal (revision)

IP 71013: Site Inspection for Plants with a Timely Renewal Application (new, based on prior issuance)

  • Baseline Inspection Related to Aging IP 71111.21N.04, Age-Related Degradation (new, in effect July 1) 2

Initial License Renewal Inspections Timing Focus 71002 During review of initial

  • Adequacy of scoping/screening
  • Capability of existing programs &

enhancements to manage aging 71003 Phase I 1-2 outages prior

  • Implementation of select aging to PEO management activities (including SSCs with reduced accessibility) 71003 Phase II 3-12 months prior
  • Implementation and completion of to PEO aging management activities (major team inspection) 71003 Phase III After entering PEO
  • As necessary, implementation of activities; follow up previously identified issues 71003 Phase IV 5-10 years into PEO
  • Minimum of 6 AMPs: implementation, corrective actions 3

Subsequent LR Inspections

Evaluate the need for an SLR Inspection Program Consider additional guidance for Phase IV to enhance consistency between Regions

  • Forthcoming IP 71003 Revisions New Phase V, entering Subsequent PEO
  • Review implementation of select activities (reduced version of Phases I-III)

New Phase VI, 5-10 years into Subsequent PEO

  • Implementation & corrective action review of 6 AMPs (similar to Phase IV)

Revisions for clarity and completeness 4

LR Inspection Additions Initial LRA 71003 71003 submission Phases I-III Phase V Initial PEO Subsequent PEO 20 40 60 80 years 45-50 years 65-70 years 71002 Inspections 71003 71003 Phase IV Phase VI 5

IP 71013 - Timely Renewal

  • For use when:

A renewed license is not anticipated to be issued prior to the licensee entering the requested period of extended operation The existing license is not deemed to have expired until the application has been finally determined (under timely renewal considerations)

  • Accomplishes the essential objectives of 71003, post-approval site inspections Communication with applicant to understand status of LR activities Implementation of proposed activities, including license conditions, AMPs, TLAAs, etc.

6

Baseline Inspection Program

  • Enhancements to baseline inspections to include periodic aging management inspections SRM-SECY-14-0016 (ML14241A578) - the staff should integrate aging management inspection guidance into each existing and applicable ROP baseline inspection procedure 2014 ROP Enhancement Project (ML14017A338) implemented the Commissions direction Recent updates per the 2018 recommendations of the Engineering Inspection Working Group (ML18103A174)
  • Complements the largely programmatic renewal IPs with a greater focus on how aging issues are addressed 7

Baseline Inspection Program Examples of prior incorporation of aging management into baseline inspections

  • 71111.08 - Inservice Inspection Activities
  • 71111.21N.05 - Fire Protection Team Inspection 8

IP 71111.21N.04 - Age-Related Degradation

  • Plan to conduct once per site
  • Part of suite of focused engineering inspections - on recent plant changes and operating experience
  • Verifies that age-related degradation is appropriately identified, addressed, and corrected Structure and component focused - emphasis on those with greatest risk significance, susceptibility to aging, and history of degradation Includes active and short-lived SSCs - broader scope than LR inspections 9

THANK YOU 10