ML23146A097

From kanterella
Jump to navigation Jump to search
16 - NRC - French SCC Update
ML23146A097
Person / Time
Issue date: 06/14/2023
From: Ali Rezai, David Rudland
NRC/NRR/DNRL/NPHP, NRC/NRR/DNRL
To:
References
Download: ML23146A097 (1)


Text

Industry / NRC Materials Programs Technical Information Exchange

French SCC Issue - Update and NRC Activities

David Rudland Senior Technical Advisor

NRC Headquarters June 14-15, 2023 Outline

  • Timeline from ASN/EDF
  • Cracking details
  • Safety implications
  • Staff plans
  • Since we went over this issue last year, we will not go through the history in detail

06/14/2023 Industry / NRC Annual Technical Exchange 2 ASN/EDF Timeline

October 2021 December 2021

  • Civaux reactor 1 - 2nd ten-year outage:
  • Civaux reactor 1: Laborator y analyses Detection of circumferential flaws in concluded that these cracks were close proximity to a weld in the safety due to IGSCC injection system piping
  • Anticipated outage for inspection of

November 2021 Januar y 2022

  • Anticipated outage for
  • Penly reactor 1: Laborator y analyses inspection of Civaux reactor 2: concluded that the cracks were due to IGSCC flaws are detected (safety injection system)
  • Extension of inspection to other welds of safety injection and RHR systems of Penly
  • Penly reactor 1-3rd ten-year reactor 1 and 1450 MWe units (N4 type) outage: flaws are detected (safety injection system)

06/14/2023 Industry / NRC Annual Technical Exchange 3 ASN/EDF Timeline

Spring 2022 Autumn 2022

  • Implementation of preliminar y inspection program on
  • End of inspections on << prioritized priority reactors : reactors >> and repairs
  • Reactors identified from reanalysis of previous
  • Discussion of the new inspection inspection repor ts (6 reactors) program between ASN and EDF
  • Reference reactor (one of each design)
  • Those with upcoming10-year outages
  • Implementation of Reinforced reactor oversight to secure the ability to quickly detect any leak

Summer 2022 Early 2023

  • Following the preliminar y inspection program
  • Beginning of the implementation of
  • Availability of new NDT method able to accurately the new inspection program, detect and size the defects concerning all reactors in operation,
  • Over 110 welds destructive tests performed
  • Beginning of the repairs program on the areas that might be susceptible to IGSCC (end of the program by 2025)
  • Large flaw found at Penly 2

06/14/2023 Industry / NRC Annual Technical Exchange 4 Original cracking

  • Civaux 1 cracking Inside

- The pipe is 300mm in diameter with a wall thickness of 30mm

- Safety injection piping near cold leg

- Stress corrosion cracking (SCC): flaw propagation is intergranular

- Location

  • heat affected zone (HAZ) on both sides of the weld
  • Crack length is 360° (full circumference) and the maximum depth is 5.6mm
  • Relatively high hardness (250<HV<290)

- Relatively big first layer of the weld (manual TIG weld )

- Residual stress supports the arrest of through cracking

- Suspected to be due to large thermal stratification loads

06/14/2023 Industry / NRC Annual Technical Exchange 5 New Cracking

  • Penly 2 Cracking Crack

- Found after expansion of the inspection plan

- Safety injection piping near hot leg

- Suspected SCC

- 85% deep, 6-inch -long circumferential crack in HAZ

- Little to no thermal stratification Hot Leg

- Weld was repaired twice - suspected driver

  • Due to unexpected size and location of cracking, understanding the safety implication to the US fleet is important

06/14/2023 Industry / NRC Annual Technical Exchange 6 Where are these flaws?

Typical Westinghouse four loop ECCS Cold Leg

Crack

Crack

Safety Injection Hot Leg System

06/14/2023 Industry / NRC Annual Technical Exchange 7 Safety Implications

  • Could this cracking occur in US fleet?
  • If it can, what are the safety implications?

- Cracks are in unisolable section of pipe

  • Break can cause LOCA
  • Only one ECCS train is affected?

- New cracking was very long and deep

  • Staff looked at risk-triplet through their BeRiskSMART process (NUREG/KM-0016)

- What can go wrong/what can go right

- What are the consequences of each

- What is the expected likelihood of each

- Qualitative assessment

06/14/2023 Industry / NRC Annual Technical Exchange 8 Safety Implications, Staff Plans

  • Conclusion from BeRiskSMART

- Uncertainties are large with unknown impact of break on plant safety

  • Are our plants susceptible? Water chemistry, etc.
  • Do we have unknown (undocumented/unrecorded) weld repairs in these locations?
  • Even though these systems are susceptible to thermal fatigue, are we inspecting these locations, i.e. are these welds in the risk -informed program?
  • What is the impact to the plant if we lose this system?
  • Staff concluded that a more quantitative analysis is needed

- Initiated a LIC-504, Integrated Risk -Informed Decisionmaking Process for Emergent Issues.

- Using a Simplified approach with the goal of completion by July 2023.

06/14/2023 Industry / NRC Annual Technical Exchange 9 Safety Implications, Staff Plans

- Investigation into the probability of rupture of an unisolable pipe in the safety injection system

  • Perform xLPR analyses or use past runs to make a conservative prediction
  • Sensitivity studies as necessary

- Investigate the conditional core damage probability resulting from loss of the portion of the safety injection system

  • Exercise Standardized Plant Analysis Risk (SPAR) models for a variety of Westinghouse 4 -

loop and 3-loop plants

- Determine risk impact and make recommendation

- Using simplified approach to be completed in 3 months

  • Other Actions

- Continue to follow industry actions and report development

06/14/2023 Industry / NRC Annual Technical Exchange 10