ML23122A222
| ML23122A222 | |
| Person / Time | |
|---|---|
| Site: | 03037450 |
| Issue date: | 04/06/2023 |
| From: | Dye C, Nieves L NRC/RGN-III |
| To: | Tasset P Olsson |
| References | |
| IR 2023001 | |
| Download: ML23122A222 (1) | |
See also: IR 05000202/2030001
Text
(04-2022)
Materials Inspection Report
U.S. NUCLEAR REGULATORY COMMISSION
Page 1 of 2
Add Continuation Page
1. Licensee/Location Inspected:
Olsson, Inc.
1700 E. 123rd St.
Olathe, KS 66061
Report Number(s) 2023001
2. NRC/Regional Office
Region III
U. S. Nuclear Regulatory Commission
2443 Warrenville Road, Suite 210
Lisle, IL 60532-4352
3. Docket Number(s)
030-37450
4. License Number(s)
15-29260-01
5. Date(s) of Inspection
3/22/2023 - 4/6/2023
LICENSEE:
The inspection was an examination of the activities conducted under your license as they relate to radiation safety and to compliance with the
Nuclear Regulatory Commission (NRC) rules and regulations and the conditions of your license. The inspection consisted of selective
examinations of procedures and representative records, interviews with personnel, and observations by the inspector. The inspection findings
are as follows:
1. Based on the inspection findings, no violations were identified.
2. Previous violation(s) closed.
3. During this inspection, certain of your activities, as described below and/or attached, were in violation of NRC requirements, and
were assessed at Severity Level IV, in accordance with the NRC Enforcement Policy.
B. The following violation(s) is/are being cited in accordance with NRC Enforcement Policy. This form is a NOTICE OF VIOLATION,
which may be subject to posting in accordance with 10 CFR 19.11.
(Violations and Corrective Actions)
Statement of Corrective Actions
I hereby state that, within 30 days, the actions described by me to the Inspector will be taken to correct the violations identified. This statement of corrective
actions is made in accordance with the requirements of 10 CFR 2.201 (corrective steps already taken, corrective steps which will be taken, date when full
compliance will be achieved). I understand that no further written response to NRC will be required, unless specifically requested.
A. The violation(s), specifically described to you by the inspector as non-cited violations, are not being cited because they were self-
identified, non-repetitive, corrective action was or is being taken, and the remaining criteria in the NRC Enforcement Policy
were satisfied.
(Non-cited violation(s) was/were discussed involving the following requirement(s)
TITLE
NRC INSPECTOR
PRINTED NAME
SIGNATURE AND DATE
LICENSEE'S
REPRESENTATIVE
Luis Nieves
BRANCH CHIEF
Luis A. Nieves Folch
Digitally signed by Luis A. Nieves Folch
Date: 2023.04.07 07:34:20 -05'00'
Digitally signed by Rhex A. Edwards
Date: 2023.04.26 05:45:03 -05'00'
(10-04-2022)
U.S. NUCLEAR REGULATORY COMMISSION
Materials Inspection Record
Page 1 of 1
NRC Form 592M (10-04-2022)
1. Licensee Name:
Olsson, Inc.
2. Docket Number(s):
030-37450
3. License Number(s)
15-29260-01
4. Report Number(s):
2023001
5. Date(s) of Inspection:
3/22/2023 - 4/6/2023
6. Inspector(s):
Luis Nieves and Carol Dye
7. Program Code(s):
03121
8. Priority:
5
9. Inspection Guidance Used:
87124
10. Licensee Contact Name(s):
Patrick Tasset- RSO
11. Licensee E-mail Address:
ptasset@olsson.com
12. Licensee Telephone Number(s):
918-346-5700
13. Inspection Type:
Initial
Routine
Announced
Non-Routine
Unannounced
14. Locations Inspected:
Hybrid
Main Office
Field Office
Temporary Job Site
Remote
15. Next Inspection Date (MM/DD/YYYY):
3/22/2028
Normal
Reduced
Extended
No change
16. Location(s) Inspected List:
826 N. Dickerson Ct., Springfield, Missouri, 65803
17. Scope and Observations:
This was an unannounced, routine inspection of an engineering company in Springfield, Missouri. The licensee
performs soil and asphalt density testing in the Missouri area. The licensee possessed three Troxler Model 3440 and
one Instrotek Model 3500. At the time of the inspection, the licensee employed 10 certified gauge users. The
licensee did not perform any service or maintenance activities on its gauges. These activities were performed by the
manufacturer and service providers.
Performance Observations
At the time of the inspection, the gauges were not being used and were properly secured with two barriers at the
office. The licensee demonstrated how they use the gauge, use ALARA practices in the field, and secure the gauge
during transport. The licensee had the required shipping papers that contained all appropriate information and
demonstrated how they are made accessible in the transport vehicle. The operators demonstrated an adequate level
of understanding of emergency and handling procedures during interviews. The inspector reviewed annual audits,
leak tests, hazmat training records, dosimetry records, inventory records, and usage logs.
The inspector reviewed a previous violation for the failure to use a minimum of two independent physical controls to
secure a gauge when not under constant surveillance. The licensee demonstrated to the inspector how they secure
the gauge to the back of a pickup when not under constant surveillance. This violation is closed.
No violations of NRC requirements were identified as a result of this inspection.
Signature and Date - Branch Chief
Digitally signed by Rhex A. Edwards
Date: 2023.04.26 05:44:14 -05'00'
From:
Luis Nieves Folch
To:
ptasset@olsson.com
Subject:
NRC IR 591 Olsson, Inc.
Date:
Monday, May 1, 2023 12:21:00 PM
Attachments:
591M- Olsson sign_RAE.pdf
Dear Patrick
Attach is the clear 591 report for the inspection conducted on 3/22/2023. At this point there is no
further actions on your part.
In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRCs Rules of
Practice, a copy of this message will be available electronically for public
inspection in the NRCs Public Document Room or from the NRC's Agencywide Documents Access
and Management System (ADAMS), accessible from the NRCs
website at http://www.nrc.gov/reading-rm/adams.html.
Please feel free to contact me if you have any questions regarding this correspondence.
Thank you,
Luis Nieves
Health Physicist
U.S. Nuclear Regulatory Commission
Division of Nuclear Materials Safety
Office: (630) 829-9571
Fax: (630) 515-1259