Attachment 6 OBDI 202 - IOLE Process Rev 3 PROPOSED OUTLINE COMMENTS Facility:

CGS First Exam Date:

2/20/23 Written Exam Outline Comment Resolution 1

NRC Generated Administrative JPM Outline Comment Resolution 1

A1 - bank from 2017 A1 None required 2

A2 - modified from 2015 A1 and 2009 A2 None required 3

A3 - change hydro to LLRT in description 4

A5 - Determine should be lower case 5

A7 - modified from 2017 A6 None required 6

A8 - bank from 2019 A8 None required Control Room / In-Plant System JPM Outline Comment Resolution 1

(E) designator is for in-plants only, thus S1, S2, and S6 should not carry this designator.

(EN) designator is for simulator / control room only, thus P3 should not carry this designator 2

S4 - bank from either 2009, 2013, 2015, 2017, or 2021 None required 3

S4-Remove. before (ALT) 4 S5 - bank from 2021 S1 None required 5

S7 - this is modified from 2019 S2. That JPM was alt path, and was opposite transformers 6

S8 - modified from 2017 S4 None required 7

P2 - Seems reasonable, but is it fair to have a JPM asking the operator to perform tasks of the Duty Electrician? Do the R.O.s train on this?

8 P3 - bank from 2017 P3 None required Simulator Scenario Outline Comments Comment Resolution 1

Not significantly varying power level on the scenarios. In the future, be more cognizant Corrected Corrected Corrected Corrected Corrected - marked as Modified Corrected -modified None required