Pcc - Workshop - Path Forward - March 30, 2023 - Final
ML23088A076
Person / Time
Issue date: 03/30/2023
From: Lundy Pressley
NRC/NRR/DRA/APOB
To:
References
Download: ML23088A076 (1)


Text

PRA Configuration Control Workshop Proposed Path Forward x March 30, 2023 Lundy Pressley Reliability and Risk Analyst Office of Nuclear Reactor Regulation Division of Risk Assessment PRA Oversight Branch

Overall Plan & Path Forward Obtained Develop Enf./SDP Develop Completed Issue Public Alignment with strategy and long-term Tabletops Report on NRC Mgt. on Regional Panel oversight process at facilities Tabletops PCC Proposal Guidance Dec 2022 April/May 2023 2026 Feb/Mar 2023 Fall 2023 Conduct public Gather feedback Developed meeting Develop from near-term Working Group Workshop with near-term oversight, update as recommendations Tabletop oversight necessary for near-term sites/Industry guidance path forward 2024-2026 Stakeholders Summer 2023 Feb 2023 Mar 2023 2

Proposal:

  • Some level of oversight is appropriate to ensure the PRA is maintained over the life of the plant.
  • Balanced approach of focused inspections within the existing ROP to monitor Plant/PRA changes and ensure appropriate implementation of PRA Configuration Control (PCC) programs for licensee PRA models that support risk-informed decision-making.
  • The NRC Working Group has leveraged insights from the information gathered from the voluntarily performed tabletops, as well as interactions with industry and public meetings, to develop options and a draft recommendation for the PRA CC framework.

3

Evaluated Options Four options considered:

  • Option 1 - Comprehensive Engineering Team Inspection (CETI)

(Internal Events, Flooding & Other Approved Hazards)

Focused Engineering Inspection (FEI) / (71111.21N)

  • Option 2 - Resident Inspector Baseline Procedures. All hazards.
  • Option 4 - OpE Smart Sample (OpESS)

Added to current CETI/FEI/Fire/and Others as applicable (i.e., IP 37060, 71151, etc.).

4

WGs Recommended Inspection Enhancement

  • Step 1 (Near-term): OpE Smart Sample (OpESS+)

PROPOSED Inspection Procedures:

71111.21M, Comprehensive Engineering Team Inspection, (CETI) 71111.21N.05, Fire Protection Team Inspection (FTPI) 37060, 10 CFR 50.69 Risk-Informed Categorization and Treatment SSC Resident Baseline: 71111 as appropriate (TBD)

  • 71111.13, Maintenance Risk Assessments and Emergent Work Control
  • 71151, Performance Indicator Verification
  • 71152, Problem Identification and Resolution (PI&R)
  • Step 1.A: Evolve/Update OpESS+ as needed.

5

Proposed OpESS+

applicable and flexible to the Risk-Informed SFCP Balanced and graded approach.

Initiatives in place.

50.69 OpESS+ NFPA 805 RICT 6

Near-term Actions - OpESS Obtained preliminary NRC Management endorsement of the WG recommendation (Complete)

Obtain and address Industry and Public Feedback (Ongoing)

Internal Communication/Awareness (Ongoing)

  • Training and Communication with Inspectors (Ongoing)

Finalize OpESS guidance (Ongoing)

Enforcement / Significance Determination Process

  • Initiate Cross Regional Panel Process (Ongoing)
  • Develop Screening Guidance (Ongoing)
  • More-than-Minor/Green Threshold criteria (Ongoing) 7

Long-term Actions - ROP Update Based upon Feedback from OpESS institutionalize changes to ROP (Target 2026-2027)

Update SDP/Enforcement of PCC issues 8

Planned Outreach Efforts Issue publicly available report on insights from Tabletops Continue to engage with public and industry

  • ROP Bi-Monthly public meetings
  • Public workshops
  • Industry meetings/interactions 9

Questions 10