Text
Krishna P. Singh Technology Campus, 1 Holtec Blvd., Camden, NJ 08104 Telephone (856) 797-0900 Fax (856) 797-0909 Document ID: 5021070 Page 1 of 1 March 16, 2023 Ms. Yen Chen, Project Manager Division of Spent Fuel Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 72-1040 Certificate of Compliance (CoC) No. 1040
Subject:
Submittal of Supplemental Information on HI-STORM UMAX Amd 3 - Non-Proprietary Version
Reference:
[1] Holtec Letter 5021069, Submittal of Supplemental Information on HI-STORM UMAX Amd 3, letter to Y. Chen (NRC) from K. Manzione (Holtec) dated March 3, 2023
Dear Ms. Chen:
In Reference [1], Holtec submitted supplemental information on HI-STORM UMAX Amd 3.
This letter provides a non-proprietary version of the RAI responses submitted as attachment 1 to the previous letter If you have any questions, please contact me at (856)-797-0900 ext. 3951.
Sincerely, Kimberly Manzione Director of Licensing - NMSS Projects Holtec International Attachments : HI-STORM UMAX Amendment 3 Supplemental Responses (Non-Proprietary)