2023 Region 2 Exercise - Program Inspection RFI Letter Responses, Rev. 1
ML23074A172
Person / Time
Issue date: 11/15/2022
From: Jacqwan Walker
Division of Reactor Safety II
To:
Shared Package
ML23074A171 List:
References
Download: ML23074A172 (1)


Text

From: Jacqwan Walker To: marcus.hofmann@dominionenergy.com; robert.williamson@dominionenergy.com; adina.k.lafrance@dominionenergy.com; Mark.DeWire@duke-energy.com; Mandy.Hare@duke-energy.com; Matthew.Nelson@duke-energy.com; William.Gunter@duke-energy.com; Celeste.Ceva@duke-energy.com; David.Wilson2@duke-energy.com; David.Hall3@duke-energy.com; Peter.Polfleit@fpl.com; Cynthia.Cashwell@fpl.com; JMPERKIN@southernco.com; bdwilken@southernco.com; DPUNKEBE@southernco.com; bftidwell@tva.gov; pmgain@tva.gov; mrwhite@tva.gov Cc: Steven Sanchez; James.e.collins@dominionenergy.com; David.Thompson4@Duke-Energy.com; Eric.White@Duke-Energy.com; Geoff.Pihl@Duke-Energy.com; rkbrown@southernco.com; RGCOLLIN@southernco.com; whlee@tva.gov; jmparshall@tva.gov; japerrel@tva.gov; jcwatso0@tva.gov; jrsowa@tva.gov; acmcneil@tva.gov; jtjohnson0@tva.gov; Eugene Guthrie

Subject:

2023 Region 2 Exercise & Program Inspection RFI Letters Date: Tuesday, November 15, 2022 8:45:00 AM Attachments: Region 2 RFI - 2023 Exercise Inspections - Rev1.docx Region 2 RFI - 2023 Program Inspections - Rev1.docx

Good Morning, Please see the attached request for information (RFI) letters. There have been a few minor revisions to hopefully improve clarity. The majority of the RFI looks similar to the previous RFI format - introductory page, a table (Attachment 1) listing each sites inspection date respectively, and the requested information (Attachment 2) for the type of inspection.

Heres what we need from each Site EP Manager:

1. Review the attached RFI; noting the schedule information in Attachment 1 for your respective site(s) and the requested inspection documents in Attachment 2.
2. Reply back to this email (do not reply all) with confirmation, stating that you have received the RFI request. If necessary, note any potential changes to the schedule information for your respective site.
3. Please share (as necessary) with your internal EP and licensing staff.

RFIs will continue to come at the end of each calendar year (ahead of the following year),

describing the proposed inspections, the dates of the inspections, and requested information.

If you have any questions please dont hesitate to contact Steve Sanchez (404) 997-4418; Steven.Sanchez@nrc.gov.

Jacqwan

From: Thomas, Jeff To: Jacqwan Walker Cc: Thompson, David A; Sanders, Jeff D; Ceva, Celeste Marie

Subject:

[External_Sender] RE: 2023 Region 2 Exercise & Program Inspection RFI Letters Date: Friday, February 10, 2023 9:03:34 AM

Jacqwan,

McGuire received both RFI letters. The inspection dates in the RFI Letter that includes McGuire in are consistent with the most recent IP 22 inspection plan (i.e., 8/21-25/23).

Jeff Thomas Regulatory Affairs McGuire Nuclear Station; Duke Energy Carolinas 980-875-4499 (Office) jeff.thomas@duke-energy.com

From: Jacqwan Walker < Jacqwan.Walker@nrc.gov>

Sent: Tuesday, November 15, 2022 8:45 AM To:marcus.hofmann@dominionenergy.com ; robert.williamson@dominionenergy.com ;

adina.k.lafrance@dominionenergy.com; DeWire, Mark R <Mark.DeWire@duke-energy.com>; Hare, Mandy Bailey <Mandy.Hare@duke-energy.com>; Nelson, Matthew Lee <Matthew.Nelson@duke-energy.com>; Gunter, William D <William.Gunter@duke-energy.com>; Ceva, Celeste Marie

<Celeste.Ceva@duke-energy.com >; Wilson, David A <David.Wilson2@duke-energy.com>; Hall, David Shawn <David.Hall3@duke-energy.com>; Peter.Polfleit@fpl.com ; Cynthia.Cashwell@fpl.com ;

JMPERKIN@southernco.com; bdwilken@southernco.com ; DPUNKEBE@southernco.com ;

bftidwell@tva.gov; pmgain@tva.gov ; mrwhite@tva.gov Cc: Sanchez, Steven P -nrc <Steven.Sanchez@nrc.gov>; James.e.collins@dominionenergy.com ;

Thompson, David A <David.Thompson4@duke-energy.com>; White, Eric <Eric.White@duke-energy.com>; Pihl, Geoff <Geoff.Pihl@duke-energy.com>; rkbrown@southernco.com ;

RGCOLLIN@southernco.com; whlee@tva.gov ; jmparshall@tva.gov ; japerrel@tva.gov ;

jcwatso0@tva.gov; jrsowa@tva.gov ; acmcneil@tva.gov ; jtjohnson0@tva.gov ; Guthrie, Eugene F -nrc

<Eugene.Guthrie@nrc.gov >

Subject:

[EXTERNAL] 2023 Region 2 Exercise & Program Inspection RFI Letters

      • CAUTION! EXTERNAL SENDER *** STOP. ASSESS. VERIFY!! Were you expecting this email? Are grammar and spelling correct? Does the content make sense? Can you verify the sender? If suspicious report it, then do not click links, open attachments or enter your ID or password.

Good Morning, Please see the attached request for information (RFI) letters. There have been a few minor revisions to hopefully improve clarity. The majority of the RFI looks similar to the previous RFI format - introductory page, a table (Attachment 1) listing each sites inspection date respectively, and the requested information (Attachment 2) for the type of inspection.

From: Tidwell, Bradley F To: Jacqwan Walker

Subject:

[External_Sender] Re: 2022 Region 2 Exercise & Program Inspection RFI Letters Date: Friday, February 3, 2023 11:32:03 PM Attachments: image001.png

Browns Ferry has received the RFI.

R

Brad Tidwell Browns Ferry Nuclear Plant EP Manager (256) 522-3663

Get Outlook for iOS

From: Walker, Jacqwan <Jacqwan.Walker@nrc.gov>

Sent: Monday, January 3, 2022 10:13:21 AM To: Tidwell, Bradley F <bftidwell@tva.gov>

Subject:

RE: RE: 2022 Region 2 Exercise & Program Inspection RFI Letters

This is an EXTERNAL EMAIL from outside TVA. THINK BEFORE you CLICK links or OPEN attachments. If suspicious, please click the Report Phishing button located on the Outlook Toolbar at the top of your screen.

Ok, thanks

From: Tidwell, Bradley F <bftidwell@tva.gov>

Sent: Monday, January 03, 2022 8:07 AM To: Walker, Jacqwan <Jacqwan.Walker@nrc.gov>

Subject:

[External_Sender] RE: 2022 Region 2 Exercise & Program Inspection RFI Letters

Jacqwan,

Sorry for the delay but Browns Ferry has received our RFI. No issues.

R

Brad Tidwell

Manager, Emergency Preparedness Browns Ferry Nuclear Plant

W. 256-729-3666 M. 256-566-6792 E.bftidwell@tva.gov Browns Ferry Nuclear Plant, PO Box 2000 (NAB 1E-BFN), Decatur, AL 35609

From: Nelson, Matthew Lee To: Jacqwan Walker

Subject:

[External_Sender] RE: [EXTERNAL] 2023 Region 2 Exercise & Program Inspection RFI Letters Date: Tuesday, November 15, 2022 9:38:51 AM

I confirm receipt. Also forwarded to others as necessary.

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Tuesday, November 15, 2022 8:45 AM To: marcus.hofmann@dominionenergy.com; robert.williamson@dominionenergy.com; adina.k.lafrance@dominionenergy.com; DeWire, Mark R <Mark.DeWire@duke-energy.com>; Hare, Mandy Bailey <Mandy.Hare@duke-energy.com>; Nelson, Matthew Lee <Matthew.Nelson@duke-energy.com>; Gunter, William D <William.Gunter@duke-energy.com>; Ceva, Celeste Marie

<Celeste.Ceva@duke-energy.com>; Wilson, David A <David.Wilson2@duke-energy.com>; Hall, David Shawn <David.Hall3@duke-energy.com>; Peter.Polfleit@fpl.com; Cynthia.Cashwell@fpl.com; JMPERKIN@southernco.com; bdwilken@southernco.com; DPUNKEBE@southernco.com; bftidwell@tva.gov; pmgain@tva.gov; mrwhite@tva.gov Cc: Sanchez, Steven P -nrc <Steven.Sanchez@nrc.gov>; James.e.collins@dominionenergy.com; Thompson, David A <David.Thompson4@duke-energy.com>; White, Eric <Eric.White@duke-energy.com>; Pihl, Geoff <Geoff.Pihl@duke-energy.com>; rkbrown@southernco.com; RGCOLLIN@southernco.com; whlee@tva.gov; jmparshall@tva.gov; japerrel@tva.gov; jcwatso0@tva.gov; jrsowa@tva.gov; acmcneil@tva.gov; jtjohnson0@tva.gov; Guthrie, Eugene F -nrc

<Eugene.Guthrie@nrc.gov>

Subject:

[EXTERNAL] 2023 Region 2 Exercise & Program Inspection RFI Letters

      • CAUTION! EXTERNAL SENDER *** STOP. ASSESS. VERIFY!! Were you expecting this email? Are grammar and spelling correct? Does the content make sense? Can you verify the sender? If suspicious report it, then do not click links, open attachments or enter your ID or password.

Good Morning, Please see the attached request for information (RFI) letters. There have been a few minor revisions to hopefully improve clarity. The majority of the RFI looks similar to the previous RFI format - introductory page, a table (Attachment 1) listing each sites inspection date respectively, and the requested information (Attachment 2) for the type of inspection.

Heres what we need from each Site EP Manager:

1. Review the attached RFI; noting the schedule information in Attachment 1 for your respective site(s) and the requested inspection documents in Attachment 2.
2. Reply back to this email (do not reply all) with confirmation, stating that you have received the RFI request. If necessary, note any potential changes to the schedule information for your respective site.
3. Please share (as necessary) with your internal EP and licensing staff.

RFIs will continue to come at the end of each calendar year (ahead of the following year),

describing the proposed inspections, the dates of the inspections, and requested From: Perkins, John M.

To: Jacqwan Walker; Wilkens, Bryce David; Punke-Bendt, Doug Cc: Collings, Ricky G.; Brown, R. Keith

Subject:

[External_Sender] RE: 2023 RFI Memos Date: Friday, February 3, 2023 12:37:47 PM

Yes we have received

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Friday, February 3, 2023 11:14 AM To: Perkins, John M. <JMPERKIN@southernco.com>; Wilkens, Bryce David

<BDWILKEN@SOUTHERNCO.COM>; Punke-Bendt, Doug <DPUNKEBE@SOUTHERNCO.COM>

Cc: Collings, Ricky G. <RGCOLLIN@southernco.com>; Brown, R. Keith <RKBROWN@southernco.com>

Subject:

2023 RFI Memos

EXTERNAL MAIL: Caution Opening Links or Files

Hello, Have you received the 2023 RFI memo? If so, can you please confirm receipt by replying to the original email?

Thanks!

Jacqwan From: Gunter, William D To: Jacqwan Walker

Subject:

[External_Sender] RE: 2023 Region 2 Exercise & Program Inspection RFI Letters Date: Monday, February 6, 2023 9:08:01 AM

I have received the email and the RFI documents. The dates for HNP appear correct. I have forwarded the information request to our reg affairs dept.

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Tuesday, November 15, 2022 8:45 AM To: marcus.hofmann@dominionenergy.com; robert.williamson@dominionenergy.com; adina.k.lafrance@dominionenergy.com; DeWire, Mark R <Mark.DeWire@duke-energy.com>; Hare, Mandy Bailey <Mandy.Hare@duke-energy.com>; Nelson, Matthew Lee <Matthew.Nelson@duke-energy.com>; Gunter, William D <William.Gunter@duke-energy.com>; Ceva, Celeste Marie

<Celeste.Ceva@duke-energy.com>; Wilson, David A <David.Wilson2@duke-energy.com>; Hall, David Shawn <David.Hall3@duke-energy.com>; Peter.Polfleit@fpl.com; Cynthia.Cashwell@fpl.com; JMPERKIN@southernco.com; bdwilken@southernco.com; DPUNKEBE@southernco.com; bftidwell@tva.gov; pmgain@tva.gov; mrwhite@tva.gov Cc: Sanchez, Steven P -nrc <Steven.Sanchez@nrc.gov>; James.e.collins@dominionenergy.com; Thompson, David A <David.Thompson4@duke-energy.com>; White, Eric <Eric.White@duke-energy.com>; Pihl, Geoff <Geoff.Pihl@duke-energy.com>; rkbrown@southernco.com; RGCOLLIN@southernco.com; whlee@tva.gov; jmparshall@tva.gov; japerrel@tva.gov; jcwatso0@tva.gov; jrsowa@tva.gov; acmcneil@tva.gov; jtjohnson0@tva.gov; Guthrie, Eugene F -nrc

<Eugene.Guthrie@nrc.gov>

Subject:

2023 Region 2 Exercise & Program Inspection RFI Letters

Good Morning, Please see the attached request for information (RFI) letters. There have been a few minor revisions to hopefully improve clarity. The majority of the RFI looks similar to the previous RFI format - introductory page, a table (Attachment 1) listing each sites inspection date respectively, and the requested information (Attachment 2) for the type of inspection.

Heres what we need from each Site EP Manager:

1. Review the attached RFI; noting the schedule information in Attachment 1 for your respective site(s) and the requested inspection documents in Attachment 2.
2. Reply back to this email (do not reply all) with confirmation, stating that you have received the RFI request. If necessary, note any potential changes to the schedule information for your respective site.
3. Please share (as necessary) with your internal EP and licensing staff.

RFIs will continue to come at the end of each calendar year (ahead of the following year),

describing the proposed inspections, the dates of the inspections, and requested information.

If you have any questions please dont hesitate to contact Steve Sanchez (404) 997-4418; Steven.Sanchez@nrc.gov.

From: Wilkens, Bryce David To: Jacqwan Walker Cc: Brown, R. Keith; Warren, Marvin Key; Long, Keith D.; Collins, Carl James

Subject:

[External_Sender] RE: 2023 Region 2 Exercise & Program Inspection RFI Letters Date: Friday, February 3, 2023 12:21:52 PM

I received the RFI request for Hatch.

Bryce Wilkens Supervisor, Emergency Preparedness Hatch

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Tuesday, November 15, 2022 8:45 AM To: marcus.hofmann@dominionenergy.com; robert.williamson@dominionenergy.com; adina.k.lafrance@dominionenergy.com; Mark.DeWire@duke-energy.com; Mandy.Hare

<Mandy.Hare@duke-energy.com>; Matthew.Nelson@duke-energy.com; William.Gunter@duke-energy.com; Celeste.Ceva@duke-energy.com; David.Wilson2@duke-energy.com; David.Hall3@duke-energy.com; Peter.Polfleit@fpl.com; Cynthia.Cashwell@fpl.com; Perkins, John M.

<JMPERKIN@southernco.com>; Wilkens, Bryce David <BDWILKEN@SOUTHERNCO.COM>; Punke-Bendt, Doug <DPUNKEBE@SOUTHERNCO.COM>; bftidwell@tva.gov; pmgain@tva.gov; mrwhite@tva.gov Cc: Sanchez, Steven <Steven.Sanchez@nrc.gov>; James.e.collins@dominionenergy.com; David.Thompson4@Duke-Energy.com; White, Eric <eric.white@duke-energy.com>;

Geoff.Pihl@Duke-Energy.com; Brown, R. Keith <RKBROWN@southernco.com>; Collings, Ricky G.

<RGCOLLIN@southernco.com>; whlee@tva.gov; jmparshall@tva.gov; japerrel@tva.gov; jcwatso0@tva.gov; jrsowa@tva.gov; acmcneil@tva.gov; jtjohnson0 <jtjohnson0@tva.gov>; Eugene Guthrie <Eugene.Guthrie@nrc.gov>

Subject:

2023 Region 2 Exercise & Program Inspection RFI Letters

Good Morning, Please see the attached request for information (RFI) letters. There have been a few minor revisions to hopefully improve clarity. The majority of the RFI looks similar to the previous RFI format - introductory page, a table (Attachment 1) listing each sites inspection date respectively, and the requested information (Attachment 2) for the type of inspection.

Heres what we need from each Site EP Manager:

1. Review the attached RFI; noting the schedule information in Attachment 1 for your respective site(s) and the requested inspection documents in Attachment 2.
2. Reply back to this email (do not reply all) with confirmation, stating that you have received the RFI request. If necessary, note any potential changes to the schedule information for your respective site.
3. Please share (as necessary) with your internal EP and licensing staff.

RFIs will continue to come at the end of each calendar year (ahead of the following year),

describing the proposed inspections, the dates of the inspections, and requested From: marcus.hofmann@dominionenergy.com To: Jacqwan Walker Cc: shayla.m.ripley@dominionenergy.com; jonathan.s.seward@dominionenergy.com

Subject:

[External_Sender] RE: 2023 Region 2 Exercise & Program Inspection RFI Letters Date: Thursday, November 17, 2022 11:41:51 AM Attachments: image001.png

Jacqwan, This is Marc Hofmann at North Anna.

I have received the RFI request.

No changes are necessary.

This information has been shared with staff.

Wishing you a Happy Thanksgiving.

Marc

Marc A. Hofmann, PE Manager - Emergency Preparedness and Licensing North Anna Power Station

Dominion Energy Phone: 540-894-2100; Internal: 8-794-2100

E-mail: marcus.hofmann@dominionenergy.com

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Tuesday, November 15, 2022 8:45 AM To: Marcus Hofmann (DEV Generation - 3) <marcus.hofmann@dominionenergy.com>; Robert Williamson (DESC Generation - 8) <robert.williamson@dominionenergy.com>; Adina K Lafrance (DEV Generation - 3) <adina.k.lafrance@dominionenergy.com>; Mark.DeWire@duke-energy.com; Mandy.Hare@duke-energy.com; Matthew.Nelson@duke-energy.com; William.Gunter@duke-energy.com; Celeste.Ceva@duke-energy.com; David.Wilson2@duke-energy.com; David.Hall3@duke-energy.com; Peter.Polfleit@fpl.com; Cynthia.Cashwell@fpl.com; JMPERKIN@southernco.com; bdwilken@southernco.com; DPUNKEBE@southernco.com; bftidwell@tva.gov; pmgain@tva.gov; mrwhite@tva.gov Cc: Steven Sanchez <Steven.Sanchez@nrc.gov>; James E Collins (Services - 6)

<James.e.collins@dominionenergy.com>; David.Thompson4@Duke-Energy.com; Eric.White@Duke-Energy.com; Geoff.Pihl@Duke-Energy.com; rkbrown@southernco.com; RGCOLLIN@southernco.com; whlee@tva.gov; jmparshall@tva.gov; japerrel@tva.gov; jcwatso0@tva.gov; jrsowa@tva.gov; acmcneil@tva.gov; jtjohnson0@tva.gov; Eugene Guthrie

<Eugene.Guthrie@nrc.gov>

Subject:

[EXTERNAL] 2023 Region 2 Exercise & Program Inspection RFI Letters

CAUTION! This message was NOT SENT from DOMINION ENERGY Are you expecting this message to your DE email? Suspicious? Use PhishAlarm to report the message. Open a From: Wilson, David A To: Jacqwan Walker

Subject:

[External_Sender] RE: [EXTERNAL] 2023 Region 2 Exercise & Program Inspection RFI Letters Date: Tuesday, January 10, 2023 1:55:13 PM

Apologies for the late acknowledgement of this email. I saw it come in when you sent it out but failed to respond.

Oconee Nuclear Station has received the request and there are no challenges with responding.

David A. Wilson, PE Nuclear Station Support Services Manager Oconee Nuclear Station (864)-873-3451

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Tuesday, November 15, 2022 8:45 AM To: marcus.hofmann@dominionenergy.com; robert.williamson@dominionenergy.com; adina.k.lafrance@dominionenergy.com; DeWire, Mark R <Mark.DeWire@duke-energy.com>; Hare, Mandy Bailey <Mandy.Hare@duke-energy.com>; Nelson, Matthew Lee <Matthew.Nelson@duke-energy.com>; Gunter, William D <William.Gunter@duke-energy.com>; Ceva, Celeste Marie

<Celeste.Ceva@duke-energy.com>; Wilson, David A <David.Wilson2@duke-energy.com>; Hall, David Shawn <David.Hall3@duke-energy.com>; Peter.Polfleit@fpl.com; Cynthia.Cashwell@fpl.com; JMPERKIN@southernco.com; bdwilken@southernco.com; DPUNKEBE@southernco.com; bftidwell@tva.gov; pmgain@tva.gov; mrwhite@tva.gov Cc: Sanchez, Steven P -nrc <Steven.Sanchez@nrc.gov>; James.e.collins@dominionenergy.com; Thompson, David A <David.Thompson4@duke-energy.com>; White, Eric <Eric.White@duke-energy.com>; Pihl, Geoff <Geoff.Pihl@duke-energy.com>; rkbrown@southernco.com; RGCOLLIN@southernco.com; whlee@tva.gov; jmparshall@tva.gov; japerrel@tva.gov; jcwatso0@tva.gov; jrsowa@tva.gov; acmcneil@tva.gov; jtjohnson0@tva.gov; Guthrie, Eugene F -nrc

<Eugene.Guthrie@nrc.gov>

Subject:

[EXTERNAL] 2023 Region 2 Exercise & Program Inspection RFI Letters

      • CAUTION! EXTERNAL SENDER *** STOP. ASSESS. VERIFY!! Were you expecting this email? Are grammar and spelling correct? Does the content make sense? Can you verify the sender? If suspicious report it, then do not click links, open attachments or enter your ID or password.

Good Morning, Please see the attached request for information (RFI) letters. There have been a few minor revisions to hopefully improve clarity. The majority of the RFI looks similar to the previous RFI format - introductory page, a table (Attachment 1) listing each sites inspection date respectively, and the requested information (Attachment 2) for the type of inspection.

Heres what we need from each Site EP Manager:

1. Review the attached RFI; noting the schedule information in Attachment 1 for your respective site(s) and the requested inspection documents in Attachment From: Polfleit, Peter To: Jacqwan Walker

Subject:

[External_Sender] RE: 2023 Region 2 Exercise & Program Inspection RFI Letters Date: Monday, November 21, 2022 12:01:13 PM

I have received the RFI request and have no comments or concerns.

Peter Polfleit St Lucie Nuclear Site Office: 772-467-4478

Florida Power & Light

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Tuesday, November 15, 2022 8:45 AM To: marcus.hofmann@dominionenergy.com; robert.williamson@dominionenergy.com; adina.k.lafrance@dominionenergy.com; Mark.DeWire@duke-energy.com; Mandy.Hare@duke-energy.com; Matthew.Nelson@duke-energy.com; William.Gunter@duke-energy.com; Celeste.Ceva@duke-energy.com; David.Wilson2@duke-energy.com; David.Hall3@duke-energy.com; Polfleit, Peter <Peter.Polfleit@fpl.com>; Cashwell, Cynthia <Cynthia.Cashwell@fpl.com>;

JMPERKIN@southernco.com; bdwilken@southernco.com; DPUNKEBE@southernco.com; bftidwell@tva.gov; pmgain@tva.gov; mrwhite@tva.gov Cc: Steven Sanchez <Steven.Sanchez@nrc.gov>; James.e.collins@dominionenergy.com; David.Thompson4@Duke-Energy.com; Eric.White@Duke-Energy.com; Geoff.Pihl@Duke-Energy.com; rkbrown@southernco.com; RGCOLLIN@southernco.com; whlee@tva.gov; jmparshall@tva.gov; japerrel@tva.gov; jcwatso0@tva.gov; jrsowa@tva.gov; acmcneil@tva.gov; jtjohnson0@tva.gov; Eugene Guthrie <Eugene.Guthrie@nrc.gov>

Subject:

2023 Region 2 Exercise & Program Inspection RFI Letters

Good Morning, Please see the attached request for information (RFI) letters. There have been a few minor revisions to hopefully improve clarity. The majority of the RFI looks similar to the previous RFI format - introductory page, a table (Attachment 1) listing each sites inspection date respectively, and the requested information (Attachment 2) for the type of inspection.

Heres what we need from each Site EP Manager:

1. Review the attached RFI; noting the schedule information in Attachment 1 for your respective site(s) and the requested inspection documents in Attachment 2.
2. Reply back to this email (do not reply all) with confirmation, stating that you have received the RFI request. If necessary, note any potential changes to the schedule information for your respective site.
3. Please share (as necessary) with your internal EP and licensing staff.

From: ROBERT WILLIAMSON To: Jacqwan Walker

Subject:

[External_Sender] RE: 2023 Region 2 Exercise & Program Inspection RFI Letters Date: Tuesday, November 15, 2022 11:12:08 AM

Jacqwan,

I confirm receipt of the RFI request.

Thanks, Bob Williamson Manager-Nuclear Emergency Preparedness VC Summer Nuclear Station 803-345-4464 (office)

robert.williamson@dominionenergy.com

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Tuesday, November 15, 2022 8:45 AM To: Marcus Hofmann (DEV Generation - 3) <marcus.hofmann@dominionenergy.com>; Robert Williamson (DESC Generation - 8) <robert.williamson@dominionenergy.com>; Adina K Lafrance (DEV Generation - 3) <adina.k.lafrance@dominionenergy.com>; Mark.DeWire@duke-energy.com; Mandy.Hare@duke-energy.com; Matthew.Nelson@duke-energy.com; William.Gunter@duke-energy.com; Celeste.Ceva@duke-energy.com; David.Wilson2@duke-energy.com; David.Hall3@duke-energy.com; Peter.Polfleit@fpl.com; Cynthia.Cashwell@fpl.com; JMPERKIN@southernco.com; bdwilken@southernco.com; DPUNKEBE@southernco.com; bftidwell@tva.gov; pmgain@tva.gov; mrwhite@tva.gov Cc: Steven Sanchez <Steven.Sanchez@nrc.gov>; James E Collins (Services - 6)

<James.e.collins@dominionenergy.com>; David.Thompson4@Duke-Energy.com; Eric.White@Duke-Energy.com; Geoff.Pihl@Duke-Energy.com; rkbrown@southernco.com; RGCOLLIN@southernco.com; whlee@tva.gov; jmparshall@tva.gov; japerrel@tva.gov; jcwatso0@tva.gov; jrsowa@tva.gov; acmcneil@tva.gov; jtjohnson0@tva.gov; Eugene Guthrie

<Eugene.Guthrie@nrc.gov>

Subject:

[EXTERNAL] 2023 Region 2 Exercise & Program Inspection RFI Letters

CAUTION! This message was NOT SENT from DOMINION ENERGY Are you expecting this message to your DE email? Suspicious? Use PhishAlarm to report the message. Open a browser and type in the name of the trusted website instead of clicking on links. DO NOT click links or open attachments until you verify with the sender using a known-good phone number. Never provide your DE password.

From: Krista.L.Longston@dominionenergy.com To: Jacqwan Walker; Steven Sanchez Cc: adina.k.lafrance@dominionenergy.com

Subject:

[External_Sender] FW: 2023 Region 2 Exercise & Program Inspection RFI Letters Date: Monday, November 21, 2022 6:24:18 PM

July 18th is the Graded Exercise for Surry. Verified the dates listed on RFI are good.

Hope you all have a Happy Thanksgiving.

Krista

From: Jacqwan Walker < Jacqwan.Walker@nrc.gov>

Sent: Tuesday, November 15, 2022 8:50 AM To: Marcus Hofmann (DEV Generation - 3) < marcus.hofmann@dominionenergy.com>; Robert Williamson (DESC Generation - 8) <robert.williamson@dominionenergy.com>; Adina K Lafrance (DEV Generation - 3) <adina.k.lafrance@dominionenergy.com>; Mark.DeWire@duke-energy.com

<Mark.DeWire@duke-energy.com >; Mandy.Hare@duke-energy.com <Mandy.Hare@duke-energy.com>; Matthew.Nelson@duke-energy.com <Matthew.Nelson@duke-energy.com >;

William.Gunter@duke-energy.com <William.Gunter@duke-energy.com >; Celeste.Ceva@duke-energy.com <Celeste.Ceva@duke-energy.com >; David.Wilson2@duke-energy.com

<David.Wilson2@duke-energy.com >; David.Hall3@duke-energy.com <David.Hall3@duke-energy.com>; Peter.Polfleit@fpl.com <Peter.Polfleit@fpl.com >; Cynthia.Cashwell@fpl.com

<Cynthia.Cashwell@fpl.com >; JMPERKIN@southernco.com <JMPERKIN@southernco.com >;

bdwilken@southernco.com <bdwilken@southernco.com >; DPUNKEBE@southernco.com

<DPUNKEBE@southernco.com >; bftidwell@tva.gov <bftidwell@tva.gov >; pmgain@tva.gov

<pmgain@tva.gov >; mrwhite@tva.gov <mrwhite@tva.gov >

Cc: Steven Sanchez <Steven.Sanchez@nrc.gov>; James E Collins (Services - 6)

<James.e.collins@dominionenergy.com >; David.Thompson4@Duke-Energy.com

<David.Thompson4@Duke-Energy.com >; Eric.White@Duke-Energy.com <Eric.White@Duke-Energy.com>; Geoff.Pihl@Duke-Energy.com <Geoff.Pihl@Duke-Energy.com >;

rkbrown@southernco.com <rkbrown@southernco.com >; RGCOLLIN@southernco.com

<RGCOLLIN@southernco.com >; whlee@tva.gov <whlee@tva.gov >; jmparshall@tva.gov

<jmparshall@tva.gov >; japerrel@tva.gov <japerrel@tva.gov >; jcwatso0@tva.gov

<jcwatso0@tva.gov >; jrsowa@tva.gov <jrsowa@tva.gov >; acmcneil@tva.gov <acmcneil@tva.gov >;

jtjohnson0@tva.gov <jtjohnson0@tva.gov >; Eugene Guthrie <Eugene.Guthrie@nrc.gov>

Subject:

[EXTERNAL] 2023 Region 2 Exercise & Program Inspection RFI Letters

CAUTION! This message was NOT SENT from DOMINION ENERGY Are you expecting this message to your DE email? Suspicious? Use PhishAlarm to report the message. Open a browser and type in the name of the trusted website instead of clicking on links. DO NOT click links or open From: Cashwell, Cynthia To: Jacqwan Walker Cc: Steven Sanchez

Subject:

[External_Sender] RE: 2023 Region 2 Exercise & Program Inspection RFI Letters Date: Wednesday, November 16, 2022 5:55:39 PM

Jacqwan -

I have received the RFI request. Thank you for the update.

Thank you Cynthia

Cynthia Cashwell Regulatory Affairs Manager Turkey Point Nuclear Station

Office-305-246-1631 Cynthia.Cashwell@FPL.com Florida Power & Light

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Wednesday, November 16, 2022 2:24 PM To: Cashwell, Cynthia <Cynthia.Cashwell@fpl.com>

Cc: Steven Sanchez <Steven.Sanchez@nrc.gov>

Subject:

FW: 2023 Region 2 Exercise & Program Inspection RFI Letters

Hello, Please see the revised Exercise Inspection RFI (the Program Inspection RFI is the same from the original email). It has been updated to include the HAB inspection procedure (71114.07) where/when applicable - like for Turkey Point next year.

Note: I left the track changes on to help with quickly finding the changes.

Jacqwan

From: Jacqwan Walker Sent: Tuesday, November 15, 2022 8:45 AM To:marcus.hofmann@dominionenergy.com ; robert.williamson@dominionenergy.com ;

adina.k.lafrance@dominionenergy.com; Mark.DeWire@duke-energy.com ; Mandy.Hare@duke-energy.com; Matthew.Nelson@duke-energy.com ; William.Gunter@duke-energy.com ;

Celeste.Ceva@duke-energy.com; David.Wilson2@duke-energy.com ; David.Hall3@duke-energy.com ;

From: Punke-Bendt, Doug To: Jacqwan Walker; Perkins, John M.; Wilkens, Bryce David Cc: Collings, Ricky G.; Brown, R. Keith

Subject:

[External_Sender] RE: 2023 RFI Memos Date: Thursday, February 9, 2023 11:58:31 AM

Received

Doug Punke-Bendt Vogtle 1-4 EP Supervisor Office: 706-848-5596

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Friday, February 3, 2023 12:14 PM To: Perkins, John M. <JMPERKIN@southernco.com>; Wilkens, Bryce David

<BDWILKEN@SOUTHERNCO.COM>; Punke-Bendt, Doug <DPUNKEBE@SOUTHERNCO.COM>

Cc: Collings, Ricky G. <RGCOLLIN@southernco.com>; Brown, R. Keith <RKBROWN@southernco.com>

Subject:

2023 RFI Memos

EXTERNAL MAIL: Caution Opening Links or Files

Hello, Have you received the 2023 RFI memo? If so, can you please confirm receipt by replying to the original email?

Thanks!

Jacqwan From: White, Michael R To: Jacqwan Walker Cc: Johnson, Jonathan Thornton

Subject:

[External_Sender] RE: 2023 Region 2 Exercise & Program Inspection RFI Letters Date: Tuesday, November 15, 2022 8:55:20 AM

Jacqwan,

I have received the RFI and concur with the scheduled dates for Watts Bar Nuclear plant

Mike White EP Manager Watts Bar Nuclear Plant

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Tuesday, November 15, 2022 8:45 AM To: marcus.hofmann@dominionenergy.com; robert.williamson@dominionenergy.com; adina.k.lafrance@dominionenergy.com; Mark.DeWire@duke-energy.com; Mandy.Hare@duke-energy.com; Matthew.Nelson@duke-energy.com; William.Gunter@duke-energy.com; Celeste.Ceva@duke-energy.com; David.Wilson2@duke-energy.com; David.Hall3@duke-energy.com; Peter.Polfleit@fpl.com; Cynthia.Cashwell@fpl.com; JMPERKIN@southernco.com; bdwilken@southernco.com; DPUNKEBE@southernco.com; Tidwell, Bradley F <bftidwell@tva.gov>;

Gain, Paul M Jr <pmgain@tva.gov>; White, Michael R <mrwhite@tva.gov>

Cc: Sanchez, Steven <Steven.Sanchez@nrc.gov>; James.e.collins@dominionenergy.com; David.Thompson4@Duke-Energy.com; Eric.White@Duke-Energy.com; Geoff.Pihl@Duke-Energy.com; rkbrown@southernco.com; RGCOLLIN@southernco.com; Lee, Walter Hugh III

<whlee@tva.gov>; Parshall, John M <jmparshall@tva.gov>; Perrel, Joshua A <japerrel@tva.gov>;

Watson, James Christipher Jr <jcwatso0@tva.gov>; Sowa, Jeffrey R <jrsowa@tva.gov>; McNeil, Andrew Clair <acmcneil@tva.gov>; Johnson, Jonathan Thornton <jtjohnson0@tva.gov>; Eugene Guthrie <Eugene.Guthrie@nrc.gov>

Subject:

2023 Region 2 Exercise & Program Inspection RFI Letters

This is an EXTERNAL EMAIL from outside TVA. THINK BEFORE you CLICK links or OPEN attachments. If suspicious, please click the Report Phishing button located on the Outlook Toolbar at the top of your screen.

Good Morning, Please see the attached request for information (RFI) letters. There have been a few minor revisions to hopefully improve clarity. The majority of the RFI looks similar to the previous RFI format - introductory page, a table (Attachment 1) listing each sites inspection date respectively, and the requested information (Attachment 2) for the type of inspection.

Heres what we need from each Site EP Manager:

1. Review the attached RFI; noting the schedule information in Attachment 1 for your respective site(s) and the requested inspection documents in Attachment 2.
2. Reply back to this email (do not reply all) with confirmation, stating that you have received the RFI request. If necessary, note any potential changes to the From: Gain, Paul M Jr To: Jacqwan Walker

Subject:

[External_Sender] RE: 2023 RFI Memos Date: Monday, March 13, 2023 5:35:01 PM

Yes we have received the RFI letter

From: Jacqwan Walker <Jacqwan.Walker@nrc.gov>

Sent: Friday, February 3, 2023 12:13 PM To: Tidwell, Bradley F <bftidwell@tva.gov>; Gain, Paul M Jr <pmgain@tva.gov>

Subject:

2023 RFI Memos

This is an EXTERNAL EMAIL from outside TVA. THINK BEFORE you CLICK links or OPEN attachments. If suspicious, please click the Report Phishing button located on the Outlook Toolbar at the top of your screen.

Hello, Have you received the 2023 RFI memo? If so, can you please confirm receipt by replying to the original email?

Thanks!

Jacqwan From: Tunnell, Bruce Nathaniel To: Jacqwan Walker

Subject:

[External_Sender] 2023 RFI Confirmation Date: Friday, February 10, 2023 8:32:53 AM

This is confirmation that Robinson Nuclear Plant (RNP) has received the Emergency Preparedness Exercise Inspection Request for Information, and RNPs dates of Inspection are from May 15-19, 2023.