Notification of Readiness for NRC 95001 Inspection
ML23059A389
Person / Time
Site: Peach Bottom Constellation icon.png
Issue date: 02/28/2023
From: Henry D
Constellation Energy Generation
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
EA-22-071, CCN 23-27
Download: ML23059A389 (1)


Text

EA-22-071 CCN 23-27 February 28, 2023 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Peach Bottom Atomic Power Station, Unit 2 Subsequent Renewed Facility Operating License No. DPR-44 NRC Docket No. 50-277

Subject:

Notification of Readiness for NRC 95001 Inspection

References:

1. Letter from Daniel S. Collins (NRC) to David P. Rhoades (Constellation Energy Generation, LLC), Peach Bottom Atomic Power Station, Units 2 and 3 - Integrated Inspection Report 05000277/2022003 and 05000278/2022003 and Preliminary White Finding and Apparent Violation, dated October 27, 2022 (ADAMS Accession No. ML22299A208)
2. Letter from David C. Lew (NRC) to David P. Rhoades (Constellation Energy Generation, LLC), Peach Bottom Atomic Power Station, Unit 2 -

Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000277/2022090, dated November 28, 2022 (ADAMS Accession No. ML22314A098)

In the Reference 1 letter, Constellation Energy Generation, LLC (CEG) was informed of an escalated enforcement action, EA-22-071, associated with a preliminary White finding and apparent violation 05000277/2022003-03, Loss of Reactor Protection System Power and Unit Scram Due to Operator Error. In the Reference 2 letter, the NRC provided a final significance determination of a White finding and notice of violation.

The NRC plans to conduct a supplemental inspection for this finding in accordance with Inspection Procedure 95001, Supplemental Inspection Response to Action Matrix Column 2 (Regulatory Response) Inputs, following CEGs notification of readiness for this inspection. This letter notifies the NRC that Peach Bottom is ready for the supplemental inspection.

There are no new regulatory commitments contained in this letter. If you should have any questions, please contact Mr. Wade Scott, Regulatory Assurance Manager, at 717-456-3047.

U.S. Nuclear Regulatory Commission Notification of Readiness for NRC 95001 Inspection February 28, 2023 Page 2 Respectfully, David A. Henry Site Vice President Peach Bottom Atomic Power Station cc:

USNRC Regional Administrator, Region I USNRC Senior Resident Inspector, PBAPS USNRC Project Manager, PBAPS W. DeHaas, Pennsylvania Bureau of Radiation Protection S. Seaman, State of Maryland