Joint Motion to Close the Hearing Record
ML23053A168
Person / Time
Site: Palisades, Big Rock Point  File:Consumers Energy icon.png
Issue date: 02/22/2023
From: King J, Leidich A, Doris Lewis, Lovett A, Moody M, Tompkins J
Balch & Bingham, LLP, Entergy Nuclear Operations, Entergy Nuclear Palisades, Holtec Decommissioning International, Holtec, Pillsbury, Winthrop, Shaw, Pittman, LLP, State of MI, Dept of Attorney General
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
License Transfer, RAS 56651, 50-255-LT-2, 50-155-LT-2, 72-043-LT-2, ASLBP 22-974-01-LT-BD01, 72-007-LT
Download: ML23053A168 (0)


Text

February 22, 2023

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

Before the Atomic Safety and Licensing Board

In the Matter of )

)

Entergy Nuclear Operations, Inc., )

Entergy Nuclear Palisades, LLC, ) Docket Nos. 50-255-LT-2 Holtec International, and ) 50-155-LT-2 Holtec Decommissioning International, LLC ) 72-007-LT

) 72-043-LT-2 (Palisades Nuclear Plant and )

Big Rock Point Site) ) ASLBP No. 22-974-01-LT-BD01

JOINT MOTION TO CLOSE THE HEARING RECORD

Entergy Nuclear Operations, Inc., Entergy Nuclear Palisades, LLC, Holtec International,

Holtec Decommissioning International, LLC, and the Michigan Attorney General (collectively,

the Parties) request that the Board grant this joint motion to close the hearing record in this

proceeding, subject to finalization of the hearing transcript.

Pursuant to paragraph 9 of the Boards order governing mandatory disclosures,1 the

Parties must continue to supplement their disclosures until the hearing record is closed.

Following conclusion of the in-person hearing on February 9, 2023, the Parties will not submit

any further exhibits or testimony. The Parties also do not anticipate that the Presiding Officer

will need to introduce any further hearing exhibits. Accordingly, the Parties request that the

Board close the hearing record, subject to finalization of the transcript.2

1 Order, Protocols Governing Mandatory Disclosures, 2-3 (Aug. 31, 2022) (Accession No. ML22243A145).

2 Consistent with the Boards direction, the Parties will file an errata sheet to the transcript by February 27, 2023.

17407497.1 Respectfully submitted,

/Executed in accord with § 2.304(d)/ /Signed electronically by Alan Lovett /

Anne R. Leidich Jason B. Tompkins David R. Lewis Alan D. Lovett PILLSBURY WINTHROP SHAW BALCH & BINGHAM LLP PITTMAN LLP 1710 Sixth Avenue North 1200 Seventeenth Street, NW Birmingham, AL 35203-2015 Washington, DC 20036 (205) 226-8743 Telephone: 202-663-8707 (205) 226-8769 anne.leidich@pillsburylaw.com jtompkins@balch.com david.lewis@pillsburylaw.com alovett@balch.com

Counsel for Entergy Nuclear Operations, Inc. Counsel for Holtec International and Holtec and Entergy Nuclear Palisades, LLC Decommissioning International, LLC

/Executed in accord with § 2.304(d)/

Michael Moody Joel King Assistant Attorneys General Michigan Department of Attorney General 525 W. Ottawa St.

Lansing, MI 48906 moodym2@michigan.gov kingj38@michigan.gov

Counsel for Michigan Attorney General Dana Nessel

2 17407497.1 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

Before the Atomic Safety and Licensing Board

In the Matter of )

)

Entergy Nuclear Operations, Inc., )

Entergy Nuclear Palisades, LLC, ) Docket Nos. 50-255-LT-2 Holtec International, and ) 50-155-LT-2 Holtec Decommissioning International, LLC ) 72-007-LT

) 72-043-LT-2 (Palisades Nuclear Plant and )

Big Rock Point Site) ) ASLBP No. 22-974-01-LT-BD01

I hereby certify that the foregoing motion has been served through the E-Filing system on the participants in the above-captioned proceeding this 22nd day of February, 2023.

/signed electronically by Alan Lovett/

Alan D. Lovett Balch & Bingham LLP 1710 Sixth Avenue North Birmingham, AL 35203-2015 Tel. 205-226-8769 Email: alovett@balch.com

Counsel for Holtec International and Holtec Decommissioning International, LLC

3 17407497.1