ML23053A157

From kanterella
Jump to navigation Jump to search
Independent Spent Fuel Storage Installation - Independent Spent Fuel Storage Installation (ISFSI) Annual Effluent Report, January Through December 2022
ML23053A157
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 02/16/2023
From: Borgen T
Northern States Power Company, Minnesota, Xcel Energy Inc
To:
Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation, Document Control Desk
References
L-Pl-23-003
Download: ML23053A157 (1)


Text

Xcel Energy February 16, 2023 ATTN: Document Control Desk Director, Division of Spent Fuel Man agem ent Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Com miss ion Washington, DC 20555-0001 Prairie Island Nuclear Generating Plant, Units 1 and 2 Docket Nos. 50-282 and 50-306 Renewed Facility Operating License Nos. DPR-42 and DPR -60 Prairie Island Independent Spent Fuel Storag e Installation Docket No. 72-10 Materials License No. SNM-2506 1717 Wakonade Drive Welch, MN 55089 L-Pl-23-003 10 CFR 72.44(d)(3)

ISFSI Tech Spec 5.3 Independent Spent Fuel Storage Installation {ISFSI) Annual Effluent Report, January through December 2022 Pursuant to the requirements of 10 CFR 72.44(d)(3) and the Prairie Island Nuclear Generating Plant ISFSI Technical Specifications, Section 5.3, Northern States Power Company, a Minnesota corporation, doing business as Xcel Energy (hereafter "NSPM"),

submits the enclosed ISFSI Annual Effluent Report for the period of January through December 2022.

Document Control Desk L-Pl-23-003 Page2

Summary of Commitments

This letter makes no new commitments and no revisions to existing commitments.

~~

Timothy P. Borgen Plant Manager, Prairie Island Nuclear Generating Plant Northern States Power Company - Minnesota

Enclosure

cc: Administrator, Region Ill, USNRC Project Manager, Prairie Island, USNRC Resident Inspector, Prairie Island, USNRC State of Minnesota, Department of Commerce ENCLOSURE

PRAIRIE ISLAND NUCLEAR GENERA TING PLANT INDEPENDENT SPENT FUEL STORAGE INSTALLATION {ISFSI)

ANNUAL EFFLUENT REPORT, JANUARY 2022 THROUGH DECEMBER 2022

Independent Spent Fuel Storage Installation 50 Total Casks

During the 2022 calendar year, there were three (3) additional casks loaded and placed in the Prairie Island ISFSI. At the end of the 2022 calendar year, there remains a total of fifty (50) casks loaded in the Prairie Island ISFSI.

Airborne Effluent Releases from the ISFSI 0.00E+00 Ci

There was no airborne effluent release from the Prairie Island ISFSI during the calendar year 2022.

Liquid Effluent Releases from the ISFSI 0.00E+00 Ci

There was no liquid effluent release from the Prairie Island ISFSI during the calendar year 2022.

Dose to Individuals Due to ISFSI Effluent Releases 0.00E+00 mrem

Page 1 of 1