REACTOR OPEN ALLEGATIONS BY CY RECEIVED*: January 2019 - January 2023 Site 2019 2020 2021 2022 2023 ARKANSAS 1 & 2 4

BEAVER VALLEY 1 & 2 2

BRAIDWOOD 1 & 2 1

CATAWBA 1 & 2 1

COLUMBIA PLANT 6

4 COMANCHE PEAK 1 & 2 1

1 COOK 1 & 2 1

DIABLO CANYON 1 & 2 2

DRESDEN 2 & 3 1

FARLEY 1 & 2 1

1 FERMI 1

GINNA 2

GRAND GULF 2

1 HARRIS 1

HATCH 1 & 2 1

MILLSTONE 2 & 3 1

1 NINE MILE POINT 1 & 2 2

NORTH ANNA 1 & 2 1

PALO VERDE 1, 2, & 3 1

PRAIRIE ISLAND 1 & 2 1

RIVER BEND 3

SEQUOYAH 1 & 2 1

SOUTH TEXAS 1 & 2 5

ST LUCIE 1 & 2 1

2 VOGTLE 1 & 2 2

VOGTLE 3 +

3 15 WATTS BAR 1 & 2 2

2 1

WOLF CREEK 2

+ Vogtle 3 began Operations on August 3, 2022

  • This table refers to allegations from sources external to the NRC that are still under evaluation.

NON-OP REACTOR OPEN ALLEGATIONS BY CY RECEIVED*: January 2019 - January 2023 Site 2019 2020 2021 2022 2023 FORT CALHOUN 2

SAN ONOFRE 1, 2 & 3 1

SUMMER 2 & 3 1

THREE MILE ISLAND 1 & 2 2

VOGTLE 4 3

8 2

  • This table refers to allegations from sources external to the NRC that are still under evaluation.

FUEL FACILITY OPEN ALLEGATIONS BY CY RECEIVED*: January 2019 - January 2023 Site 2019 2020 2021 2022 2023 HONEYWELL 1

  • This table refers to allegations from sources external to the NRC that are still under evaluation.