Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr 52.7 (Respondent is same as in Subpart C below.)
application for exemption 1
25 25 360 9000
$2,610,000 Regulatory Guide (RG) 1.206, "Applications for Nuclear Power Plants" conduct of pre-application activities 1
1 1
25,000 25000
$7,250,000 Subtotal: General Provisions 2
26 34000
$9,860,000 Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr 52.17(a)(1) site safety analysis report 0
0 0
6000 0
$0 52.17(b)(1) submitting information on physical characteristics of the proposed site that could pose a significant impediment to the development of emergency plans 0
0 0
20 0
$0 52.17(b)(2)(i) and 52.17(b)(3) without ITAAC propose major features of the emergency plans in the site SAR 0
0 0
1000 0
$0 52.17(b)(2)(i) and 52.17(b)(3) with ITAAC propose major features of the emergency plans in the site SAR 0
0 0
2667 0
$0 52.17(b)(2)(ii) and 52.17(b)(3) propose complete and integrated emergency plans in the site SAR 0
0 0
2000 0
$0 52.17(b)(4) include a description of contacts and arrangements made with Federal, State, and local governmental agencies with emergency planning responsibilities 0
0 0
40 0
$0 52.29(a) requirements for a renewal application of any ESP 0
0 0
6000 0
$0 52.35 requires the holder to notify the agency of the non-nuclear use 0
0 0
40 0
$0 52.39(b) applicants for a CP, OL, or COL who have filed an application referencing an ESP to update their emergency preparedness information provided under 52.17(b) 52.39(d) an applicant referencing an ESP may include in its application a request for a variance from one or more site characteristics, design parameters, or terms and conditions of the ESP, or from the site SAR 0
0 0
120 0
$0 Subtotal: Subpart A 0
0 0
$0 NRC expects 0 new ESP applications over the next 3 years. (0/3=0)
TABLE 1 ANNUAL REPORTING BURDEN SUBPART A: EARLY SITE PERMITS (ESPs)
GENERAL PROVISIONS Burden covered under 10 CFR 52.79(b)
DNRL LIGHT WATER REACTORS & DANU NON-LIGHT WATER REACTORS (burden numbers combined below)
Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr 52.45 an application for a DC may be filed even if an application for a CP or COL for such a facility has not been filed 52.47(a), except (a)(6) & (a)(27) requires that a DC application contain a Final Safety Analysis Report (FSAR) 0.33 1
0.33 35,300 11,649
$3,378,210 52.47(a)(27) requires a DC application to contain a FSAR that describes the design-specific probabilistic risk assessment (PRA) and its results 0.33 1
0.33 45,400 14,982
$4,344,780 52.47(b)(1) requires that a DC application contain proposed inspections, tests, analyses, and acceptance criteria (ITAAC) 0.33 1
0.33 25,300 8,349
$2,421,210 52.47(c)(1) requires that an application for certification of a nuclear power reactor design that is an evolutionary change from light-water reactor (LWA) designs of plants must provide an essentially complete NPP design except for site-specific elements.
52.47(c)(2) requires that an application for certification of a nuclear power reactor design that differs significantly from the LWA designs described in paragraph (c)(1) or uses simplified, inherent, passive, or other innovative means to accomplish its safety functions must provide an essentially complete nuclear power reactor design except for site-specific elements and meet the requirements of 10CFR50.43(e).
52.51 requires that applicants for DC must submit a design control document (DCD) prior to completing a proposed rule for certifying a standard design by rulemaking is essentially the same requirement of Section 52.47(a).
52.57(a) provides a procedure for application for renewal of a DC 0
0 0
10,000 0
$0 52.63(b)(1) n/a Subtotal: Subpart B 0.33 1
34,980
$10,144,200
[1]Duetorounding,thetotalburdencostmaynotequalthesumofthecostsoftheindividualrequirements.
SUBPART B: STANDARD DESIGN CERTIFICATIONS (DCs)
NRC expects 1 new NLWR DC applications and 0 new NLWR or LWR DC renewal applications over the next 3 years. (1/3=0.33)
Burden covered under 10 CFR 52.46 and 52.47 Burden covered under 10 CFR 52.47(a) and 52.47(b)
Burden covered under 10 CFR 52.47(a) and 52.47(b)
Burden covered under 10 CFR 52.47(a)
Burden covered under 10 CFR 52.7
Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr 52.79(a), except (a)(45) & (a)(46) addresses a COL application that does not reference any other type of Part 52 license, certification, or approval 0.67 1
0.67 58,420 39,141
$11,351,006 52.79(a)(46) requires a COL application to contain a FSAR that describes the plant-specific probabilistic risk assessment or analysis (PRA) and its results 1
1 1
54,000 54,000
$15,660,000 52.79(b) addresses a COL application that references an ESP 0
0 0
102,368 0
$0 52.79(c) addresses a COL application that references a design approval 0.33 1
0.33 46,460 15,332
$4,446,222 52.79(d) addresses a COL application that references a DC 0
0 0
31,460 0
$0 52.79(e) addresses a COL application that references a manufactured reactor licensed under Subpart F of 10 CFR Part 52 0
0 0
36,460 0
$0 52.79(b) & (d) addresses a COL application that references both an ESP and DC 0
0 0
26,560 0
$0 52.80(a) - 40,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for applications which do not reference a DC application requires that a COL application contain the proposed inspections, tests, and analyses, including those applicable to emergency planning, that the licensee shall perform 1
1 1
40,000 40,000
$11,600,000 52.80(a) - 10,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for applications that do reference a certified design requires that a COL application contain the proposed inspections, tests, and analyses, including those applicable to emergency l
i th t th li h ll f
0 0
0 10,000 0
$0 52.80(d) requires applicants for power reactor operating licenses under Part 52 to include in their applications information on the plan for implementing the requirements of 10 CFR 50.155(b), and the requirement and planned locations of the equipment on which the strategies and guidelines will rely.
1 1
1 300 300
$87,000 SUBPART C: COMBINED LICENSES (COLs)
NRC expects 1 new LWR COL application and 2 new NLWR COL applications over the next 3 years (3/3=1 responses/year) 1 LWR COLs under construction; 0 NLWR COLs under construction; 0 COLs decommissioning NRC expects to receive a total of 1 LWR and 0 NLWR All ITAAC Complete Notifications over the next 3 years (1/3=0.33) 0 new LWR or NLWR COLs referencing a DC application (0/3=0 responses/year)
52.93(a) allows applicants for a COL under this subpart, or any amendment to a COL, to include in the application a request for an exemption from one or more of the Commissions regulations. Information submitted with an exemption request would be used to determine if the exemption is authorized by law, will not present an undue risk to public health and safety, and is consistent with the common defense and security, or if other special circumstances are present requiring consideration of the exemption request.
52.93(b) allows applicants for a COL referencing an ESP to include in the application a request for a variance from one or more site characteristics, design parameters, or terms and conditions of the permit, or from the site SAR. The NRC would use the information in an applicants request for a variance to determine if the information that did not conform to the ESP was in conformance with the NRCs regulations.
52.93(c) allows applicants for a COL referencing a nuclear power reactor manufactured under a ML to include in the application a request for a departure from one or more design characteristics, site parameters, terms and conditions, or approved design of the manufactured reactor. The NRC would use the information in an applicants request for a departure to determine if the information that did not conform to the ML or approved design of the manufactured reactor was in conformance with the NRCs regulations.
52.99(a) requires licensees to submit to the NRC, no later than 1 year after issuance of a COL, a detailed schedule for completing the inspections, tests, or analyses in the ITAAC and provide updates to the ITAAC schedule every 6 months thereafter 0.33 1
0.33 20 7
$1,914 52.99(c)(1) requires that, after issuance of the COL, the licensee notify the NRC that the inspections, tests, or analyses in the ITAAC have been successfully completed and that the corresponding acceptance criteria have been met (ITAAC Closure Notification) 0.33 41 13.53 40 541
$156,948 Burden covered under 10 CFR 52.7 Burden covered under 10 CFR 52.39 Burden covered under 10 CFR 52.171
52.99(c)(2) requires that the licensee notify the NRC in a timely manner of new information that materially alters the basis for determining that either inspections, tests, or analyses were performed as required, or that acceptance criteria are met (ITAAC Post-closure Notifications) 0.33 2
0.66 20 13
$3,828 52.99(c)(3) requires that, if the licensee has not provided, by the date 225 days before the scheduled date for initial loading of fuel, the notification required by paragraph (c)(1) of this section for all ITAAC, then the licensee must notify the NRC that the inspections, tests, or analyses for all uncompleted ITAAC will be successfully completed and all acceptance criteria will be met prior to operation (Uncompleted ITAAC Notifications) 0 1
0 40 0
$0 52.99(c)(4) requires that the licensee to notify the NRC that all ITAAC are complete (All ITAAC Complete Notification) 0.33 1
0.33 8
3
$766 52.99(d)(1) & 52.99(d)(2)
These sections states that in the event that an activity is subject to an ITAAC derived from a referenced ESP or standard DC and the licensee has not demonstrated that the ITAAC has been met, the licensee may take corrective actions to successfully complete that ITAAC, request a variance from the ESP ITAAC, or request an exemption from the standard DC ITAAC, as applicable. In the event that an activity is subject to an ITAAC not derived from a referenced ESP or standard DC and the licensee has not demonstrated that the ITAAC has been met, the licensee may take corrective actions to successfully complete that ITAAC or request a license amendment under
'52.98(f). The information submitted under this section would be used by the NRC to determine if the applicant met the NRCs requirements related to the particular ITAAC that had not been successfully completed.
52.103(a) requires that the licensee shall notify the NRC of its scheduled date for initial loading of fuel no later than 270 days before the scheduled date and shall notify the NRC of updates to its schedule every 30 days thereafter 0.33 1
0.33 10 3
$957 Burden covered under 10 CFR 52.39 (variances) and 52.7 (exemptions)
52.110(a) requirements for when a licensee has determined to permanently cease operations 0
0 0
20 0
$0 52.110(d) requires that, before or within 2 years following permanent cessation of operations, the licensee submit a post shutdown decommissioning activities report 0
0 0
3,000 0
$0 52.110(g) requirements following submittal of the post-shutdown decommissioning activities report 0
0 0
20 0
$0 52.110(h)(3) requires that within 2 years following permanent cessation of operations, if not already submitted, the licensee shall submit a site-specific decommissioning cost estimate 0
0 0
20 0
$0 52.110(h)(4) requirements for decommissioning activities 0
0 0
20 0
$0 Subtotal: Subpart C 1.33 19.18 149,340
$43,308,641
Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr 52.137(a), except (a)(6) & (a)(25) requires that a design approval application contain a FSAR 0.33 1
0.33 42,000 13,860
$4,019,400 52.137(a)(25) requires a design approval application to contain a FSAR that describes the design-specific PRA and its results 0.33 1
0.33 54,000 17,820
$5,167,800 Subtotal: Subpart E 0.33 0.66 31,680
$9,187,200 Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr 52.157, except 52.157(f)(9) & (f)(31) requires that a ML application contain a FSAR 0.33 1
0.33 50,000 16,500 52.157(f)(31) requires a ML application to contain a FSAR that describes the design-specific PRA and its results 0.33 1
0.33 54,000 17,820
$5,167,800 52.158(a) require that a ML application contain the proposed inspections, tests and analyses that the licensee who will be operating the reactor shall perform, and the acceptance criteria 0.33 1
0.33 30,000 9,900
$2,871,000 52.177 contains requirements for renewal of an application for a ML previously issued by the NRC 0
0 0
10,000 0
$0 Subtotal: Subpart F 0.33 1
44,220
$8,038,800 Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr X.A.2 requires an applicant or licensee who references this design certification to maintain the plant-specific DCD throughout the period of the application and for the term of the license.
SUBPART F: MANUFACTURING LICENSES Burden covered under 10 CFR 52.99(c)(1)
APPENDIX A: ABWR DESIGN CERTIFICATION RULE NRC expects 0 COL applicants referencing the ABWR Design Certification Rule over the next 3 years.
NRC expects 0 COL licensees referencing Appendix A NOT under construction over the next 3 years.
NRC expects 0 LWR and 1 new NLWR manufacturing license applications over the next 3 years (1/3=0.33 responses per year).
SUBPART E: STANDARD DESIGN APPROVALS NRC expects 0 new LWR and 1 new NLWR design approval applications over the next 3 years (1/3=0.33 responses per year)
X.B.1 requires applicants or licensees who reference the DC to submit reports on plant-specific departures from the DCD 0
0 0
0 0
$0 X.B.2 requires applicants or licensees who reference this DC to submit updates to its DCD 0
0 0
0 0
$0 X.B.3.c states that after the Commission has authorized operation of the nuclear plant, the frequency for submitting reports and updates returns to the frequency required by 10 CFR 50.59 and 50.71, respectively.
Appendix A Total 0
0 0
$0 Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr X.A.2 requires an applicant or licensee who references this design certification to maintain the plant-specific DCD throughout the period of the application and for the term of the license.
X.B.1 requires applicants or licensees who reference the DC to submit reports on plant-specific departures from the DCD 0
0 0
8 0
$0 X.B.2 requires applicants or licensees who reference this DC to submit updates to its DCD 0
0 0
500 0
$0 X.B.3.c states that after the Commission has authorized operation of the nuclear plant, the frequency for submitting reports and updates returns to the frequency required by 10 CFR 50.59 and 50.71, respectively.
Appendix B Total 0
0 0
$0 Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr X.A.2 requires an applicant or licensee who references this design certification to maintain the plant-specific DCD throughout the period of the application and for the term of the license.
NRC expects 0 COLs referencing Appendix B under construction over the next 3 years NRC expects 0 applicants to reference the System 80+ Design Certification Rule over the next 3 years.
NRC expects 0 COLs referencing Appendix C under construction over the next 3 years Burden covered under X.B.1 and X.B.2 Burden covered under 10 CFR 52.99(c)(1)
APPENDIX C: AP600 DESIGN CERTIFICATION RULE NRC expects 0 applicants to reference the AP600 Design Certification Rule over the next 3 years.
Burden covered under X.B.1 and X.B.2 Burden covered under 10 CFR 52.99(c)(1)
APPENDIX B: SYSTEM 80+ DESIGN CERTIFICATION RULE
X.B.1 requires applicants or licensees who reference the DC to submit reports on plant-specific departures from the DCD 0
0 0
8 0
$0 X.B.2 requires applicants or licensees who reference this DC to submit updates to its DCD 0
0 0
500 0
$0 X.B.3.c states that after the Commission has authorized operation of the nuclear plant, the frequency for submitting reports and updates returns to the frequency required by 10 CFR 50.59 and 50.71, respectively.
Appendix C Total 0
0 0
$0 APPENDIX D: AP1000 DESIGN CERTIFICATION RULE Burden covered under X.B.1 and X.B.2
Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr X.A.2 requires an applicant or licensee who references this design certification to maintain the plant-specific DCD throughout the period of the application and for the term of the license.
X.B.1 requires applicants or licensees who reference the DC to submit reports on plant-specific departures from the DCD 0
0 0
8 0
$0 X.B.2 requires applicants or licensees who reference this DC to submit updates to its DCD 0
0 0
500 0
$0 X.B.3.c states that after the Commission has authorized operation of the nuclear plant, the frequency for submitting reports and updates returns to the frequency required by 10 CFR 50.59 and 50.71, respectively.
Appendix D Total 0
0 0
$0 Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr IV.A.2.a, c, h Section IV.A.2.a requires a plant-specific DCD as part of the COL application. This section partially fulfills the requirements for contents of applications for a COL (10 CFR 52.79) and ensures that the COL applicant commits to complying with the DCD.
Section IV.A.2.c requires plant-specific technical specifications (10 CFR 50.36 and 50.36a) as part of the COL application.
This information collection is the same as for 10 CFR 50.36, but the timing of the burden is earlier (10 CFR 52.79).Section IV.A.2.h requires information required by 10 CFR 52.47(a), that is not within the scope of this design certification, as part of the COL application. This section fulfills part of the requirements for a COL (10 CFR 52.79).
NRC expects 0 COL applicants to reference the ESBWR Design Certification Rule over the next 3 years.
NRC expects 0 COL licensees referencing Appendix E NOT under construction over the next 3 years.
NRC expects 0 COL applicants to reference the AP1000 Design Certification Rule over the next 3 years.
APPENDIX E: ESBWR DESIGN CERTIFICATION RULE Burden covered under 10 CFR 52.99(c)(1)
NRC expects 0 COL licensees referencing Appendix D under construction over the next 3 years.
Burden covered in 10 CFR 52.79 NRC expects 0 COL licensees referencing Appendix D NOT under construction over the next 3 years.
Burden covered under X.B.1 and X.B.2
IV.A.2.b requires reports on departures from and updates to the DCD, under Section X.B of Appendix G, as part of the COL application. This section ensures that the COL application is up-to-date.
X.B.1 requires applicants or licensees who reference the DC to submit reports on plant-specific departures from the DCD 0
0 0
0 0
$0 X.B.2 requires applicants or licensees who reference this DC to submit updates to its DCD 0
0 0
0 0
$0 X.B.3.a requires submittal of reports and updates to the generic DCD with the initial COL application. This requirement ensures that the initial application is up-to-date and partially fulfills the requirements contents of applications in 10 CFR 52.79.
X.B.3.b requires that during the period of review of the application and construction of a facility that references this design certification, summary reports on changes to the design must be submitted semi-annually. These reports are needed to provide timely notification of design changes during the critical period of application review and facility construction.
X.B.3.c states that after the Commission has authorized operation of the nuclear plant, the frequency for submitting reports and updates returns to the frequency required by 10 CFR 50.59 and 50.71, respectively.
Appendix E Total 0
0 0
$0 Subtotal: Appendices A through E 0
0 0
$0
[1]Duetorounding,thetotalburdencostmaynotequalthesumofthecostsoftheindividualrequirements.
Section Description of requirement No. of Respondents Responses /
Respondent Total No. of Responses Burden per
Response
Total Annual Burden (Hrs)
Cost @ $290/Hr IV.A.2.a ) (COL applicant) requires a plant-specific DCD as part of the COL application. This section partially fulfills the requirements for contents of applications for a COL (10 CFR 52.79) and ensures that the COL applicant commits to complying with the DCD.
Burden included in X.B below Burden covered in X.B.1, X.B.2 Burden covered in 10 CFR 52.79 Burden in 10 CFR 50.59(d) + 10 CFR 50.71(e)
APPENDIX F: DESIGN CERTIFICATION FOR THE APR1400 DESIGN NRC expects 0 combined license applicants to use Appendix F over the next 3 years.
Burden covered under 10 CFR 52.79
IV.A.2.b (COL applicant) requires reports on departures from and updates to the DCD, under Section X.B of Appendix G, as part of the COL application.
This section ensures that the COL application is up-to-date IV.A.2.c (COL applicant) requires plant-specific technical specifications (10 CFR 50.36 and 50.36a) as part of the COL application. This information collection is the same as for 10 CFR 50.36, but the timing of the burden is earlier (10 CFR 52.79).
IV.A.2.d (COL applicant) requires information demonstrating compliance with site parameters and interface requirements as part of the COL application. This section fulfills part of the requirements for a COL (10 CFR 52.79).
IV.A.2.e (COL applicant) requires the COL applicant to address COL items in the generic DCD as part of the COL application. This section fulfills part of the requirements for a COL (10 CFR 52.79).
IV.A.2.f (COL applicant) requires information required by 10 CFR 52.47(a), that is not within the scope of this design certification, as part of the COL application. This section fulfills part of the requirements for a COL (10 CFR 52.79).
IV.A.2.g (COL applicant) requires information required by 10 CFR 52.47(a), that is not within the scope of this design certification, as part of the COL application. This section fulfills part of the requirements for a COL (10 CFR 52.79).
IV.A.2.h (COL applicant) requires information required by 10 CFR 52.47(a), that is not within the scope of this design certification, as part of the COL application. This section fulfills part of the requirements for a COL (10 CFR 52.79).
IV.A.3 (COL applicant) requires the COL applicant to include, in the plant-specific DCD, the proprietary and safeguards information referenced in the generic DCD to ensure that the applicant has actual notice of these requirements.
This section fulfills part of the requirements for contents of applications for a COL (10 CFR 52.79).
X.B.1 (COL applicant) requires COL applicants or licensees who reference this design certification to submit reports on departures from the plant-specific DCD. This section is similar to the requirements in 10 CFR 50.59(d)(2).
0 1
0 8
0
$0 Burden included in X.B below Burden covered under 10 CFR 52.79 Burden covered under 10 CFR 52.79 Burden covered under 10 CFR 52.79 Burden covered under 10 CFR 52.79 Burden covered under 10 CFR 52.79 Burden covered under 10 CFR 52.79 Burden covered under 10 CFR 52.79
X.B.2 (COL applicant) requires COL applicants or licensees who reference this design certification to submit updates to its plant-specific DCD that reflect generic changes to and plant specific departures from the generic DCD. This section is similar to the requirements in 10 CFR 50.71(e).
0 1
0 500 0
$0 X.B.3.a requires submittal of reports and updates to the generic DCD with the initial COL application. This requirement ensures that the initial application is up-to-date and partially fulfills the requirements contents of applications in 10 CFR 52.79.
X.B.3.b requires that during the period of review of the application and construction of a facility that references this design certification, summary reports on changes to the design must be submitted semi-annually. These reports are needed to provide timely notification of design changes during the critical period of application review and facility construction.
X.B.3.c states that after the Commission has authorized operation of the nuclear plant, the frequency for submitting reports and updates returns to the frequency required by 10 CFR 50.59 and 50.71, respectively.
Total 0
0 0
0 Description of requirement No. of Respondents Responses /
Respondent Total No. of Responses Burden per
Response
Total Annual Burden (Hrs)
Cost @ $290/Hr IV.A.2.a requires a plant-specific DCD as part of the COL application. This section partially fulfills the requirements for contents of applications for a COL (10 CFR 52.79) and ensures that the COL applicant commits to complying with the DCD.
IV.A.2.b requires reports on departures from and updates to the DCD, under Section X.B of Appendix G, as part of the COL application. This section ensures that the COL application is up-to-date.
IV.A.2.c requires plant-specific technical specifications (10 CFR 50.36 and 50.36a) as part of the COL application. This information collection is the same as for 10 CFR 50.36, but the timing of the burden is earlier (10 CFR 52.79).
NRC expects 0 combined license applicants to use Appendix G over the next 3 years.
(Burden covered under 10 CFR 52.79) (COL applicant)
(Burden included in X.B below) (COL applicant)
Burden covered under 10 CFR 52.79) (COL applicant)
Burden covered under 10 CFR 52.79 Burden covered under X.B.1, X.B.2 (Burden covered under 10 CFR 50.59(d) + 10 CFR 50.71(e))
APPENDIX G: DESIGN CERTIFICATION FOR THE NUSCALE DESIGN
IV.A.2.d requires information demonstrating compliance with site parameters and interface requirements as part of the COL application. This section fulfills part of the requirements for a COL (10 CFR 52.79).
IV.A.2.e requires the COL applicant to address COL items in the generic DCD as part of the COL application. This section fulfills part of the requirements for a COL (10 CFR 52.79).
IV.A.2.f requires information required by 10 CFR 52.47(a), that is not within the scope of this design certification, as part of the COL application. This section fulfills part of the requirements for a COL (10 CFR 52.79).
IV.A.2.g requires information required by 10 CFR 52.47(a), that is not within the scope of this design certification, as part of the COL application. This section fulfills part of the requirements for a COL (10 CFR 52.79).
IV.A.2.h requires information required by 10 CFR 52.47(a), that is not within the scope of this design certification, as part of the COL application. This section fulfills part of the requirements for a COL (10 CFR 52.79). n/a IV.A.3 requires the COL applicant to include, in the plant-specific DCD, the proprietary and safeguards information referenced in the generic DCD to ensure that the applicant has actual notice of these requirements.
This section fulfills part of the requirements for contents of applications for a COL (10 CFR 52.79).
IV.A.4 requires the COL applicant to include, as part of the COL application, information demonstrating that an entity other than NuScale Power is qualified to supply the NuScale design, unless NuScale Power supplies the design for the COL applicants use.
X.B.1 (COL applicant) requires COL applicants or licensees who reference this design certification to submit reports on departures from the plant-specific DCD. This section is similar to the requirements in 10 CFR 50.59(d)(2).
0 0
0 0
0
$0 (Burden covered under 10 CFR 52.79) (COL applicant)
(Burden covered under 10 CFR 52.79) (COL applicant)
(Burden covered under 10 CFR 52.79) (COL applicant)
(Burden covered under 10 CFR 52.79) (COL applicant)
(Burden covered under 10 CFR 52.79) (COL applicant)
(Burden covered under 10 CFR 52.79) (COL applicant)
(Burden covered under 10 CFR 52.79) (COL applicant)
X.B.2 (COL applicant) requires COL applicants or licensees who reference this design certification to submit updates to its plant-specific DCD that reflect generic changes to and plant specific departures from the generic DCD. This section is similar to the requirements in 10 CFR 50.71(e).
0 0
0 0
0
$0 X.B.3.a requires submittal of reports and updates to the generic DCD with the initial COL application. This requirement ensures that the initial application is up-to-date and partially fulfills the requirements contents of applications in 10 CFR 52.79.
X.B.3.b requires that during the period of review of the application and construction of a facility that references this design certification, summary reports on changes to the design must be submitted semi-annually. These reports are needed to provide timely notification of design changes during the critical period of application review and facility construction.
X.B.3.c states that after the Commission has authorized operation of the nuclear plant, the frequency for submitting reports and updates returns to the frequency required by 10 CFR 50.59 and 50.71, respectively.
Total 0
0 0
0 0
$0
- The respondents in X.B.1 and X.B.2 are the same entity and should not be double counted in the total.
Section Description of requirement Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per
Response
Total Annual Burden Hours Estimate Annual Cost @ $290/hr Paragraph 2 requires that each COL application submitted pursuant to this appendix be submitted as specified in 52.75 and 10 CFR 2.101 and that each application state that the applicant wishes to have the application considered under 10 CFR Part 52, Appendix N 0
0 0
10 0
$0 Paragraph 3 requirements for what each application should include 0
0 0
40 0
$0 APPENDIX N: STANDARDIZATION OF NUCLEAR POWER PLANT DESIGNS:
COMBINED LICENSES TO CONSTRUCT AND OPERATE NUCLEAR POWER REACTORS OF IDENTICAL DESIGN AT MULTIPLE SITES NRC expects 0 combined license applicants to use Appendix N over the next 3 years.
(Burden covered under 10 CFR 50.59(d) + 10 CFR 50.71(e))
(Burden covered under 10 CFR 52.79)
(Burden covered under X.B.1, X.B.2)
Paragraph 4 This paragraph requires that each COL application submitted pursuant to this appendix contain an ER as required by 52.80(b), and which complies with the applicable provisions of 10 CFR Part 51 and states that the application may incorporate by reference a single ER on the environmental impacts of the common design.
Subtotal: Appendix N 0
0 0
$0 Total Part 52 Reporting Burden 4
48 294,220
$80,538,841 Applicant/Licensee Name Reporting Section 2024 2025 2026 NuScale DC application Subpart B A (Feb 2023)
NuScale SDA application (30 month review started March 2023)
Subpart B N
N N
CFPP/UAMPS COL application
- Subpart C N
N N
AP1000 DC renewal application
- Subpart B N
N Vogtle Unit 3 COL Subpart C & Appendix D Z
Vogtle Unit 4 COL Subpart C & Appendix D Z
COL A (non-LWR reactor)*
Subpart C N
N N
COL B (non-LWR reactor)*
Subpart C N
ML (non-LWR reactor)*
Subpart F N
N SDA (non-LWR reactor)*
Subpart E N
N DC (non-LWR reactor)*
Subpart B N
N
- = new application submitted during this reporting period N = license/permit/design certification not yet issued; A = license/permit/design certification issued; Z = initial fuel load Continue ITAAC complete notifications 12 per year until notification of all ITAAC met ANNUAL REPORTING BURDEN UNDER 10 CFR 52.99(a) 10 CFR PART 52 TABLE 3 Burden covered under 10 CFR 52.80© For reporting purposes it is assume that each unit will submit a separate report Notes:
NOTE: Bell Bend, Callaway, Calvert Cliffs, Comanche Peak, Grand Gulf, Nine Mile Point, River Bend, Lee, Shearon Harris, Bellefonte, and Victoria County COL applications are suspended or withdrawn; and therefore have been removed from the table Summer Levy and South Texas Project COLs were terminated at the request of the licensees; and therefore have been removed from the table
Section Description of requirement Number of Record keepers Burden Hrs. per Record keeper Total Annual Burden Hours Estimate Annual Cost @
$290/hr 52.47 requirements for the contents of applications for the certification of a standard plant design 2
500 1,000
$290,000 Regulatory Guide (RG) 1.206, "Applications for Nuclear Power Plants" provides guidance on the format and content of applications and on the conduct of pre-application activities submitted under 10 CFR Part 52.
2 5000 10,000
$2,900,000 52.57(a)-renewals provides a procedure for application for renewal of a DC
- requires updating any of the information that was submitted under Sections 52.46 and 52.47 0
500 0
$0 52.63(b)(2) requires that licensees who reference a standard DC must maintain records of all changes to the facility 2
1,500 3,000
$870,000 52.63(c) & 52.73(b) requires applicants for CPs, OLs, or COLs who reference standard DCs, SDAs, or MLs to acquire or complete, and make available for audit, detailed design-related information normally contained in procurement, construction, and installation specifications 1
500 500
$145,000 Subtotal 7
14,500
$4,205,000 Recordkeepers under 52.63(b)(2) and 52.63(b) are noted as the same record keeper and are only counted once.
NRC expects 0 applicant to maintain records for the ABWR Design Certification Rule over the next 3 years.
TABLE 2 APPENDIX A: ABWR DESIGN CERTIFICATION RULE ANNUAL RECORDKEEPING BURDEN 10 CFR PART 52 NRC expects 5 new NLWR applications (includes 1 DC, 2 COLs, 1 ML, a 1 SDA) and 1 new LWR COL application to be submitted over the next 3 years NRC expects 0 new DC renewal applications to be submitted over the next 3 years.
NRC expects there to be 2 COL licensees who reference a standard DC by the end of January 2027 NRC expects there to be 1 LWR COL licensee who references a standard design approval by the end of January 2027
Section Description of requirement Number of Record keepers Burden Hrs. per Record keeper Total Annual Burden Hours Estimate Annual Cost @
$290/hr X.A.1 requires that the applicant for the DC maintain a copy of the generic DCD and maintain the proprietary and safeguards information referenced in the generic DCD for the period that the appendix may be referenced 0
34 0
$0 X.A.2 requires an applicant or licensee who references this design certification to maintain the plant-specific DCD throughout the period of the application and for the term of the license.
X.A.3 requires an applicant or licensee who references this design certification to prepare and maintain the bases for its changes to this design certification throughout the period of the application and the term of the license.
X.A.4.a Requires the applicant for the amendment to the U.S. ABWR design to maintain a copy of the aircraft impact assessment performed to comply with the requirements of 10 CFR 50.150(a) for the term of the certification (including any period of renewal) 0 1
0
$0 X.A.4.a Requires the applicant for the amendment to the ABWR design to maintain a copy of the aircraft impact assessment performed to comply with the requirements of 10 CFR 50.150(a) for the term of the certification (including any period of renewal) 0 1
0
$0 Appendix A Total 0
0
$0 Burden covered under 10 CFR 50.71(e)
Burden covered under 10 CFR 50.59(d)
[1]Duetorounding,thetotalburdencostmaynotequalthesumofthecostsoftheindividualrequirements.
Section Description of requirement Number of Record keepers Burden Hrs. per Record keeper Total Annual Burden Hours Estimate Annual Cost @
$290/hr X.A.1 requires that the applicant for the DC maintain a copy of the generic DCD and maintain the proprietary and safeguards information referenced in the generic DCD for the period that the appendix may be referenced 0
0 0
$0 X.A.2 requires an applicant or licensee who references this design certification to maintain the plant-specific DCD throughout the period of the application and for the term of the license.
X.A.3 requires an applicant or licensee who references this design certification to prepare and maintain the bases for its changes to this design certification throughout the period of the application and the term of the license.
Appendix B Total 0
0
$0 Section Number of Record keepers Burden Hrs. per Record keeper Total Annual Burden Hours Estimate Annual Cost @
$290/hr X.A.1 requires that the applicant for the DC maintain a copy of the generic DCD and maintain the proprietary and safeguards information referenced in the generic DCD for the period that the appendix may be referenced 0
0 0
$0 X.A.2 requires an applicant or licensee who references this design certification to maintain the plant-specific DCD throughout the period of the application and for the term of the license.
Burden covered under 10 CFR 50.59(d)
Burden covered under 10 CFR 50.71(e)
APPENDIX C: AP600 DESIGN CERTIFICATION RULE NRC expects 0 applicant to maintain records for the AP600 Design Certification Rule over the next 3 years. (This certified design has expired)
Burden covered under 10 CFR 50.71(e)
APPENDIX B: SYSTEM 80+ DESIGN CERTIFICATION RULE NRC expects 0 applicant to maintain records for the System 80+ Design Certification Rule over the next 3 years. (This certified design has expired)
X.A.3 requires an applicant or licensee who references this design certification to prepare and maintain the bases for its changes to this design certification throughout the period of the application and the term of the license.
Appendix C Total 0
0
$0 Section Description of requirement Number of Record keepers Burden Hrs. per Record keeper Total Annual Burden Hours Estimate Annual Cost @
$290/hr X.A.1 requires that the applicant for the DC maintain a copy of the generic DCD and maintain the proprietary and safeguards information referenced in the generic DCD for the period that the appendix may be referenced 1
34 34
$9,860 X.A.2 requires an applicant or licensee who references this design certification to maintain the plant-specific DCD throughout the period of the application and for the term of the license.
X.A.3 requires an applicant or licensee who references this design certification to prepare and maintain the bases for its changes to this design certification throughout the period of the application and the term of the license.
Appendix D Total 1
34
$9,860 Section Description of requirement No. of Recordkeepers Burden Hours per Recordkeeper Total Annual Burden Hours Cost @ $290/Hr Burden covered under 10 CFR 50.59(d)
Burden covered under 10 CFR 50.71(e)
Burden covered under 10 CFR 50.59(d)
APPENDIX E: ESBWR DESIGN CERTIFICATION RULE NRC expects 1 applicant to maintain records for the ESBWR Design Certification Rule over the next 3 years.
APPENDIX D: AP1000 DESIGN CERTIFICATION RULE NRC expects 1 applicant for two plants to maintain records for the AP1000 Design Certification Rule over the next 3 years
X.A.1 requires that the applicant for the DC maintain a copy of the generic DCD and maintain the proprietary and safeguards information referenced in the generic DCD for the period that the appendix may be referenced 1
34 34
$9,860 X.A.2 requires an applicant or licensee who references this design certification to maintain the plant-specific DCD throughout the period of the application and for the term of the license.
X.A.3 requires an applicant or licensee who references this design certification to prepare and maintain the bases for its changes to this design certification throughout the period of the application and the term of the license.
Appendix E Total 1
34
$9,860 Section Description of requirement No. of Recordkeepers Burden Hours per Recordkeeper Total Annual Burden Hours Cost @ $290/Hr X.A.1(similar burden to 10 CFR 50.71(e)) (DCD applicant) requires that the applicant for this appendix shall maintain a copy of the generic DCD that includes all generic changes that are made to Tier 1 and Tier 2, and the generic TS and other operational requirements.
1 34 34
$9,860 X.A.2 requires an applicant or licensee who references this design certification to maintain the plant-specific DCD throughout the period of the application and for the term of the license.
X.A.3 requires an applicant or licensee who references this design certification to prepare and maintain the bases for its changes to this design certification throughout the period of the application and the term of the license.
Burden covered under 10 CFR 50.71(e)
APPENDIX F: APR1400 DESIGN CERTIFICATION RULE NRC expects 1 applicant to maintain records for the APR1400 Design Certification Rule over the next 3 years Burden covered under 10 CFR 50.59(d)
Burden covered under 10 CFR 50.71(e)
Burden covered under 10 CFR 50.59(d)
X.A.4.a (DCD applicant) requires that the applicant for the APR1400 design shall maintain a copy of the aircraft impact assessment performed to comply with the requirements of 10 CFR 50.150(a) for the term of the certification (including any period of renewal) 1 3
3
$870 X.A.4.b (COL applicant) requires that the applicant or licensee who references this appendix shall maintain a copy of the aircraft impact assessment performed to comply with the requirements of 10 CFR 50.150(a) throughout the pendency of the application and for the term of the license (including any periods 1
3 3
$870 Appendix F Total 1
40
$11,600 Section Description of requirement No. of Recordkeepers Burden Hours per Recordkeeper Total Annual Burden Hours Cost @ $290/Hr X.A.1(similar burden to 10 CFR 50.71(e)) (DCD applicant) 1 103 103.0
$29,870 X.A.2 requires an applicant or licensee who references this design certification to maintain the plant-specific DCD throughout the period of the application and for the term of the license.
X.A.3 requires an applicant or licensee who references this design certification to prepare and maintain the bases for its changes to this design certification throughout the period of the application and the term of the license.
X.A.4.a (DCD applicant) requires the applicant for this design certification to maintain a copy of the aircraft impact assessment (AIA) performed to comply with the requirements of 10 CFR 50.150(a) for the term of the certification (including any period of renewal).
0 3
0
$0 APPENDIX G: NUSCALE DESIGN CERTIFICATION RULE NRC expects 1 applicant to maintain records for the Nuscale Design Certification Rule over the next 3 years.
Burden covered under 10 CFR 50.71(e)
Burden covered under 10 CFR 50.59(d)
X.A.4.b (COL applicant) requires COL applicants or licensees who references this design certification to maintain a copy of the AIA performed to comply with the requirements of 10 CFR 50.150(a) throughout the pendency of the application and for the term of the license (including any period of renewal).
0 3
0
$0 Appendix G Total 1
109 103
$29,870 Total Part 52 Recordkeeping Burden 11.00 14,711
$4,224,720 Total Storage Cost
$1,706.48 Applicant/Licensee Name Recordkeeping Section NuScale DC application 52.47 Oklo COL (non-LWR reactor)
- Subpart C NuScale SDA application 52.47 Summer Unit 2 COL Subpart C & Appendix D UAMPS COL application*
52.47 and 52.63(c) & 52.73(b)
Summer Unit 3 COL Subpart C & Appendix D AP1000 DC renewal application*
52.47 ABWR DC Renewal Subpart B Vogtle Unit 3 COL 52.63(b)(2)
Bellefonte 1 COL Subpart C Vogtle Unit 4 COL 52.63(b)(2)
COL A (non-LWR reactor)*
52.79 COL B (non-LWR reactor)*
52.73(b)
ML (non-LWR reactor)*
52.157 SDA (non-LWR reactor)*
52.137 DC (non-LWR reactor)*
52.47 Notes:
For reporting purposes it is assumed that each unit will submit a separate report.
From 2020 not in 2023 TABLE 1
Hours Responses Reporting 294,220 47.8 Recordkeeping 14,711 11.0 Total 308,931 58.8 Total cost
@$290/hr 89,590,031 Additional costs (item #14) 1,706 Burden Totals Part 52 Renewal