Text

Pacific Gas and Maureen R. Zawalick Diablo Canyon Power Plant Electric Company"' Vice President Mail code 104/6/608 Business and P.O. Box 56 Technical Services Avila Beach, CA 93424

805.545.4242 Marueen.Zawalick@pge.com So-2.,~15 5o ~* '32. 3

December 27, 2022

US Nuclear Regulatory Commission Document Control Desk Washington DC 20555-0001

Attention: Commission Librarian

Re: Diablo Canyon Independent Safety Committee Annual Report Response on Safety of Operations

Dear US Nuclear Regulatory Commission:

Enclosed please find a copy of PG&E's response to the Diablo Canyon Independent Safety Committee's (DCISC) Thirty-Second Annual Report on the safety of Diablo Canyon operations for the period of July 1, 2021 to June 30, 2022.

In accordance with Public Utilities Code §712.1 (f) PG&E shall respond to this annual report and distribute its response to the governmental entities specified in Public Utilities Code §712.1 (e)(2) and a copy of PG&E's response will be included in the DCISC's next annual report.

Maureen Zawalick Vice President, Business and Technical Services

A member of the STARS Alliance

  • Callaway
  • Diablo Canyon
  • Palo Verde
  • Wolf Creek Pacific Gas and Electric Company,;,

Paula Gerfen Diablo Canyon Power Plant Senior Vice President & P.O. Box 56 Chief Nuclear Officer Avila Beach, CA 93424

805.545.4596 E-Mail:

Paula.Gerfen@pge.com

December 08, 2022

PG&E Letter ISC-22-001

Dr. Peter Lam c/o The Diablo Canyon Independent Safety Committee 857 Cass Street, Suite D Monterey, CA 93940

Response to the Diablo Canyon Independent Safety Committee Thirty-Second Annual Report on the Safety of Diablo Canyon Power Plant Operations - July 1, 2021 to June 30, 2022

Dear Dr. Lam:

On November 22, 2022, Pacific Gas and Electric Company (PG&E) received the Diablo Canyon Independent Safety Committee's (DCISC) Thirty-Second Annual Report on the safety of Diablo Canyon operations for the period of July 1, 2021 to June 30, 2022.

Your report concludes that PG&E continues to operate Diablo Canyon Power Plant (DCPP) safely and has no recommendations for PG&E during this report period.

As you are aware, operating the plant conservatively to protect public health and safety is our highest priority, and we will continue to ensure that we fulfill this commitment.

We welcome DCISC's independent review and oversight, which contributes to the continued safe operation of DCPP.

Sincerely,

Paula Gerfen Senior Vice President and Chief Nuclear Officer Dr. Peter Lam PG&E Letter ISC-22-001 December 08, 2022 Page 2

cc/: Dr. Robert Budnitz Dr. Per F. Peterson Richard McWhorter Robert W. Rathie Ferman Wardell Robert R. Wellington Blair Jones