ML23017A026

From kanterella
Jump to navigation Jump to search
Independent Safety Committee - Annual Report Response on Safety of Operations
ML23017A026
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 12/27/2022
From: Zawalick M
Pacific Gas & Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML23017A026 (1)


Text

Pacific Gas and Electric Company"'

December 27, 2022 US Nuclear Regulatory Commission Document Control Desk Washington DC 20555-0001 Attention: Commission Librarian Re: Diablo Canyon Independent Safety Committee Annual Report Response on Safety of Operations

Dear US Nuclear Regulatory Commission:

Maureen R. Zawalick Vice President Business and Technical Services Diablo Canyon Power Plant Mail code 104/6/608 P.O. Box 56 Avila Beach, CA 93424 805.545.4242 Marueen.Zawalick@pge.com So-2.,~15 5o ~* '32. 3 Enclosed please find a copy of PG&E's response to the Diablo Canyon Independent Safety Committee's (DCISC) Thirty-Second Annual Report on the safety of Diablo Canyon operations for the period of July 1, 2021 to June 30, 2022.

In accordance with Public Utilities Code §712.1 (f) PG&E shall respond to this annual report and distribute its response to the governmental entities specified in Public Utilities Code §712.1 (e)(2) and a copy of PG&E's response will be included in the DCISC's next annual report.

Maureen Zawalick Vice President, Business and Technical Services A

member of the STARS Alliance

  • Callaway
  • Diablo Canyon
  • Palo Verde
  • Wolf Creek

Pacific Gas and Electric Company,;,

December 08, 2022 PG&E Letter ISC-22-001 Dr. Peter Lam c/o The Diablo Canyon Independent Safety Committee 857 Cass Street, Suite D Monterey, CA 93940 Paula Gerfen Senior Vice President &

Chief Nuclear Officer Diablo Canyon Power Plant P.O. Box 56 Avila Beach, CA 93424 805.545.4596 E-Mail:

Paula.Gerfen@pge.com Response to the Diablo Canyon Independent Safety Committee Thirty-Second Annual Report on the Safety of Diablo Canyon Power Plant Operations - July 1, 2021 to June 30, 2022

Dear Dr. Lam:

On November 22, 2022, Pacific Gas and Electric Company (PG&E) received the Diablo Canyon Independent Safety Committee's (DCISC) Thirty-Second Annual Report on the safety of Diablo Canyon operations for the period of July 1, 2021 to June 30, 2022.

Your report concludes that PG&E continues to operate Diablo Canyon Power Plant (DCPP) safely and has no recommendations for PG&E during this report period.

As you are aware, operating the plant conservatively to protect public health and safety is our highest priority, and we will continue to ensure that we fulfill this commitment.

We welcome DCISC's independent review and oversight, which contributes to the continued safe operation of DCPP.

Sincerely, Paula Gerfen Senior Vice President and Chief Nuclear Officer

Dr. Peter Lam December 08, 2022 Page 2 cc/:

Dr. Robert Budnitz Dr. Per F. Peterson Richard McWhorter Robert W. Rathie Ferman Wardell Robert R. Wellington Blair Jones PG&E Letter ISC-22-001