January 20, 2023 Mr. Daniel G. Stoddard Senior Vice President and Chief Nuclear Officer Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

SURRY POWER STATION, UNITS 1 AND 2 - FLOOD MITIGATION MODIFICATION CHANGE IN COMPLETION DATE

Dear Mr. Stoddard:

By letter dated December 7, 2022, Virginia Electric and Power Company (the licensee, Dominion) submitted a document (Agency Documents Access and Management System Accession No. ML22342A424), titled Virginia Electric and Power Company, Surry Power Station Units 1 and 2 (SPS) Response to March 12, 2012 Request for Information Enclosure 2, Recommendation 2.1, Flooding Focused Evaluation Integrated Assessment Submittal Revised Commitment Completion Date, (ML12053A340).

As stated in the above submittal, Dominion identified a revised commitment date for the completion of the flooding mitigation modifications (flood barriers) for SPS to November 1, 2023.

The licensee also stated that the new completion dates were due to scope increases and significant COVID-19 impacts that affected timely delivery of the flood barriers. The submittal also stated that these factors created a 2-year delay in the delivery of the flood barriers. Lastly, the licensee further stated that temporary flood barrier design is approximately 70% complete and that the pending implementation of the flood barrier designs is related to the Turbine Building Air Intakes, the Auxiliary Building ground water infiltration, and the Fuel Building ground water infiltration.

NRC staff has reviewed the submittal and the conditions contributing to the delay and revised commitment for the associated completion date, and finds the extension reasonable and acceptable. This letter acknowledges the revised proposed completion date of November 1, 2023.

If you have any questions, please contact me at (301) 415-5136, or via email at John.Klos@nrc.gov.

Sincerely,

/RA/

L. John Klos, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-280 and 50-281 cc: Listserv

ML23005A240 OFFICE NRR/DORL/LPL2-1/PM NRR/DORL/LPL2-1/LA NRR/DORL/LPMB/BC NAME JKlos KGoldstein UShoop DATE 01/04/2023 01/05/2023 01/17/2023 OFFICE NRR/DORL/LPL2-1/BC NRR/DORL/LPL2-1/PM NAME MMarkley JKlos DATE 01/19/2023 01/20/2023