Model S-6213 Power Unit Shipping Container Amendment Request
ML23003A237
Person / Time
Site: 07109186
Issue date: 12/28/2022
From: Plate N
US Dept of Energy, Naval Reactors
To: John Lubinski
Office of Nuclear Material Safety and Safeguards
References
Download: ML23003A237 (1)


Text

CONFIDENTIAL//RESTRICTED DATA RESTRICTED DATA This document contains Restricted Data as defined in the Atomic Energy Act of 1954, as amended. Unauthorized disclosure is subject to administrative and criminal sanctions.

Classified By:

N. S. Plate - Nuclear Engineer Derived From: DOE-DOD CG-RN1 Rev 3 Feb 1996, DOE OC CONFIDENTIAL//RESTRICTED DATA NR:RR:JHKampen G#C2205956 December 28, 2022 Unclassified upon removal of Enclosures (1) and (2).

John Lubinski Director, Office of Nuclear Material Safety and Safeguards Nuclear Regulatory Commission Washington, DC 20555 S-6213 POWER UNIT SHIPPING CONTAINERSAFETY ANALYSIS REPORT FOR PACKAGING OF S9G POWER UNITS; REQUEST FOR NUCLEAR REGULATORY COMMISSION REVIEW AND CONCURRENCE (U)

References:

(a) NR letter G#C21-04464 dated September 23, 2021 (b) NR letter G#22-00013 dated January 18, 2022

Background:

a. The S-6213 power unit shipping container (PUSC) is used to transport submarine power units (fully assembled and unirradiated cores). The S-6213 PUSC is certified as a Type B package for shipment of fissile and highly radioactive material. Compliance with Title 10, Code of Federal Regulations, Part 71 (10CFR71) is demonstrated through a safety analysis report for packaging (SARP). The S9G power unit in the S-6213 PUSC SARP evaluates the Next Generation Reactor (NGR) and VIRGINIA Forward Fit (VAFF) cores as authorized contents in the S-6213 PUSC.
b. Reference (a) notified the NRC that a design modification was being pursued for the S-6213 PUSC and that NRC review and concurrence would be requested with the revised SARP incorporating the design modification. Reference (b) requested renewal of NRC Certificate of Compliance (CoC) USA/9186/B(U)F-96 for the S-6213 PUSC, and recommended NRC take action on the renewal request as part of the review of the SARP revision for the S-6213 PUSC design modification.

Discussion:

a. The Naval Nuclear Propulsion Program has designed and manufactured a new internal pressure cap design for the S-6213 PUSC. The S9G Power Unit in the S-6213 DEPARTMENT OF ENERGY NATIONAL NUCLEAR SECURITY ADMINISTRATION 1000 INDEPENDENCE AVENUE SW WASHINGTON DC 20585-1000 Enclosures (1) & (2) Removed.

UNCLASSIFIED 2

NR:RR:JHKampen G#C2205956 UNCLASSIFIED PUSC SARP is revised via an Addendum that, together with the SARP, demonstrates compliance with 10CFR71 for the S9G power unit in the S-6213 PUSC package. The Addendum addresses all aspects of the S9G power unit in the S-6213 PUSC package that have changed as a result of the internal pressure cap design change. Enclosure (1) provides a high level summary of the changes presented in the Addendum.

Enclosure (2) provides the full text of the Addendum.

b. Reference (b) requested renewal of the S-6213 PUSC NRC CoC (USA/9186/B(U)F-96) and removal of NGR and TDC power units as authorized contents because no further shipments of these contents are planned. Naval Reactors requested NRC take action on the renewal as part of this SARP review. Additionally, no shipments of S6W power units are planned and S6W power units are removed as authorized contents from the CoC. The S9G power unit in the S-6213 PUSC package weight is revised because the Addendum calculates a slightly different weight compared to previous analyses. Enclosure (3) contains all CoC changes requested in reference (b) and this letter.

Request for Action: Naval Reactors requests NRC review and concurrence with the S9G Power Unit in the S-6213 PUSC SARP Addendum, Revision Original, provided in Enclosure (2). NRC is requested to renew NRC CoC USA/9186/B(U)F-96, as requested in reference (b), with the changes as documented in Enclosure (3). To support planned shipments of S9G power units to support national security needs for VIRGINIA Class submarine construction, Naval Reactors requests NRC schedule their review to complete by October 2023. Naval Reactors will schedule a review kickoff meeting with the NRC.

If you have any questions, please do not hesitate to call me at (202) 781-6034.

N. S. Plate Naval Reactors (1)

SUMMARY

OF CHANGES IN THE S9G POWER UNIT IN THE S-6213 PUSC SARP ADDENDUM (2) S9G POWER UNIT IN THE S-6213 POWER UNIT SHIPPING CONTAINER SAFETY ANALYSIS REPORT FOR PACKAGING ADDENDUM, REVISION ORIGINAL (3) REQUESTED CHANGES TO THE NRC CERTIFICATE OF COMPLIANCE FOR THE S-6213 PUSC, USA/9186/B(U)F-96, REVISION 20 (DRAFT)

Enclosure:

Digitally signed by Nicholas Plate Date: 2022.12.28 10:19:29 -05'00'

UNCLASSIFIED 3

NR:RR:JHKampen G#C2205956 UNCLASSIFIED NTK: PRNR-REC, PRNR-REP Copy to (Hard copy with Enclosure (2)):

Director, Division of Fuel Management, NMSS, NRC (S. Helton)

Chief, Storage and Transportation Licensing Branch, DFM, NMSS, NRC (Y. Diaz-Sanabria)

Project Manager, STLB, DFM, NMSS, NRC (C. Allen)

Copy to (Electronic, without Enclosure (2) contents):

NNL ADSARS General Manager, NNL (T. Sambolt)

Executive Manager, RS.Reactor Servicing (RS), NNL (V. Pantloni)

Executive Manager, RSS.Reactor Servicing Systems (RSS), NNL (M. Drewen)

Subdivision Technical Manager, RSS.Shipping Containers, NNL (S. Fiscus)

Unit Technical Manager, RSS.New Fuel and Exams, NNL (A. Brenneman)

Advisor Engineer, RSS.Shipping Container Recapitalization, NNL (M. Uhl)

Manager, NRLFO (J. Showman)

1 Enclosure (3) to NR:RR:JHKampen G#C2205956 ENCLOSURE (3)

RECOMMENDED CHANGES TO THE NRC CERTIFICATE OF COMPLIANCE FOR THE S-6213 PUSC, USA/9186/B(U)F-96, REVISION 20 (DRAFT)

Enclosed are recommended changes to the NRC Certificate of Compliance, showing additions and deletions from the latest revision (Revision 19) of the certificate. These changes include those recommended in Naval Reactors letter G#22-00013 dated January 18, 2022.

20 An internal pressure cap and seal ring are attached to the PUSC barrel flange.

20 (i) 320,400

20

Naval Reactors letter G#22-00013, dated January 18, 2022; and Naval Reactors Letter G#22-05956 dated December 28, 2022.

March 31, 2027 20

20

Naval Reactors letter G#22-00013, dated January 18, 2022; and Naval Reactors Renew Renew Letter G#22-05956 dated December 28, 2022.