Delay of Planned End of Date for Fourth 10-Year Inservice Testing (IST) Program Interval
ML22314A258
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 11/09/2022
From: James Holloway
Dominion Energy South Carolina
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
22-334
Download: ML22314A258 (1)


Text

Dominion Energy South Carolina. Inc.

5000 Dominion Boulevard, Glen Allen, VA 23060 Dominion Energy.com Attn: Document Control Desk November 09, 2022 U. S. Nuclear Regulatory Commission Washington, DC 20555-0001 DOMINION ENERGY SOUTH CAROLINA (DESC)

VIRGIL C. SUMMER NUCLEAR STATION (VCSNS) UNIT 1 A Dominion tJ tr" Energy !

Serial No.:

NRA/YG:

Docket No.:

License No.:

22-334 RO 50-395 NPF-12 DELAY OF PLANNED END DATE FOR FOURTH 10-YEAR INSERVICE TESTING {1ST)

PROGRAM INTERVAL The purpose of this letter is to notify the U.S. Nuclear Regulatory Commission (NRC) that Dominion Energy South Carolina (DESC) is revising the end date for the fourth 10-year Inservice Testing (1ST) program interval for the Virgil C. Summer Nuclear Station (VCSNS), Unit 1.

The fourth 10-year interval for VCSNS is scheduled to end on December 31, 2023. The fourth 10-year jnterval for VCSNS follows the requirement of the American Society of Mechanical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants (OM Code}, 2004 Edition through 2006 addenda, which states the following in ISTA-3120, lnservice Test Interval, paragraph (d):

(d)

Each of the inservice test intervals may be extended or decreased as much as 1 year. Adjustments shall not cause successive intervals to be altered by more than 1 year from the original pattern of intervals.

DESC is extending the fourth 1ST interval end date to December 31, 2024, versus the previously scheduled interval end date of December 31, 2023, to allow time to adopt and apply alternative to the 2020 Edition of the ASME OM Code, approved (incorporated by reference) by issuance of the final rulemaking effective November 28, 2022. Based on this new end date for the fourth 1ST interval, the fifth 1ST interval will now begin on January 1, 2025, and will end on December 31, 2033. The 1ST interval will then reestablish the original pattern of intervals, unless DESC extends the fifth interval based on NRC approved methods.

In summary, the 1ST program plan end dates for the fourth and fifth 1ST intervals are December 31, 2024, and December 31, 2033, respectively.

Should you have any questions, please contact Yan Gao at (804) 273-2768.

Respectfully, Jam:t':lo

Vice President - Nuclear Engineering and Fleet Support

Commitments made in this letter: None.

Serial No.22-334 Docket No. 50-395 Page 2 of 3

cc:

U.S. Nuclear Regulatory Commission, Region II Marquis One Tower 245 Peachtree Center Avenue, NE Suite 1200 Atlanta, Georgia 30303-1257 Mr. G. Edward Miller NRC Senior Project Manager U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 09 E-3 11555 Rockville Pike Rockville, Maryland 20852-2738 NRC Senior Resident Inspector V.C. Summer Nuclear Station Ms. Anuradha Nair-Gimmi Bureau of Environmental Health Services Serial No.22-334 Docket No. 50-395 Page 3 of 3 South Carolina Department of Health and Environmental Control 2600 Bull Street Columbia, SC 29201 Mr. G. J. Lindamood Santee Cooper - Nuclear Coordinator 1 Riverwood Drive Moncks Corner, SC 29461