Presentation Slides - November 3, 2022, Public Meeting Between Holtec International and NRC Staff to Discuss Status and Schedule for the Licensing Review of the HI-STORE CISF License Application
ML22306A282
Person / Time
Site: HI-STORE
Issue date: 11/03/2022
From: Cuadrado J, Yoira Diaz-Sanabria
Storage and Transportation Licensing Branch, Division of Fuel Management
To:
References
Download: ML22306A282 (1)


Text

Public Meeting with Holtec International -

Update on Review Status and Schedule for HI-STORE CISF License Application Jose Cuadrado, Project Manager Yoira Diaz-Sanabria - Chief, Storage and Transportation Licensing Branch U.S. Nuclear Regulatory Commission November 3, 2022

Holtec HI-STORE CISF Safety Review

- Timeline

  • License application submitted to NRC on March 30, 2017; accepted for detailed review on February 28, 2018
  • NRC staff issued multiple requests for additional information (RAIs) to Holtec

- First Round RAIs issued in 6 parts (~300 items), issued April 2018 - August 2020

- Second Round RAI (~71 items), issued May 20, 2021, Holtec response completed October 29, 2021

- Third Round RAI (~45 items), issued March 23, 2022; Holtec response submitted April 15, 2022, supplemented August 15, 2022 All publicly available documents can be retrieved at:

https://www.nrc.gov/waste/spent-fuel-storage/cis/holtec-international.html 2

Holtec HI-STORE CISF Safety Review

- Path Forward

  • NRC staff to issue final licensing decision in February 2023

- NRC issued previous schedule letter on May 26, 2022:

  • Publication of Final EIS on July 2022; final licensing decision on January 2023

- Schedule letter sought additional clarification and supplement to 3rd Round RAI responses by June 2022

- Holtec submitted supplement to 3rd RAI on August 15, 2022

- Holtec to submit final revision of SAR and application documents by November 2022

  • Final SAR/application revisions provide editorial clarification; do not affect safety or environmental review findings

- NRC expects final licensing decision by February 2023 All publicly available documents can be retrieved at:

https://www.nrc.gov/waste/spent-fuel-storage/cis/holtec-international.html 3

Holtec HI- STORE CISF Environmental Review - Timeline

  • EIS public scoping process:

- Four-month scoping comment period (March 30 - July 30, 2018); NRC held 5 in-person public meetings in New Mexico, plus one nationwide webinar; received ~6,600 individual comments, received in-person, via email, website, and regular mail

  • Draft EIS issued March 9, 2020:

- Six-month public comment period; NRC held 6 nationwide virtual meetings/webinars; received ~5,000 individual comments

  • Final EIS issued on July 13, 2022:

- Documents the environmental impacts of the entire project from construction through decommissioning; recommends issuance of license, subject to completion of safety review

  • Supplement to Final EIS issued on October 27, 2022

- Provides response to two comment submissions (SRIC, NEI) that were inadvertently not included in July FEIS

- Supplement does not change findings from July 2022 FEIS, or affect schedule for final licensing decision All publicly available documents can be retrieved at:

https://www.nrc.gov/waste/spent-fuel-storage/cis/holtec-international.html 4

Holtec HI-STORE CISF -

Next Steps

  • Holtec to submit final revisions to SAR and application documents

- Expected by November 2022

  • NRC staff to complete safety review of SAR and application documents, complete final Safety Evaluation Report

- Final licensing decision expected in February 2023

- Will include publication of Record of Decision 5