ML22306A143
| ML22306A143 | |
| Person / Time | |
|---|---|
| Site: | Peach Bottom |
| Issue date: | 11/02/2022 |
| From: | Henry D Constellation Energy Generation |
| To: | Office of Nuclear Reactor Regulation, Document Control Desk |
| Shared Package | |
| ML22306A142 | List: |
| References | |
| CCN 22-82, TS 5.6.5.d | |
| Download: ML22306A143 (1) | |
Text
TS 5.6.5.d CCN 22-82 November 2, 2022 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Peach Bottom Atomic Power Station, Unit 2 Subsequent Renewed Facility Operating License No. DPR-44 NRC Docket No. 50-277
Subject:
Issuance of the Core Operating Limits Report for Reload 24, Cycle 25 Enclosed is a copy of Revision 18 of the Core Operating Limits Report (COLR) for Peach Bottom Atomic Power Station (PBAPS) Unit 2 for Reload 24, Cycle 25. This revision incorporates the modified cycle specific parameters resulting from the new core configuration as a result of the PBAPS Unit 2 refueling outage.
This COLR is being submitted to the NRC as required by the PBAPS, Unit 2 Technical Specifications (TS) Section 5.6.5.d.
If you have any questions concerning this letter, please contact the Peach Bottom Regulatory Assurance Manager, Wade Scott at (717) 456-3047.
Respectfully, David A. Henry Site Vice President Peach Bottom Atomic Power Station
Attachment:
Core Operating Limits Report for PBAPS Unit 2, Revision 18 cc:
Regional Administrator, Region I, USNRC (with attachment)
USNRC Senior Resident Inspector, PBAPS (with attachment)
Project Manager - PBAPS, USNRC (with attachment)
W. De Haas, Pennsylvania Bureau of Radiation Protection (with attachment)
S. Seaman, State of Maryland (with attachment)