Letter Sequence Supplement |
---|
|
|
MONTHYEARPMNS20210976, Pre-Submittal Meeting - Proposed Hatch TSTF-505 Lar(Provide Risk-Informed Extended Completion Times- RITSTF LAR 4b)2021-07-22022 July 2021 Pre-Submittal Meeting - Proposed Hatch TSTF-505 Lar(Provide Risk-Informed Extended Completion Times- RITSTF LAR 4b) Project stage: Meeting NL-21-0576, Units 1 and 2 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2021-10-26026 October 2021 Units 1 and 2 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Project stage: Request ML21321A3812021-11-16016 November 2021 NRR E-mail Capture - Acceptance Review - Hatch TSTF-505 LAR (L-2021-LLA-0199) Project stage: Acceptance Review ML21309A0002021-11-29029 November 2021 Regulatory Audit in Support of Review of the Application to Adopt Risk-Informed Extended Completion Times RITSTF Initiative 4B (EPID L-2021-LLA- 0199) Project stage: Approval ML22048C2232022-03-0101 March 2022 Audit Agenda and Questions for License Amendment Request to Adopt TSTF-505, Risk-Informed Extended Completion Times - RITSTF Initiative 4B Project stage: Other NL-22-0283, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf.2022-04-29029 April 2022 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf. Project stage: Supplement ML22140A1192022-05-20020 May 2022 NRR E-mail Capture - RAIs - Hatch, Units 1 and 2, TSTF-505 LAR Project stage: RAI ML22157A3542022-06-0606 June 2022 NRR E-mail Capture - RAI - Hatch, Units 1 and 2, TSTF-505 LAR Project stage: RAI ML22186A0022022-07-0707 July 2022 Audit Summary for License Amendment Request to Adopt Risk-Informed Extended Completion Times RITSTF Initiative 4B Project stage: Other NL-22-0590, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Exten2022-08-18018 August 2022 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Exten Project stage: Response to RAI NL-22-0757, Units 1 & 2, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-09-30030 September 2022 Units 1 & 2, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Project stage: Supplement NL-22-0832, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF .2022-10-27027 October 2022 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF . Project stage: Supplement ML22297A1462022-12-22022 December 2022 Issuance of Amendments Nos. 319 and 264, Regarding Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times RITS Project stage: Approval 2022-03-01
[Table View] |
Similar Documents at Hatch |
---|
Category:Letter type:NL
MONTHYEARNL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. NL-23-0889, Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems2023-12-0606 December 2023 Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems NL-23-0879, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0841, Update to Notice of Intent to Pursue Subsequent License Renewal2023-11-20020 November 2023 Update to Notice of Intent to Pursue Subsequent License Renewal NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use NL-23-0422, Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R272023-05-30030 May 2023 Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R27 NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 NL-23-0019, GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2023-04-12012 April 2023 GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI NL-23-0263, Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report2023-04-0505 April 2023 Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report NL-23-0208, Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update2023-03-29029 March 2023 Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding NL-23-0228, Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21)2023-03-20020 March 2023 Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21) NL-23-0179, National Pollutant Discharge Elimination System (NPDES) Permit Renewal2023-03-13013 March 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal NL-23-0101, Cycle 28 Core Operating Limits Report Version 12023-02-23023 February 2023 Cycle 28 Core Operating Limits Report Version 1 NL-23-0003, Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 12023-01-20020 January 2023 Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1 NL-23-0069, Correction of Technical Specification Omission and Typographical Error2023-01-20020 January 2023 Correction of Technical Specification Omission and Typographical Error NL-22-0316, Emergency License Amendment Request for Technical Specification 3.7.2 Regarding One-Time Extension of Completion Time for Plant Service Water (Psw) Pump Inoperable2022-11-30030 November 2022 Emergency License Amendment Request for Technical Specification 3.7.2 Regarding One-Time Extension of Completion Time for Plant Service Water (Psw) Pump Inoperable NL-22-0850, Supplement to License Amendment Request to Revise the NFPA 805 Fire Protection Program2022-11-18018 November 2022 Supplement to License Amendment Request to Revise the NFPA 805 Fire Protection Program NL-22-0832, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF .2022-10-27027 October 2022 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF . NL-22-0800, Supplement to Authorized Relief Request HNP-ISI-RR-05-022022-10-27027 October 2022 Supplement to Authorized Relief Request HNP-ISI-RR-05-02 NL-22-0801, Response to Request for Additional Information Regarding: Application to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-208, Revision 0, Extension of .2022-10-14014 October 2022 Response to Request for Additional Information Regarding: Application to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-208, Revision 0, Extension of . NL-22-0757, Units 1 & 2, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-09-30030 September 2022 Units 1 & 2, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b NL-22-0687, Notice of Intent to Pursue Subsequent License Renewal for Hatch Units 1 & 22022-08-31031 August 2022 Notice of Intent to Pursue Subsequent License Renewal for Hatch Units 1 & 2 NL-22-0406, Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes2022-08-19019 August 2022 Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes NL-22-0650, Units 1 and 2 - Response to Request for Confirmation of Information Regarding License Amendment Request to Revise the NFPA 805 Fire Protection Program2022-08-19019 August 2022 Units 1 and 2 - Response to Request for Confirmation of Information Regarding License Amendment Request to Revise the NFPA 805 Fire Protection Program NL-22-0590, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Exten2022-08-18018 August 2022 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Exten NL-22-0672, Registration of Spent Fuel Cask Use2022-08-17017 August 2022 Registration of Spent Fuel Cask Use NL-22-0564, and Vogtle Electric Generating Plant, Registration of Spent Fuel Cask Use2022-07-21021 July 2022 and Vogtle Electric Generating Plant, Registration of Spent Fuel Cask Use NL-22-0510, Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20212022-07-14014 July 2022 Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2021 NL-22-0499, Registration of Spent Fuel Cask Use2022-06-27027 June 2022 Registration of Spent Fuel Cask Use NL-22-0362, Southern Nuclear Operating Company, Inc. - Foreign Ownership, Control, or Influence Five-Year Renewal Filing and NRC Facility Clearance Update2022-06-0101 June 2022 Southern Nuclear Operating Company, Inc. - Foreign Ownership, Control, or Influence Five-Year Renewal Filing and NRC Facility Clearance Update NL-22-0365, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R302022-05-31031 May 2022 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R30 NL-22-0335, Supplement to Application to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.3 And.2022-05-17017 May 2022 Supplement to Application to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.3 And. NL-22-0344, Annual Radiological Environmental Operating Reports for 20212022-05-10010 May 2022 Annual Radiological Environmental Operating Reports for 2021 NL-22-0315, Technical Specification 5.6.6 Post Accident Monitoring Instrumentation Report for Drywell Temperature Indicator Inoperable for Greater than 30 Days2022-05-0404 May 2022 Technical Specification 5.6.6 Post Accident Monitoring Instrumentation Report for Drywell Temperature Indicator Inoperable for Greater than 30 Days NL-22-0325, Withdrawal of Emergency License Amendment Request for Technical Specification 3.7.2 Regarding One-Time Extension of Completion Time for Plant Service Water (Psw) Pump Inoperable2022-05-0303 May 2022 Withdrawal of Emergency License Amendment Request for Technical Specification 3.7.2 Regarding One-Time Extension of Completion Time for Plant Service Water (Psw) Pump Inoperable NL-22-0283, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf.2022-04-29029 April 2022 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf. NL-22-0271, Changes to the Physical Security Plan2022-04-19019 April 2022 Changes to the Physical Security Plan NL-22-0240, SNC Response to Regulatory Issue Summary 2022-01: Preparation and Scheduling of Operator Licensing Examinations2022-03-31031 March 2022 SNC Response to Regulatory Issue Summary 2022-01: Preparation and Scheduling of Operator Licensing Examinations NL-21-0918, License Amendment Request to Revise the NFPA 805 Fire Protection Program. with Attachments 3 to 52022-03-31031 March 2022 License Amendment Request to Revise the NFPA 805 Fire Protection Program. with Attachments 3 to 5 NL-22-0220, Units 1 and 2 - Nuclear Property Insurance Coverage as of April 1, 20222022-03-28028 March 2022 Units 1 and 2 - Nuclear Property Insurance Coverage as of April 1, 2022 NL-22-0221, Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21)2022-03-28028 March 2022 Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21) 2024-01-30
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARNL-23-0889, Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems2023-12-0606 December 2023 Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems NL-22-0316, Emergency License Amendment Request for Technical Specification 3.7.2 Regarding One-Time Extension of Completion Time for Plant Service Water (Psw) Pump Inoperable2022-11-30030 November 2022 Emergency License Amendment Request for Technical Specification 3.7.2 Regarding One-Time Extension of Completion Time for Plant Service Water (Psw) Pump Inoperable NL-22-0832, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF .2022-10-27027 October 2022 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF . NL-22-0757, Units 1 & 2, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-09-30030 September 2022 Units 1 & 2, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b NL-22-0406, Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes2022-08-19019 August 2022 Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes NL-22-0335, Supplement to Application to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.3 And.2022-05-17017 May 2022 Supplement to Application to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.3 And. NL-21-0918, License Amendment Request to Revise the NFPA 805 Fire Protection Program. with Attachments 3 to 52022-03-31031 March 2022 License Amendment Request to Revise the NFPA 805 Fire Protection Program. with Attachments 3 to 5 NL-22-0010, Application to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.3 and Administrative.2022-03-25025 March 2022 Application to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.3 and Administrative. NL-21-1037, License Amendment Request to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2022-02-0404 February 2022 License Amendment Request to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling NL-21-0784, License Amendment Request: Revise Technical Specifications to Adopt TSTF-227, Revision to EOC-RPT Pump Actions and TSTF-297, Enhancements to Required Actions for Feedwater and Main Turbine High Water Level Trip2021-12-13013 December 2021 License Amendment Request: Revise Technical Specifications to Adopt TSTF-227, Revision to EOC-RPT Pump Actions and TSTF-297, Enhancements to Required Actions for Feedwater and Main Turbine High Water Level Trip NL-21-0722, Units 1 and 2, License Amendment Request: Revise Technical Specifications to Adopt TSTF-207-A, Completion Time for Restoration of Various Excessive Leakage Rates2021-12-0606 December 2021 Units 1 and 2, License Amendment Request: Revise Technical Specifications to Adopt TSTF-207-A, Completion Time for Restoration of Various Excessive Leakage Rates NL-21-0576, Units 1 and 2 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2021-10-26026 October 2021 Units 1 and 2 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b NL-21-0385, Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements2021-09-29029 September 2021 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements NL-21-0852, Emergency License Amendment Request for Technical Specification 3.7.2 Regarding One-Time Extension of Completion Time for Plant Service Water (Psw) Pump Inoperable2021-09-21021 September 2021 Emergency License Amendment Request for Technical Specification 3.7.2 Regarding One-Time Extension of Completion Time for Plant Service Water (Psw) Pump Inoperable NL-21-0613, Supplement to License Amendment Request to Revise Technical Specification 5.7, High Radiation Area, .2021-06-30030 June 2021 Supplement to License Amendment Request to Revise Technical Specification 5.7, High Radiation Area, . NL-21-0160, License Amendment Request to Remove Table of Contents from Technical Specifications2021-06-22022 June 2021 License Amendment Request to Remove Table of Contents from Technical Specifications NL-21-0413, Supplement to Emergency License Amendment Request for Technical Specification 3.5.1 Re One-Time Extension of Completion Time for 2D RHR Pump2021-04-20020 April 2021 Supplement to Emergency License Amendment Request for Technical Specification 3.5.1 Re One-Time Extension of Completion Time for 2D RHR Pump NL-21-0411, Emergency License Amendment Request for Technical Specification 3.5.1 Regarding One-Time Extension of Completion Time for 2D RHR Pump2021-04-19019 April 2021 Emergency License Amendment Request for Technical Specification 3.5.1 Regarding One-Time Extension of Completion Time for 2D RHR Pump NL-21-0065, License Amendment Request to Revise Technical Specification 5.7, High Radiation Area, Administrative Controls2021-03-25025 March 2021 License Amendment Request to Revise Technical Specification 5.7, High Radiation Area, Administrative Controls NL-20-0949, License Amendment Request to Revise, Technical Specifications to Adopt TSTF-541, Revision 22020-10-30030 October 2020 License Amendment Request to Revise, Technical Specifications to Adopt TSTF-541, Revision 2 NL-20-0785, Southern Nuclear Operating Co - Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2020-08-28028 August 2020 Southern Nuclear Operating Co - Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements ML20224A4642020-08-11011 August 2020 Southern Nuclear Operating Co, Inc - Supplement to License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions NL-20-0843, License Amendment Request to Revise the Required Actions of Technical Specifications 3.8.1, AC Sources - Operating, for One-Time Extension of Completion Time for Unit 1 and Swing Emergency Diesel Generators2020-07-31031 July 2020 License Amendment Request to Revise the Required Actions of Technical Specifications 3.8.1, AC Sources - Operating, for One-Time Extension of Completion Time for Unit 1 and Swing Emergency Diesel Generators ML20192A1402020-06-30030 June 2020 Southern Nuclear Operating Co., Inc. - License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions NL-19-1455, Emergency License Amendment Request for Technical Specification 3.7.1 Regarding One-Time Extension of Completion Time for RHRSW Pump Inoperable2019-11-29029 November 2019 Emergency License Amendment Request for Technical Specification 3.7.1 Regarding One-Time Extension of Completion Time for RHRSW Pump Inoperable NL-19-1266, Supplement to License Amendment Request for Technical Specifications 3.3.8.1 and 3.8.1 Regarding Degraded Voltage Protection2019-10-17017 October 2019 Supplement to License Amendment Request for Technical Specifications 3.3.8.1 and 3.8.1 Regarding Degraded Voltage Protection NL-19-0355, Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems, Using the Consolidated Line Item Improvement Process2019-07-23023 July 2019 Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems, Using the Consolidated Line Item Improvement Process NL-19-0006, Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2019-07-15015 July 2019 Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML19123A1012019-04-30030 April 2019 License Amendment Request for Technical Specifications 3.3.8.1 and 3.8.1 Regarding Unit 1 Degraded Voltage Protection NL-19-0250, Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR2019-04-23023 April 2019 Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR NL-19-0173, Emergency License Amendment Request for Technical Specification 3.8.1 Regarding Voltage Limit Increase for Emergency Diesel Generator Load Rejection Surveillance Test2019-02-19019 February 2019 Emergency License Amendment Request for Technical Specification 3.8.1 Regarding Voltage Limit Increase for Emergency Diesel Generator Load Rejection Surveillance Test ML18226A0942018-08-0909 August 2018 Edwin I. Hatch, Units 1 and 2; and Vogtle, Units 1 and 2 - License Amendment Request to Revise Technical Specification 5.2.2.g and Update Emergency Plan Minimum On-shift Staff Tables NL-18-0601, Revision to Technical Specification End State for Residual Heat Removal Drywell Spray2018-08-0606 August 2018 Revision to Technical Specification End State for Residual Heat Removal Drywell Spray NL-16-0108, Units 1 and 2, License Amendment Request to Correct Non-Conservative Technical Specification Allowable Values for the Condensate Storage Tank Low Level Transfer Function2018-06-29029 June 2018 Units 1 and 2, License Amendment Request to Correct Non-Conservative Technical Specification Allowable Values for the Condensate Storage Tank Low Level Transfer Function NL-17-1962, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors.2018-06-0707 June 2018 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. NL-18-0630, Supplement to License Amendment Request to Adopt TSTF-542 Reactor Pressure Vessel Water Inventory Control2018-05-0101 May 2018 Supplement to License Amendment Request to Adopt TSTF-542 Reactor Pressure Vessel Water Inventory Control NL-18-0282, Edwin I. Hatch, Units 1 and 2, License Amendment Request to Adopt NFPA-805 Performance Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition)2018-04-0404 April 2018 Edwin I. Hatch, Units 1 and 2, License Amendment Request to Adopt NFPA-805 Performance Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) ML18096A9562018-04-0404 April 2018 Enclosure 2: NFPA 805 LAR Transition Report for Edwin I. Hatch (Redacted) NL-18-0282, Enclosure 1: NFPA 805 LAR Transition Report for Edwin I. Hatch2018-04-0404 April 2018 Enclosure 1: NFPA 805 LAR Transition Report for Edwin I. Hatch ML18096A9552018-04-0404 April 2018 License Amendment Request to Adopt NFPA-805 Performance Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) NL-18-0074, License Amendment Request for Technical Specification 3.3.8.1 Regarding Degraded Voltage Protection2018-03-0909 March 2018 License Amendment Request for Technical Specification 3.3.8.1 Regarding Degraded Voltage Protection NL-18-0206, Supplement to Application to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-02-19019 February 2018 Supplement to Application to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control NL-17-1088, Submittal of License Amendment Request, Relocation of the Emergency Operations Facility2017-08-30030 August 2017 Submittal of License Amendment Request, Relocation of the Emergency Operations Facility NL-17-0328, Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control.2017-04-20020 April 2017 Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control. NL-16-1582, Request for License Amendment to Address Secondary Containment Access Openings2017-04-0707 April 2017 Request for License Amendment to Address Secondary Containment Access Openings ML16340A0052016-12-0101 December 2016 License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Rev 4, Clarify Use and Application Rules. NL-16-1564, Revised Technical Specifications Pages for Technical Specifications Revision Request to Implement TSTF-500, DC Electrical Re-Write.2016-09-20020 September 2016 Revised Technical Specifications Pages for Technical Specifications Revision Request to Implement TSTF-500, DC Electrical Re-Write. NL-16-1328, License Amendment Request Concerning Safety Limit Minimum Critical Power Ratio2016-08-29029 August 2016 License Amendment Request Concerning Safety Limit Minimum Critical Power Ratio ML16245A2582016-08-29029 August 2016 License Amendment Request Concerning Safety Limit Minimum Critical Power Ratio NL-16-1390, License Amendment Request to Revise Technical Specification Section 5.5.12 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies, Correction to Attachment 32016-08-24024 August 2016 License Amendment Request to Revise Technical Specification Section 5.5.12 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies, Correction to Attachment 3 2023-12-06
[Table view] |
Text
Cheryl A. Gayheart 3535 Colonnade Parkway Regulatory Affairs Director Birmingham, AL 35243 205 992 5316 tel 205 992 7601 fax cagayhea@southernco.com October 27, 2022 Docket Nos.: 50-321 NL-22-0832 50-366 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Edwin I. Hatch Nuclear Plant - Units 1 and 2 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Ladies and Gentlemen:
On October 26, 2021 [ADAMS Accession Number ML21300A153], pursuant to the provisions of Section 50.90 of Title 10 of the Code of Federal Regulations, Southern Nuclear Operating Company (SNC) requested amendments to Edwin I. Hatch Nuclear Plant (HNP), Units 1 and 2 renewed facility operating licenses (RFOLs) DPR-57 and NPF-5, respectively. The proposed amendment requested U.S. Nuclear Regulatory Commission (NRC) approval to modify Technical Specifications (TS) requirements to permit the use of Risk Informed Completion Times in accordance with TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b [ML18183A493]. The LAR impacted several TS sections, including TS 3.3.4.1, TS 3.3.4.2, and TS 3.6.1.3.
On December 6, 2021, subsequent to the submittal of the HNP TSTF-505 license amendment request (LAR), SNC submitted a LAR to adopt certain aspects of TSTF-207 [ML21340A255].
On September 2, 2022, the NRC issued Amendments 317 and 262 to the HNP Units 1 and 2 RFOLs, respectively, approving SNCs Hatch TSTF-207 LAR [ML22192A117]. Amendments 317 and 262 include changes to some of the same pages in TS 3.6.1.3 as the HNP TSTF-505 LAR. To account for Amendments 317 and 262, SNC provided a supplement to the HNP TSTF-505 LAR on September 30, 2022 [ML22273A096].
On December 13, 2021, subsequent to the submittal of the HNP TSTF-505 LAR, SNC submitted a LAR to adopt TSTF-227 and TSTF-297 [ML21347A385] (with supplement dated February 1, 2022 [ML22033A073]). It is anticipated that the NRC will issue Amendments 318 and 263 to the HNP Units 1 and 2 RFOLs, respectively, approving the HNP TSTF-227/297 LAR prior to approving the HNP TSTF-505 LAR. Amendments 318 and 263 will include changes to some of the same pages in TS 3.3.4.1 and TS 3.3.4.2 as the HNP TSTF-505 LAR.
The Enclosure to this letter describes the TS markup changes due to Amendments 318 and 263 and assesses their impact on SNCs Hatch TSTF-505 LAR.
U. S. Nuclear Regulatory Commission NL-22-0832 Page 2 of 2 The Attachment to this letter updates the impacted TS markups, provided initially in the license amendment request dated October 26, 2021, to include the effects of Amendments 318 and 263. These markups supersede only the TS 3.3.4.1 and TS 3.3.4.2 markups provided in the initial license amendment request dated October 26, 2021.
SNC requests the same approval and implementation schedule as requested in its original application [ML21300A153]. The conclusions of the No Significant Hazards Consideration Determination and Environmental Consideration contained in the original application have been reviewed and are unaffected by this supplement.
In accordance with 10 CFR 50.91, SNC is notifying the State of Georgia of this supplement to license amendment request by transmitting a copy of this letter, with attachment, to the designated State Official.
This letter contains no regulatory commitments. If you have any questions, please contact Amy Chamberlain at 205.992.6361.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 27th day of October 2022.
Respectfully submitted, C. A. Gayheart Director, Regulatory Affairs Southern Nuclear Operating Company CAG/agq
Enclosure:
Assessment of Amendments 318 and 263 Impact on HNP TSTF-505 License Amendment Request
Attachment:
Revised TSTF-505 Markups Reflecting Amendments 318 and 263 cc: Regional Administrator, Region ll NRR Project Manager - Hatch Senior Resident Inspector - Hatch Director, Environmental Protection Division - State of Georgia RType: CHA02.004
Edwin I. Hatch Nuclear Plant - Units 1 and 2 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b" Enclosure to NL-22-0832 Assessment of Amendments 318 and 263 Impact on HNP TSTF-505 License Amendment Request
Enclosure to NL-22-0832 Assessment of Amendments 318 and 263 Impact on HNP TSTF-505 License Amendment Request
1.0 INTRODUCTION
On October 26, 2021 [ADAMS Accession Number ML21300A153], Southern Nuclear Operating Company (SNC) requested amendments to Edwin I. Hatch Nuclear Plant (HNP), Units 1 and 2 renewed facility operating licenses (RFOLs) DPR-57 and NPF-5, respectively. The proposed amendment requested U.S. Nuclear Regulatory Commission (NRC) approval to modify Technical Specifications (TS) requirements to permit the use of Risk Informed Completion Times in accordance with TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b [ML18183A493]. The LAR impacted several TS sections, including TS 3.3.4.1, EOC-RPT Instrumentation and TS 3.3.4.2, ATWS-RPT Instrumentation.
On December 13, 2021, subsequent to the submittal of the HNP TSTF-505 license amendment request (LAR), SNC submitted a LAR to adopt TSTF-227 and TSTF-297 [ML21347A385] (with supplement dated February 1, 2022 [ML22033A073]). It is anticipated that the NRC will issue Amendments 318 and 263 to the HNP Units 1 and 2 RFOLs, respectively, approving the HNP TSTF-227/297 LAR prior to approving the HNP TSTF-505 LAR. Amendments 318 and 263 will include changes to some of the same pages in TS 3.3.4.1 and 3.3.4.2 as the HNP TSTF-505 LAR.
2.0 DESCRIPTION
OF CHANGE AND ASSESSMENT OF IMPACT The issuance of HNP RFOL Amendments 318 and 263 will include issuance of revised TS pages 3.3-28 through 3.3-30, 3.3-32, and 3.3-33 (impacts TS 3.3.4.1 Condition A and Required Action C.1 and TS 3.3.4.2 Required Action D.1). The Hatch TSTF-505 LAR included changes to TS pages 3.3-28 and 3.3-29 (impacts the Completion Time for Required Actions A.1 and A.2), thus there is overlap in the affected pages. Table 1 provides descriptions of the changes and assess the impact Amendments 318 and 263 have on SNCs HNP TSTF-505 LAR.
Page 1 of 3
Enclosure to NL-22-0832 Assessment of Amendments 318 and 263 Impact on HNP TSTF-505 License Amendment Request Table 1: Descriptions of Changes and Assessment of Impact (Sheet 1 of 2)
TS Condition Amendment 318 and 263 HNP TSTF-505 LAR (1)(2)
Changes (3) Proposed Changes (3) Assessment of Impact to HNP TSTF-505 LAR TS 3.3.4.1 Revises Condition A as Adds following to the The addition of required to Condition A is an administrative follows: Completion Time for Required clarification. Without the word required, one could interpret Condition A Actions A.1 and A.2: Condition A as needing entry even if the fuel thermal limits were being One or more required applied instead of applying the operability requirements to the End of channels inoperable. OR Cycle Recirculation Pump Trip (EOC-RPT) instrumentation. This change clarifies that the EOC-RPT instrumentation would not be In accordance with the Risk required, and Condition A would not need to be entered, if the Informed Completion Time Minimum Critical Power Ratio limits are made applicable, as allowed Program by the Limiting Condition for Operation (LCO).
Due to the administrative nature of the Amendments 318 and 263 change, there is no impact to the HNP TSTF-505 LAR application of Risk Informed Completion Time (RICT) to Required Actions A.1 and A.2.
TS 3.3.4.1 Revises Required Action C.1 The Amendments 318 and 263 change adds clarity to TS 3.3.4.1 Condition C as follows: Required Action C.1. TS 3.3.4.1 already has provisions to remove the associated recirculation pump from service if the trip function is lost.
NOTE------------ However, the modified wording and note added to the TS provide Only applicable if additional clarity that the Required Action to remove the affected inoperable channel is recirculation pump from service is only applicable if the inoperable the result of an channel is the result of an inoperable RPT breaker.
inoperable RPT breaker.
Due to the administrative nature of the Amendments 318 and 263 change, and the fact that the HNP TSTF-505 LAR does not propose applying RICT to the Completion Time for Required Action C.1, there is Remove the associated no impact to the HNP TSTF-505 LAR application of RICT to Required affected recirculation pump Actions A.1 and A.2 aside from changes to background text in the TS from service. markups.
Page 2 of 3
Enclosure to NL-22-0832 Assessment of Amendments 318 and 263 Impact on HNP TSTF-505 License Amendment Request Table 1: Descriptions of Changes and Assessment of Impact (Sheet 2 of 2)
TS Condition Amendment 318 and 263 HNP TSTF-505 LAR (1)(2)
Changes (3) Proposed Changes (3) Assessment of Impact to HNP TSTF-505 LAR TS 3.3.4.2 Adds following to the Amendments 318 and 263 do not impact TS 3.3.4.2 Condition A or the Completion Time for Required associated Required Actions and Completion Times. Therefore, there is Condition A Actions A.1 and A.2: no impact to the HNP TSTF-505 LAR application of RICT to Required Actions A.1 and A.2.
OR In accordance with the Risk Informed Completion Time Program TS 3.3.4.2 Revises Required Action D.1 The Amendments 318 and 263 change adds clarity to TS 3.3.4.2 Condition D as follows: Required Action D.1. TS 3.3.4.2 already has provisions to remove the associated recirculation pump from service if the trip function is lost.
NOTE------------ However, the modified wording and note added to the TS provide Only applicable if additional clarity that the Required Action to remove the affected inoperable channel is recirculation pump from service is only applicable if the inoperable the result of an channel is the result of an inoperable RPT breaker.
inoperable RPT breaker.
Due to the administrative nature of the Amendments 318 and 263 change, and the fact that the HNP TSTF-505 LAR does not propose Remove the associated applying RICT to the Completion Time for Required Action D.1, there is affected recirculation pump no impact to the HNP TSTF-505 LAR aside from changes to from service. background text in the TS markups.
Notes:
- 1. Due to formatting of tracked changes, some text rolls to subsequent pages. Therefore, the changes are compared on a TS Condition basis.
- 2. Conditions listed apply to Unit 1 TS and Unit 2 TS pages.
- 3. Underline format (e.g., underline) text indicates added text, and strikethrough format (e.g., deleted) text indicates deleted text.
Page 3 of 3
Edwin I. Hatch Nuclear Plant - Units 1 and 2 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Attachment to NL-22-0832 Revised TSTF-505 Markups Reflecting Amendments 318 and 263 Note:
Blue underline indicates new text proposed in submittal dated October 26, 2021 Red strikethrough indicates deleted text proposed in submittal dated October 26, 2021 Green underline indicates new text added by Amendments 318 and 263 Grey strikethrough indicates text deleted by Amendments 318 and 263 Attachment consists of 8 pages, excluding this cover page
EOC-RPT Instrumentation 3.3.4.1 3.3 INSTRUMENTATION 3.3.4.1 End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation LCO 3.3.4.1 a. Two channels per trip system for each EOC-RPT instrumentation Function listed below shall be OPERABLE:
- 1. Turbine Stop Valve (TSV) - Closure; and
- 2. Turbine Control Valve (TCV) Fast Closure, Trip Oil Pressure - Low.
OR
- b. LCO 3.2.2, "MINIMUM CRITICAL POWER RATIO (MCPR)," limits for inoperable EOC-RPT as specified in the COLR are made applicable.
APPLICABILITY: THERMAL POWER 27.6% RTP.
ACTIONS
NOTE------------------------------------------------------------
Separate Condition entry is allowed for each channel.
CONDITION REQUIRED ACTION COMPLETION TIME A. One or more required A.1 Restore channel to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> channels inoperable. OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program OR (continued)
HATCH UNIT 1 3.3-28 Amendment No. 318
EOC-RPT Instrumentation 3.3.4.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. (continued) A.2 -----------NOTE------------
Not applicable if inoperable channel is the result of an inoperable breaker.
Place channel in trip. 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> OR In accordance with the Risk Informed Completion Time Program B. One or more Functions with B.1 Restore EOC-RPT trip 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> EOC-RPT trip capability not capability.
maintained.
OR AND B.2 Apply the MCPR limit 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> MCPR limit for inoperable for inoperable EOC-RPT not made EOC-RPT as specified applicable. in the COLR.
C. Required Action and C.1 -----------NOTE------------
associated Completion Only applicable if Time not met. inoperable channel is the result of an inoperable RPT breaker.
Remove the associated 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> affected recirculation pump from service.
OR C.2 Reduce THERMAL 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> POWER to < 27.6%
RTP.
HATCH UNIT 1 3.3-29 Amendment No. 318
ATWS-RPT Instrumentation 3.3.4.2 3.3 INSTRUMENTATION 3.3.4.2 Anticipated Transient Without Scram Recirculation Pump Trip (ATWS-RPT)
Instrumentation LCO 3.3.4.2 Two channels per trip system for each ATWS-RPT instrumentation Function listed below shall be OPERABLE:
- a. Reactor Vessel Water Level - ATWS-RPT Level; and
- b. Reactor Steam Dome Pressure - High.
APPLICABILITY: MODE 1.
ACTIONS
NOTE------------------------------------------------------------
Separate Condition entry is allowed for each channel.
CONDITION REQUIRED ACTION COMPLETION TIME A. One or more channels A.1 Restore channel to 14 days inoperable. OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program OR (continued)
HATCH UNIT 1 3.3-31 Amendment No. 266
ATWS-RPT Instrumentation 3.3.4.2 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. (continued) A.2 -----------NOTE------------
Not applicable if inoperable channel is the result of an inoperable breaker.
Place channel in trip. 14 days OR In accordance with the Risk Informed Completion Time Program B. One Function with B.1 Restore ATWS-RPT trip 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> ATWS-RPT trip capability capability.
not maintained.
C. Both Functions with C.1 Restore ATWS-RPT trip 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> ATWS-RPT trip capability capability for one not maintained. Function.
D. Required Action and D.1 -----------NOTE------------
associated Completion Only applicable if Time not met. inoperable channel is the result of an inoperable RPT breaker.
Remove the associated 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> affected recirculation pump from service.
OR D.2 Be in MODE 2. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> HATCH UNIT 1 3.3-32 Amendment No. 318
EOC-RPT Instrumentation 3.3.4.1 3.3 INSTRUMENTATION 3.3.4.1 End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation LCO 3.3.4.1 a. Two channels per trip system for each EOC-RPT instrumentation Function listed below shall be OPERABLE:
- 1. Turbine Stop Valve (TSV) - Closure; and
- 2. Turbine Control Valve (TCV) Fast Closure, Trip Oil Pressure - Low.
OR
- b. LCO 3.2.2, "MINIMUM CRITICAL POWER RATIO (MCPR)," limits for inoperable EOC-RPT as specified in the COLR are made applicable.
APPLICABILITY: THERMAL POWER 27.6% RTP.
ACTIONS
NOTE----------------------------------------------------------
Separate Condition entry is allowed for each channel.
CONDITION REQUIRED ACTION COMPLETION TIME A. One or more required A.1 Restore channel to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> channels inoperable. OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program OR (continued)
HATCH UNIT 2 3.3-28 Amendment No. 263
EOC-RPT Instrumentation 3.3.4.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. (continued) A.2 ------------NOTE-----------
Not applicable if inoperable channel is the result of an inoperable breaker.
Place channel in trip. 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> OR In accordance with the Risk Informed Completion Time Program B. One or more Functions with B.1 Restore EOC-RPT trip 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> EOC-RPT trip capability not capability.
maintained.
OR AND B.2 Apply the MCPR limit 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> MCPR limit for inoperable for inoperable EOC-RPT not made EOC-RPT as specified applicable. in the COLR.
C. Required Action and C.1 -----------NOTE------------
associated Completion Only applicable if Time not met. inoperable channel is the result of an inoperable RPT breaker.
Remove the associated 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> affected recirculation pump from service.
OR C.2 Reduce THERMAL 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> POWER to < 27.6%
RTP.
HATCH UNIT 2 3.3-29 Amendment No. 263
ATWS-RPT Instrumentation 3.3.4.2 3.3 INSTRUMENTATION 3.3.4.2 Anticipated Transient Without Scram Recirculation Pump Trip (ATWS-RPT)
Instrumentation LCO 3.3.4.2 Two channels per trip system for each ATWS-RPT instrumentation Function listed below shall be OPERABLE:
- a. Reactor Vessel Water Level - ATWS-RPT Level; and
- b. Reactor Steam Dome Pressure - High.
APPLICABILITY: MODE 1.
ACTIONS
NOTE------------------------------------------------------------
Separate Condition entry is allowed for each channel.
CONDITION REQUIRED ACTION COMPLETION TIME A. One or more channels A.1 Restore channel to 14 days inoperable. OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program OR (continued)
HATCH UNIT 2 3.3-31 Amendment No. 210
ATWS-RPT Instrumentation 3.3.4.2 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. (continued) A.2 ------------NOTE-----------
Not applicable if inoperable channel is the result of an inoperable breaker.
Place channel in trip. 14 days OR In accordance with the Risk Informed Completion Time Program B. One Function with B.1 Restore ATWS-RPT trip 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> ATWS-RPT trip capability capability.
not maintained.
C. Both Functions with C.1 Restore ATWS-RPT trip 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> ATWS-RPT trip capability capability for one not maintained. Function.
D. Required Action and D.1 -----------NOTE------------
associated Completion Only applicable if Time not met. inoperable channel is the result of an inoperable RPT breaker.
Remove the associated 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> affected recirculation pump from service.
OR D.2 Be in MODE 2. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> HATCH UNIT 2 3.3-32 Amendment No. 263