COL Docs - FW: Clarification Requested on 9.21.2022 Snoc VEGP 1-4 Single PSP, T&Qp, & SCP
ML22294A044
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 10/21/2022
From:
Office of Nuclear Reactor Regulation
To:
References
Download: ML22294A044 (3)


Text

From:

Billy Gleaves Sent:

Friday, October 21, 2022 9:12 AM To:

Vogtle PEmails

Subject:

FW: Clarification Requested on 9.21.2022 SNOC VEGP 1-4 single PSP, T&QP, &

SCP For record-keeping. As of the sending of this clarification, the staff had not enough information to know whether there was an issue to be discussed or not. So that was the purpose of this early interaction.

From: Billy Gleaves Sent: Thursday, October 20, 2022 1:38 PM To: William (Will) Garrett (wgarrett@southernco.com) <wgarrett@southernco.com>

Cc: Cayetano Santos <Cayetano.Santos@nrc.gov>; Victor Hall <Victor.Hall@nrc.gov>; Niry Simonian

<Niry.Simonian@nrc.gov>; John Lamb <John.Lamb@nrc.gov>

Subject:

Clarification Requested on 9.21.2022 SNOC VEGP 1-4 single PSP, T&QP, & SCP

Will, In order for the staff to know whether more review may be necessary of your subject plan, please review the staffs requested clarification below and respond within a reasonable period.

If you believe your response may take longer than a week, please provide an estimate for when you may respond.

In the September 26, 2022, letter from Southern Nuclear Operating Company (SNC) titled, Report of Changes Incorporated into Version 18-VEGP-2 of the Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan (ML22269A481) the licensees submittal is ambiguous and can be interpreted as if SNC has implemented its Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan for Unit 4 and should therefore be in compliance with 10 CFR 73.55 security requirements for all four units as of September 21, 2022. Specifically, in the cover letter SNC states, In accordance with the reporting requirements of 10 CFR 50.54(p), Southern Nuclear Operating Company (SNC) hereby submits a report containing a description of the changes incorporated into Version 18-VEGP-2 of the Vogtle Electric Generating Plant (VEGP) Physical Security Plan (PSP), which includes the Training and Qualification Plan and Safeguards Contingency Plan.

This created a single Physical Security Plan, Training and Qualification Plan and Safeguards Contingency Plan for Vogtle Units 1 through 4, which became effective as of September 21, 2022, and replaces the VEGP 3&4 PSP in its entirety. Several other examples exist in the Description of Changes that would lead staff to believe that SNC has implemented its physical security plan for Unit 4. For example:

  • Section 1.0 - Revised the section to add wording clarifying the applicability of the PSP to Vogtle Units 1 through 4.
  • Section 11.2.1 - Revised the description of the VEGP Units 1-4 vehicle barrier system (VBS) to accurately reflect the types of barriers utilized.
  • Section 11.3 - Revised the section to add a description of the co-located ISFSI PA boundary and add a statement that PA access control measures described in the PSP apply to both the Units 1-4 PA and the ISFSI PA.
  • App. C, Section 7.0 - Revised the description of the VEGP Units 1-4 vehicle barrier system (VBS) to accurately reflect the types of barriers utilized.

Staff is looking for clarification on whether Vogtle Electric Generating Plant, Unit 4, has implemented its Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan.

If you believe that a public meeting and discussion would be more appropriate, please let me know that too in your response.

Billy William (Billy) Gleaves Senior Project Manager NRR/Vogtle Project Office US Nuclear Regulatory Commission The contents of this message may be sensitive. If this message has been received in error, please delete it without reading it. Your receipt of this message is not intended to waive any applicable privilege. Do not disseminate this message without the permission of the author. Communications by this author do not represent NRC policy or staff positions and are not binding on the Commission.

Hearing Identifier:

Vogtle_COL_Docs_Public Email Number:

639 Mail Envelope Properties (DM6PR09MB4839E8128071E665369DB5FA9F2D9)

Subject:

FW: Clarification Requested on 9.21.2022 SNOC VEGP 1-4 single PSP, T&QP,

& SCP Sent Date:

10/21/2022 9:12:10 AM Received Date:

10/21/2022 9:12:12 AM From:

Billy Gleaves Created By:

Bill.Gleaves@nrc.gov Recipients:

"Vogtle PEmails" <Vogtle.PEmails@usnrc.onmicrosoft.com>

Tracking Status: None Post Office:

DM6PR09MB4839.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3907 10/21/2022 9:12:12 AM Options Priority:

Normal Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date: