MONTHYEARML24135A2542024-05-15015 May 2024 Deis Public Meeting May 15, 2024 ML24127A2392024-05-0707 May 2024 Presentation Slides for Monticello 2023 End-of-Cycle Meeting ML24127A1982024-05-0707 May 2024 Deis Presentation Slides ML23192A7552023-07-14014 July 2023 July 14, 2023 Alternative Request to Defer PVT of MO-2397 Pre-submittal Meeting Slides ML23157A0422023-06-0606 June 2023 2022 Monticello End-of-Cycle Meeting Presentation ML23086C0722023-03-27027 March 2023 Presentation Slide for Monticello Scoping Webinar, March 29, 2023 ML23081A0392023-03-22022 March 2023 Presentation Slide for Monticello Public Scoping Meeting, March 22, 2023 ML22255A2162022-09-13013 September 2022 Subsequent License Renewal Application- Public Meeting September 13, 2022, Applicant Slides ML22130A5852022-05-10010 May 2022 2021 Monticello and Prairie Island Nuclear Generating Plant End-of-Cycle Meeting Presentation ML22024A3722022-01-24024 January 2022 Pre-application Public Meeting Slides for Potential Relief Request Related to Excess Flow Check Valves at Monticello Nuclear Generating Plant ML21274A2762021-10-0505 October 2021 Public Preapplication Meeting Presentation for Fuel Oil Storage Tank Amendment ML21166A3792021-06-15015 June 2021 Units 1 and 2 2020 End-of-Cycle Meeting Presentation ML21032A2632021-02-0303 February 2021 Slides for Public Meeting with Xcel Energy to Discuss a Planned Amendment to Combine the Emergency Plans and Create a Common Emergency Offsite Facility for Monticello and Prairie Island ML20273A3102020-10-0202 October 2020 Xcel Energy Presentation for Forthcoming Public Meeting Related to Safety Limit Minimum Critical Power Ratio Amendment ML20055F8122020-02-27027 February 2020 Pre-Application Meeting - License Amendment Request - Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritsf Initiative 4b ML18039A0892018-02-0808 February 2018 Pre - Application Meeting Risk-Informed Exemption Request Regarding Exposed Structural Steel February 8, 2018 ML17293A4292017-10-23023 October 2017 Pre-Application Meeting October 23, 2017 ML17058A4842017-03-0202 March 2017 03/02/2017 Presentation Slides for the Exemption Request for Restoring Dry Shielded Canister (DSC) 11-15 Compliance to 10 CFR Part 72 Pre-Submittal Meeting ML17037D1172017-02-0707 February 2017 License Amendment Requests for Change in Emergency Plan Staff Augmentation Response Times Pre-Submittal Meeting for Prairie Island Nuclear Generating Plant Monticello Nuclear Generating Plant: February 7, 2017 ML17023A0652017-01-24024 January 2017 Pre-Submittal Call Regarding License Amendment Requests for Prairie Island Nuclear Generating Plant, Units 1 and 2 and Monticello Nuclear Generating Plant Emergency Action Level Scheme Changes ML16333A3112016-11-17017 November 2016 Excel Energy Meeting Presentation 11/17/2016 ML16312A5072016-11-0909 November 2016 Xcel Energy Presentation - Pre-Application Public Meeting on 11/09/2016 Re: Plan for Restoring DCS Nos. 11 - 16 (Monticello Nuclear Generating Plant, Independent Spent Fuel Storage Installation) (Docket No. 72-58, CAC No. L25156) ML15092A4802015-03-26026 March 2015 Annual Assessment Meeting - Slides ML14153A0242014-05-16016 May 2014 Xcel Energy'S Presentation Slides Supporting a May 16, 2014, Public Meeting to Discuss the Flood Hazard Reevaluation Schedule for the Monticello and Prairie Island Nuclear Generating Plants ML14108A4012014-03-31031 March 2014 Annual Assessment Meeting - Reactor Oversight Process 2013 Slides ML14108A4052014-03-31031 March 2014 EOC Meeting Licensee Slides ML13171A1522013-06-24024 June 2013 April 24, 2013, Summary of Public Meeting in City of Kewaunee to Make Post-Shutdown Decommissioning of Activities Report (PSDAR) Available for Public Comment ML13066A4462013-02-28028 February 2013 Xcel Energy Presentation Handout Supporting February 28, 2013, Pre-Application Meeting to Discuss Proposed Fuel Transition License Amendment Request ML12093A0982012-04-0202 April 2012 Slides Provided by Monticello Licensee for 4/3/12 Meeting Regarding Containment Accident Pressure Credit for EPU Operation ML12017A0482012-01-17017 January 2012 Handout for 1-17-12 Meeting Re. a Future Application for Amendment Concerning Fuel Storage Criticality Analysis ML0934908762009-12-15015 December 2009 Meeting Slides from December 15, 2009 - Mellla+ LAR ML0912505822009-05-0505 May 2009 Meeting Slides, Monticello, Preparation & Assessment for Hostile Action-based Drill. ML0835703272008-12-17017 December 2008 Meeting Slides, Independent Human Performance Focused Self-Assessment Results, Presented by (Northern States Power Company, Minnesota at Public Meeting ML0810604592008-04-14014 April 2008 Summary of Meeting with Nuclear Management Company, Regarding the Nrc'S 2007 End-of Cycle Assessment of the Monticello Nuclear Generating Plant Safety Performance ML0804504802008-02-13013 February 2008 2/13/08 Meeting Handout ML0800905242008-01-0909 January 2008 Meeting Handout, Nuclear Emergency Plan Submittal for Monticello & Prairie Island, Units 1 and 2 ML0727705082007-10-0303 October 2007 10/3/07 Meeting Handout, Steam Dryer Evaluation Approach for Monticello Extended Power Uprate (Epu). ML0715806062007-06-0505 June 2007 Handout for Pre-application Meeting for Monticello Extended Power Uprate ML0710204892007-04-0404 April 2007 Meeting Slides, Monticello Annual Assessment Meeting Reactor Oversight Process - Cy 2006. ML0705106742007-02-21021 February 2007 NMC Slides for Public Meeting, Conduct of Operations Action Plan Update. ML0609606112006-03-22022 March 2006 Open House Handout for Monticello Draft Supplemental EIS Public Meeting - Monticello Nuclear Genearting Plant ML0606703372006-03-0606 March 2006 NMC Presentation on Alternative Source Term - Full Scope ML0514404942005-05-19019 May 2005 Public Meeting Slides Monticello End-of-Cycle Plant Performance Assessment ML0513802172005-05-11011 May 2005 Presentation Slides Used at Meeting on May 11, 2005, Between the NRC and NMC to Discuss Monticello LRA ML0434900602004-11-30030 November 2004 NMC Slides for 11/30/04 Public Meeting ML0413803782004-05-0707 May 2004 NMC New Fuel Supplier Development Initiative ML17252A1571977-09-14014 September 1977 Summary of Meeting Held with Representatives of the Mark I Owner'S Group to Discuss the Structural Acceptance Criteria for the Mark I Containment Long Term Program 2024-05-07
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24135A2542024-05-15015 May 2024 Deis Public Meeting May 15, 2024 ML24127A2392024-05-0707 May 2024 Presentation Slides for Monticello 2023 End-of-Cycle Meeting ML24127A1982024-05-0707 May 2024 Deis Presentation Slides ML23262B2272023-09-21021 September 2023 September 21, 2023, Pre-Submittal Meeting on License Amendment Request to Revise PTLR to Incorporate New Surveillance Capsule Data (EPID L-2023-LRM-0070) (Slides) ML23192A7552023-07-14014 July 2023 July 14, 2023 Alternative Request to Defer PVT of MO-2397 Pre-submittal Meeting Slides ML23157A0422023-06-0606 June 2023 2022 Monticello End-of-Cycle Meeting Presentation ML23086C0722023-03-27027 March 2023 Presentation Slide for Monticello Scoping Webinar, March 29, 2023 ML23081A0392023-03-22022 March 2023 Presentation Slide for Monticello Public Scoping Meeting, March 22, 2023 ML22255A2162022-09-13013 September 2022 Subsequent License Renewal Application- Public Meeting September 13, 2022, Applicant Slides ML22130A5852022-05-10010 May 2022 2021 Monticello and Prairie Island Nuclear Generating Plant End-of-Cycle Meeting Presentation ML22067A0272022-03-16016 March 2022 Subsequent License Renewal Application Pre-Application Meeting March 16, 2022 ML22067A0672022-03-15015 March 2022 Pre-application Public Meeting 3/15/22 Slides-NRC ML22068A1222022-03-15015 March 2022 Pre-application Public Meeting 3/15/22 Slides - Applicant ML22024A3722022-01-24024 January 2022 Pre-application Public Meeting Slides for Potential Relief Request Related to Excess Flow Check Valves at Monticello Nuclear Generating Plant ML21274A2762021-10-0505 October 2021 Public Preapplication Meeting Presentation for Fuel Oil Storage Tank Amendment ML21166A3792021-06-15015 June 2021 Units 1 and 2 2020 End-of-Cycle Meeting Presentation ML21082A4702021-03-25025 March 2021 Xcel Presentation for Monticello Pre-Application Public Meeting to Adopt Advanced Framatome Methods ML21032A2632021-02-0303 February 2021 Slides for Public Meeting with Xcel Energy to Discuss a Planned Amendment to Combine the Emergency Plans and Create a Common Emergency Offsite Facility for Monticello and Prairie Island ML20212L8622020-07-29029 July 2020 2019 Monticello and Prairie Island EOC Presentation from Webinar ML20055F8122020-02-27027 February 2020 Pre-Application Meeting - License Amendment Request - Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritsf Initiative 4b ML18039A0892018-02-0808 February 2018 Pre - Application Meeting Risk-Informed Exemption Request Regarding Exposed Structural Steel February 8, 2018 ML17346A0842017-12-12012 December 2017 Pre-Application Meeting License Amendment for TSTF-425 Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program Xcel Energy Monticello Nuclear Generating Plant ML17293A4292017-10-23023 October 2017 Pre-Application Meeting October 23, 2017 ML17058A4842017-03-0202 March 2017 03/02/2017 Presentation Slides for the Exemption Request for Restoring Dry Shielded Canister (DSC) 11-15 Compliance to 10 CFR Part 72 Pre-Submittal Meeting ML17037D1172017-02-0707 February 2017 License Amendment Requests for Change in Emergency Plan Staff Augmentation Response Times Pre-Submittal Meeting for Prairie Island Nuclear Generating Plant Monticello Nuclear Generating Plant: February 7, 2017 ML17023A0652017-01-24024 January 2017 Pre-Submittal Call Regarding License Amendment Requests for Prairie Island Nuclear Generating Plant, Units 1 and 2 and Monticello Nuclear Generating Plant Emergency Action Level Scheme Changes ML16312A5072016-11-0909 November 2016 Xcel Energy Presentation - Pre-Application Public Meeting on 11/09/2016 Re: Plan for Restoring DCS Nos. 11 - 16 (Monticello Nuclear Generating Plant, Independent Spent Fuel Storage Installation) (Docket No. 72-58, CAC No. L25156) ML16323A3292016-09-23023 September 2016 Flood Hazard Reevaluation Report - Response to Requested Information ML15092A4802015-03-26026 March 2015 Annual Assessment Meeting - Slides ML15092A4822015-03-26026 March 2015 EOC Licensee Meeting Slides ML14323A9372014-11-19019 November 2014 Regcon, November 19-29, 2014: 02-Panel-3 Presentation Michael Baumann - Ope Experiences Monticello ML14153A0242014-05-16016 May 2014 Xcel Energy'S Presentation Slides Supporting a May 16, 2014, Public Meeting to Discuss the Flood Hazard Reevaluation Schedule for the Monticello and Prairie Island Nuclear Generating Plants ML14108A4012014-03-31031 March 2014 Annual Assessment Meeting - Reactor Oversight Process 2013 Slides ML14108A4052014-03-31031 March 2014 EOC Meeting Licensee Slides ML13171A1522013-06-24024 June 2013 April 24, 2013, Summary of Public Meeting in City of Kewaunee to Make Post-Shutdown Decommissioning of Activities Report (PSDAR) Available for Public Comment ML13066A4462013-02-28028 February 2013 Xcel Energy Presentation Handout Supporting February 28, 2013, Pre-Application Meeting to Discuss Proposed Fuel Transition License Amendment Request ML12093A0982012-04-0202 April 2012 Slides Provided by Monticello Licensee for 4/3/12 Meeting Regarding Containment Accident Pressure Credit for EPU Operation ML12017A0482012-01-17017 January 2012 Handout for 1-17-12 Meeting Re. a Future Application for Amendment Concerning Fuel Storage Criticality Analysis ML0934908762009-12-15015 December 2009 Meeting Slides from December 15, 2009 - Mellla+ LAR ML0912505822009-05-0505 May 2009 Meeting Slides, Monticello, Preparation & Assessment for Hostile Action-based Drill. ML0835703302008-12-22022 December 2008 Licensee (Northern States Power Company, Minnesota) Slides Presented at Public Meeting: Human Performance Assessment and Improvement ML0835703272008-12-17017 December 2008 Meeting Slides, Independent Human Performance Focused Self-Assessment Results, Presented by (Northern States Power Company, Minnesota at Public Meeting ML0828903572008-10-15015 October 2008 Meeting Slides, Monticello Extended Power Uprate Resubmittal ML0810604592008-04-14014 April 2008 Summary of Meeting with Nuclear Management Company, Regarding the Nrc'S 2007 End-of Cycle Assessment of the Monticello Nuclear Generating Plant Safety Performance ML0800905242008-01-0909 January 2008 Meeting Handout, Nuclear Emergency Plan Submittal for Monticello & Prairie Island, Units 1 and 2 ML0710204892007-04-0404 April 2007 Meeting Slides, Monticello Annual Assessment Meeting Reactor Oversight Process - Cy 2006. ML0705106742007-02-21021 February 2007 NMC Slides for Public Meeting, Conduct of Operations Action Plan Update. ML0625401632006-09-0808 September 2006 Slides: Accelerated ISTS Conversion (Piilot) by P. Hearn, NRR ML0615106012006-05-23023 May 2006 EPRI HRA Users Group Review of Draft NUREG-1842 ML0614302562006-05-17017 May 2006 Public Meeting NRC Presentation Slides Monticello Plant Performance Annual Assessment 2024-05-07
[Table view] |
Text
MONTICELLO NUCLEAR GENERATING PLANT SUBSEQUENT LICENSE RENEWAL APPLICATION
Public Meeting September 13, 2022
1 Public Meeting, MNGP SLRA
Purpose of Meeting:
- 1. Share examples of CAT 1 issue analysis to be provided and obtain NRC feedback
22 AGENDA 1.Opening Remarks NRC XCEL Energy 2.MNGP Examples of CAT 1 issue analysis presented in ER 3.Questions / Feedback 4.Closing Remarks XCEL NRC OPENING REMARKS 1.NRC 2.XCEL MNGP SLR ER Project Team Scott McCall, Director of Nuclear Fleet Operations Paul Young, Manager Site Routine Projects Steve Sollom, Senior Engineer, PE, SLR Tom Slavonic, ER Project Manager (ENERCON)
Rachel Turney-Work, ER Technical Lead (ENERCON)
Discussion of Generic Examples
- Effect of Feb. 24, 2022 NRC Memoranda and Orders on MNGP SLR ER Content:
- The Commission provided applicants the option of proceeding in site-specific manner
- Xcel is including site-specific analysis of Category 1 issues in Chapter 4 of the ER
- Accordingly Section 5 will be modified
- Generic example No. 1: Land Use and Visual Resources
- Generic Example No. 2: Scouring Caused by Discharge Cooling Water
5 Generic Example No. 1: Land Use and Visual Resources
4.1 LAND USE AND VISUAL RESOURCES
Impacts to land use and visual resources are evaluated in the GEIS and are considered to be generic (the same or similar at all plants). The following sections address the land use issues applicable to MNGP, providing background and environmental analyses representing the proposed SLR operating term.
4.1.1 Generic Analysis for Initial License Renewals [GEIS Section 4.2.1.1]
Operational activities at a nuclear power plant during the license renewal term would be similar to those occurring during the current license term. Generally, onsite land use conditions would remain unchanged.
However, additional spent nuclear fuel and low-level radioactive waste generated during the license renewal term could require the construction of new or expansion of existing onsite storage facilities. Should additional storage facilities be required, this action would be addressed in separate license reviews conducted by the NRC.
Refurbishment activities, such as steam generator and vessel head replacement, have not permanently changed onsite land use conditions.
For initial license renewals, the NRC codified its conclusion that changes in onsite land use from continued operations and refurbishment associated with license renewal would be a small fraction of the nuclear power plant site and would involve only land that is controlled by the licensee. The NRC found the impact for this issue to be SMALL.
6 Generic Example No. 1: Land Use and Visual Resources (Cont.)
4.1.2 Site-Specific Analysis for MNGP SLR
Onsite land use information is discussed in Section 3.2.1 of this ER. No license renewal-related refurbishment activities have been identified, as presented in Section 2.3. As discussed in Section 3.1.4, currently planned projects include the replacement of the cooling towers within the existing cooling tower footprints and the installation of a new ISFSI pad within the existing ISFSI fenced area. These projects do not change existing onsite land uses. Continued operation of MNGP during the proposed SLR term is not expected to change and no refurbishment activities are anticipated, and therefore no changes to onsite land use are projected. As to this issue, the 2013 GEIS analysis of the incremental effects of a 20- year renewal does not materially differ between an initial 20-year renewal period and a second 20-year renewal period.
Thus, the 2013 GEIS analysis of land use and visual resources remains valid and applicable to one SLR term for MNGP as supported by the Site-Specific Analysis. Based on the discussion above and that no new and significant information was identified, Xcel finds that collectively, the Generic Analysis for Initial License Renewal and the Site-Specific Analysis for MNGP SLR demonstrates that impacts to onsite land uses for the proposed SLR term are SMALL.
7 Generic Example No. 2: Scouring Caused by Discharged Cooling Water 4.5 WATER RESOURCES Site-specific impacts to water resources are discussed below.
4.5.7 Scouring Caused by Discharged Cooling Water 4.5.7.1 Generic Analysis for Initial License Renewals [GEIS Section 4.5.1.1]
The high flow rate of water from a cooling system discharge structure has the potential to scour sediments and redeposit them elsewhere. While scouring is possible during reactor startup, operational periods would typically have negligible scouring. Scouring is expected to occur only in the vicinity of the discharge structure where flow rates are high. Scouring has been observed at only three nuclear power plants and the effects were localized and minor. The NRC reviewed the impacts of scouring caused by discharged cooling water and found the impacts during the license renewal term would be SMALL for all plants.
For initial license renewals, the NRC codified its conclusion that scouring effects would be limited to the area in the vicinity of the intake and discharge structures. These impacts have been SMALL at operating nuclear power plants.
8 Generic Example No. 2: Scouring Caused by Discharged Cooling Water (Cont.)
4.5.7.2 S i te-Specific Analysis for MNGP SLR The discharge canal is separated from the Mississippi River by a discharge weir. The discharge weir consists of an earth filled dike and a vertical sheet-pile overflow section. The crest level of the 54 -foot-wide weir structure is at 910 feet msl.
The water elevation in the discharge canal is at 912.5 feet msl; therefore, the height of the overflow is 2.5 feet. When the water is at this level, the overflow section discharges at a rate of 645 c fs to the river. To prevent scouring below the discharge, a 20-foot-long concrete apron was built on the downstream side of the sheet pile wall, and a 50 -foot-long rip-rap apron was built downstream of the concrete apron. (Section 20 2.2.3.1 )
There are no plant operations or modifications planned for the proposed SLR operating term that would alter discharge patterns and flow rates. (Section 2.2 )
The GEIS determined continued operation of a nuclear plant in a license renewal term to have a small impact due to scouring caused by cooling water discharge. As to this issue, the 2013 GEIS analysis of the incremental effects of a 20 -year renewal does not materially differ between an initial 20 -year renewal period and a second 20 -year renewal period.
Thus, the 2013 GEIS analysis of scouring caused by discharged cooling water remains valid and applicable to one SLR term for MNGP as supported by the Site-Specific Analysis. Based on the discussion above and that no new and significant information was identified, Xcel finds that collectively, the Generic Analysis for Initial License Renewal and the Site-Specific Analysis for MNGP SLR demonstrates that impacts to onsite land uses for the proposed SLR term are SMALL.
9 Questions and/or Feedback
10 Closing Remarks