MONTHYEARML24025A9362024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0055 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000263/20230042024-01-31031 January 2024 Integrated Inspection Report 05000263/2023004 ML24024A0722024-01-24024 January 2024 Independent Spent Fuel Storage Installation, Onticello, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000263/20244012024-01-22022 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2024401 L-MT-23-054, Subsequent License Renewal Application Supplement 82024-01-11011 January 2024 Subsequent License Renewal Application Supplement 8 L-MT-23-047, License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data2023-12-29029 December 2023 License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data L-MT-23-056, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 22023-12-18018 December 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 2 ML23349A0572023-12-15015 December 2023 and Independent Spent Fuel Storage Installation, Revision to Correspondence Service List for Northern States Power - Minnesota IR 05000263/20234022023-12-13013 December 2023 Security Baseline Inspection Report 05000263/2023402 L-MT-23-042, 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462023-12-11011 December 2023 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 L-MT-23-052, Subsequent License Renewal Application Supplement 72023-11-30030 November 2023 Subsequent License Renewal Application Supplement 7 L-MT-23-051, Update to the Technical Specification Bases2023-11-28028 November 2023 Update to the Technical Specification Bases L-MT-23-049, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 12023-11-21021 November 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 ML23319A3182023-11-15015 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000263/20230032023-11-13013 November 2023 Integrated Inspection Report 05000263/2023003 and 07200058/2023001 L-MT-23-043, 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-092023-11-13013 November 2023 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-09 L-MT-23-038, License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.62023-11-10010 November 2023 License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 L-MT-23-046, Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 12023-11-0909 November 2023 Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 1 ML23291A1102023-10-23023 October 2023 Environmental Audit Summary and RCIs and RAIs ML23285A3062023-10-12012 October 2023 Implementation of the Fleet Standard Emergency Plan for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant L-MT-23-041, Subsequent License Renewal Application Response to Request for Confirmation of Information Set 22023-10-0303 October 2023 Subsequent License Renewal Application Response to Request for Confirmation of Information Set 2 L-MT-23-037, Subsequent License Renewal Application Response to Request for Additional Information Set 32023-09-22022 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 3 ML23262B0372023-09-19019 September 2023 Response to NRC Request for Additional Information Regarding the 2023 Monticello and Prairie Island Plant Decommissioning Funding Status Reports ML23248A2092023-09-18018 September 2023 Proposed Alternative VR-11 to the Requirements of the ASME OM Code Associated with Periodic Verification Testing of MO-2397, Reactor Water Cleanup Inboard Isolation Valve ML23256A1682023-09-13013 September 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Voluntary Security Clearance Program 2023 Insider Threat Program Self-Inspection IR 05000263/20230102023-09-0707 September 2023 Commercial Grade Dedication Inspection Report 05000263/2023010 L-MT-23-036, Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 62023-09-0505 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 6 ML23214A2412023-08-31031 August 2023 Letter: Aging Management Audit - Monticello Unit 1 - Subsequent License Renewal Application IR 05000263/20230052023-08-30030 August 2023 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2023005) L-MT-23-035, Subsequent License Renewal Application Supplement 52023-08-28028 August 2023 Subsequent License Renewal Application Supplement 5 ML23241A9732023-08-21021 August 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application (Docket No. 50-263) L-MT-23-034, Subsequent License Renewal Application Response to Request for Additional Information Set 12023-08-15015 August 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 1 ML23222A0122023-08-10010 August 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Changes in Foreign Ownership, Control or Influence ML23215A1312023-08-0909 August 2023 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application IR 05000263/20230022023-08-0707 August 2023 Plantintegrated Inspection Report 05000263/2023002 L-MT-23-028, 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report2023-07-31031 July 2023 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report L-MT-23-032, 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-112023-07-31031 July 2023 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-11 ML23198A0412023-07-28028 July 2023 LRA Availability Letter ML23206A2342023-07-25025 July 2023 Independent Spent Fuel Storage Installation, and Monticello Nuclear Generating Plant, Changes in Foreign Ownership, Control or Influence ML23201A0352023-07-24024 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23202A0032023-07-21021 July 2023 Independent Spent Fuel and Independent Spent Fuel Storage Installation, Monticello Nuclear Generating Plant, Submittal of Quality Assurance Topical Report (NSPM-1) L-MT-23-031, Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 12023-07-18018 July 2023 Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 1 ML23195A1732023-07-14014 July 2023 Revision of Standard Practice Procedures Plan IR 05000263/20235012023-07-13013 July 2023 Emergency Preparedness Inspection Report 05000263/2023501 2024-01-31
[Table view] |
Text
July 29, 2022 Mr. Christopher P. Domingos Site Vice President Northern States Power Company - Minnesota Monticello Nuclear Generating Plant 2807 West County Road 75 Monticello, MN 55362
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT - CLOSEOUT OF BULLETIN 2012-01, DESIGN VULNERABILITY IN ELECTRIC POWER SYSTEM
Dear Mr. Domingos:
The purpose of this letter is to inform you that the U.S. Nuclear Regulatory Commission (NRC) staff has verified that Northern States Power Company (the licensee) has provided the necessary information requested in NRCs Bulletin 2012-01, Design Vulnerability in Electric Power System dated July 27, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12074A115), for Monticello Nuclear Generating Plant (Monticello).
The NRC staff has completed its review of this information and this letter closes out Bulletin 2012-01 for Monticello.
The NRC issued Bulletin 2012-01 to all holders of operating licenses and combined licenses for nuclear power reactors, except those who have permanently ceased operation and have certified that fuel has been removed from the reactor vessel. The bulletin requested information about each facilitys electric power system designs that would allow the NRC staff to verify the systems capability to address open phase conditions. Specifically, the NRC requested licensees to provide the following information:
A description of how the protection scheme for engineered safety features buses (Class 1E for current operating plants or non-Class 1E for passive plants) is designed to detect and automatically respond to a single-phase open circuit condition or high impedance ground fault condition on offsite power circuits or another power source; and A description of the operating configuration of engineered safety features buses (Class 1E for current operating plants or non-Class 1E for passive plants) at power (i.e., normal operating condition).
By letter dated October 22, 2012 (ML12297A138), the licensee provided its response to Bulletin 2012-01 for Monticello. By letter dated January 30, 2014 (ML14031A088), the licensee provided supplemental information for this facility in response to an NRC staff request for additional information issued on December 20, 2013 (ML13351A314).
By letters dated October 9, 2013 (ML13333A147), and March 16, 2015 (ML15075A454), the Nuclear Energy Institute (NEI) submitted a voluntary industry initiative to address open phase conditions at nuclear power plants. The NEI letter dated March 16, 2015, stated, in part: The
C. Domingos initiative is a formal commitment by the companies that operate nuclear power plants to follow a specific policy or plan of action. The initiative calls for a proactive plan and schedule for addressing potential design vulnerabilities to the open phase condition.
To evaluate the adequacy of the open phase isolation systems designs, the NRC staff inspected four nuclear power plants with four distinct open phase isolation system designs using the NRC Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems (NRC Bulletin 2012-01), dated October 31, 2017 (ML17137A416). A summary of the NRC staffs preliminary observations and issues needing additional clarity were discussed with industry representatives in two public meetings conducted on September 19, 2018, and October 17, 2018. The meeting summaries can be found in ADAMS under Package Accession Nos. ML18268A342 and ML18309A226, respectively.
By letter dated June 6, 2019 (ML19163A176), NEI submitted Revision 3 of the voluntary industry initiative to include an option for plants to perform a risk evaluation under certain boundary conditions to support manual response to an open phase condition. NEI also submitted NEI 19-02, Guidance for Assessing Open Phase Condition Implementation Using Risk Insights on June 20, 2019 (ML19172A086). On August 18, 2020, the NRC staff issued Revision 2 of TI 2515/194 (ML20230A328), which provided temporary inspection instructions for the purpose of verifying that licensees appropriately implemented Revision 3 of the NEI voluntary industry initiative.
In August 2021, the NRC staff performed an inspection at Monticello using TI 2515/194, Revision 2. The inspection was performed to verify the licensees implementation of the voluntary industry initiative at this facility. To address the open phase condition design vulnerability issue at Monticello, the licensee implemented open phase isolation system plant modifications, which provide detection and alarm in the control room, and necessary plant procedures that allow operators to diagnose and take manual action to mitigate an open phase condition. The NRC staff documented the results of the TI 2515/194 inspection in a report dated September 29, 2021 (ML21272A212).
The NRC staff reviewed the information submitted by the licensee and the results of the TI 2515/194 inspection for Monticello. Based on this review, the NRC staff concludes that the licensee provided the necessary information requested in Bulletin 2012-01 and has completed the implementation of its open phase isolation system. Therefore, the NRC staff closes Bulletin 2012-01 for Monticello.
C. Domingos If you have any questions, please contact me at 301-415-3733 or Robert.Kuntz@nrc.gov.
Sincerely,
/RA/
Robert Kuntz, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-263 cc: Listserv
ML22189A019 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DEX/EEEB/BC NAME RKuntz SRohrer WMorton DATE 7/7/2022 7/11/2022 7/5/2022 OFFICE NRR/DRA/APOB/BC NRR/DRO/IOEB/BC NRR/DORL/LPL3/BC NAME AZoulis LRegner NSalgado DATE 7/15/2022 7/26/2022 7/26/2022 OFFICE NRR/DORL/LPL3/PM NAME RKuntz DATE 7/29/2022