ML22187A278
| ML22187A278 | |
| Person / Time | |
|---|---|
| Site: | 99900880 |
| Issue date: | 07/07/2022 |
| From: | Kerri Kavanagh NRC/NRR/DRO/IQVB |
| To: | Steen D Ultra Energy |
| Odunayo Ayegbusi 301-415-8107 | |
| References | |
| IR 2022001 | |
| Download: ML22187A278 (2) | |
Text
Ms. Diane Steen Director of Quality Ultra Energy 707 Jeffrey Way Round Rock, TX 78665
SUBJECT:
POSTPONEMENT OF PREVIOUSLY ANNOUNCED INSPECTION NO. 99900880/2022-001
Dear Ms. Steen:
As discussed in a letter dated June 15, 2022, (Agencywide Document Access and Management System Accession No. ML22166A374), the Nuclear Regulatory Commission (NRC) planned to perform an inspection of Ultra Energy (Ultra) to review the implementation of Ultras quality assurance program in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B and 10 CFR Part 21. The letter discussed a preliminary schedule for the inspection. The NRC inspection team planned to arrive at your facility in Round Rock, TX on Monday, July 18, 2022, and conduct the inspection through Friday, July 22, 2022. Due to the ongoing pandemic associated with the Coronavirus, specifically the increasing positivity rate in Williamson County, TX, where Ultras facility is located, the NRC has decided to postpone the inspection at this time. The NRC will contact you in the future to reschedule this inspection.
Please contact Mr. Odunayo Ayegbusi at 301-415-8107 or via electronic mail at Odunayo.Ayegbusi@nrc.gov, if you have any questions or need assistance regarding this matter.
Sincerely, Kerri A. Kavanagh, Chief Quality Assurance and Vendor Inspection Branch Division of Reactor Oversight Office of Nuclear Reactor Regulation Docket No.: 99900880 July 7, 2022 Signed by Kavanagh, Kerri on 07/07/22
ML22187A278 NRR-106 OFFICE NRR/DRO/IQVB NRR/DRO/IQVB NAME OAyegbusi KKavanagh DATE 07/7/2022 07/7/2022