MONTHYEARML24023A6952024-01-26026 January 2024 Westinghouse Columbia Fuel Fabrication Facility, U.S. Nuclear Regulatory Commission Inspection Report Number 07001151/2023004 ML24017A2252024-01-22022 January 2024 Westinghouse Electric Company, LLC, Conveyance of Revised Standby Trust Agreement to Support the Decommissioning Funding Plan (Enterprise Project Identifier L-2023-DFA-0009) ML23349A2722023-12-14014 December 2023 Westinghouse, Submittal of Monthly Progress Reports Under Consent Agreement 19-02-HW with the South Carolina Department of Health and Environmental Control ML23338A3372023-12-0404 December 2023 Submittal of Amendment 4 to Standby Trust Agreement (STA) for License Nu. SNM-1107, Replacement of Trust Fund with Additional Surety Bonds, and Certification of Financial Assurance for SNM-1107 ML23311A0032023-11-0606 November 2023 Westinghouse Columbia Fuel Fabrication Facility, U.S. Nuclear Regulatory Commission Inspection Report Number 70-1151/2023-402 (Cover Letter) ML23296A0362023-10-24024 October 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151/2023003 ML23240A5082023-08-28028 August 2023 Westinghouse Electric Company LLC - NRC Semi-Annual Discharge Report (January- June 2023) ML23230B2022023-08-18018 August 2023 Westinghouse, Supplemental Information for Request for Modification to Temporary License Conditions for Sampling, Analysis and Disposition of Hematite Ash Material ML23216A0712023-08-0404 August 2023 Westinghouse Columbia Fuel Fabrication Facility Physical Security Core Inspection Report 07001151/202340 ML23202A1472023-07-24024 July 2023 Westinghouse Columbia Fuel Fabrication Facility Integrated Inspection Report 07001151/2023002 ML23150A2362023-07-0303 July 2023 Letter to Westinghouse Regarding Effluent Testing Issue ML23184A1512023-06-29029 June 2023 Westinghouse Columbia Fuel 2023 Special Nuclear Material Inventory Summary Report Revision ML23171B1502023-06-20020 June 2023 Westinghouse Columbia Fuel 2023 Special Nuclear Material Inventory Summary Report ML23160A2612023-06-0909 June 2023 Westinghouse, Request for Modification to Temporary License Conditions for Sampling, Analysis and Disposition of Hematite Ash Material ML23139A1942023-06-0505 June 2023 Westinghouse Electric Company LLC - Approval of Environmental Sampling and Monitoring Program ML23138A3762023-05-18018 May 2023 Westinghouse Submittal of Columbia Fuel Fabrication Facility Site Emergency Plan, Revision 23 ML23096A2812023-05-15015 May 2023 Letter - Transfer of Control Approval 2023 ML23094A1582023-05-0505 May 2023 Westinghouse Electric Company, LLC - Revision to Temporarily Store Hematite Ash Above License Limits and Removal of Uranium Flywheel ML23115A2382023-04-26026 April 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151/2023001 ML23114A3592023-04-24024 April 2023 Westinghouse Submittal of Environmental Sampling and Monitoring Program for NRC Review and Approval ML23114A3612023-03-23023 March 2023 Enclosures 2 & 3 - SCDHEC Approval Letter of Westinghouse Ri Report, Dated March 23, 2023 and Environmental Sampling and Monitoring Program Section of SNM-1107 License Application ML23058A4482023-02-27027 February 2023 Request for Threshold Determination for Interim Transaction Included in December 20, 2022 Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals ML23058A2722023-02-27027 February 2023 Westinghouse, NRC Semiannual Discharge Report July - December 2022 ML23053A0712023-02-17017 February 2023 Westinghouse Electric Company LLC, Supplement to Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals and Request for Threshold Determination ML23053A0752023-02-17017 February 2023 Westinghouse Electric Co. - Supplement 2 to Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals and Request for Threshold Determination ML23047A4562023-02-16016 February 2023 Westinghouse, Response to Request for Additional Information - Request for Temporary License Amendment for Storage of Hematite Ash ML23030B8552023-01-30030 January 2023 Westinghouse 10CFR70.72 Facility Change Report ML23024A2312023-01-30030 January 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151//2022004 ML23013A2122023-01-27027 January 2023 Acceptance Letter for Westinghouse License Transfer - Cac/Epid L-2022-LLM-0004 ML23026A3642023-01-26026 January 2023 Westinghouse, January 2023 Updated Integrated Safety Analysis Summary ML22354A0732023-01-19019 January 2023 Response to Westinghouse Revised Funding Instrument in Support of the Decommissioning Funding Plan ML22363A0152022-12-29029 December 2022 Westinghouse Electric Co - 60-Day Report Regarding the November 1, 2022, Incident Reported Under 10 CFR 70 Appendix a 24-Hr Report, Columbia Fuel Fabrication Facility (License No. SNM-1107, Docket No. 70-1151) ML22354A2912022-12-20020 December 2022 Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals and Request for Threshold Determination ML22347A1162022-12-13013 December 2022 Westinghouse 2021-2022 Annual Groundwater Monitoring Report ML22336A1742022-12-0202 December 2022 Westinghouse Request for Temporary License Amendment for Storage of Hematite Ash ML22316A0052022-11-10010 November 2022 Westinghouse Electric Company LLC, Submittal of Amendment to Trust Agreement for License Number SNM-1107, Surety Bond Rider for SNM-1107, and Certification of Financial Assurance for SNM-1107 (Proprietary/Non-Proprietary) ML22298A0432022-10-28028 October 2022 Westinghouse Columbia Fuel Fabrication Facility Integrated Inspection Report 07001151/2022003 ML22294A1792022-10-21021 October 2022 Westinghouse, Request to Amend License SNM-1107 and Submittal of SNM-1107 License Application Page Changes ML22259A1802022-09-27027 September 2022 Letter -WEC 2022 DFP Approval MD ML22157A3492022-09-12012 September 2022 Westinghouse Electric Company, LLC - Renewal of Materials License SNM-1107 (Enterprise Project Identifier: L-2017-RNW-0016) ML22249A2252022-09-0606 September 2022 EPA Comments_Columbia Fuels Feis 2022 ML22228A1812022-08-16016 August 2022 Westinghouse, NRC Semi-Annual Discharge Report January - June 2022 ML22217A0422022-08-0505 August 2022 Response Ltr. to Mmitchum, Chief, Pine Hill Indian Tribe, the First People of Fort Jackson Re., Correspondence Related to the Proposed License Renewal for the WEC Cfff in Richland, Sc ML22214A1492022-08-0202 August 2022 Letter to Ms. Michelle Mitchum, Pine Hill Indian Tribe; Re. Westinghouse Cfff ML22215A1952022-08-0202 August 2022 Letter to USNRC and Schpo 8-2-22 from Pine Hill Indian Tribe Re Columbia Fuel Fabrication Facility ML22182A4352022-07-29029 July 2022 Letter to Applicant - Notice of Availability of the Final Environmental Impact Statement for Westinghouse Columbia Fuel Fabrication Facility 2024-01-26
[Table view] Category:Meeting Summary
MONTHYEARML22041A2022022-03-14014 March 2022 Westinghouse Trip Summary January 19-20, 2022 ML22161A9412021-10-18018 October 2021 Westinghouse, September 2021 Virtual Meeting Summary & Proposed Actions ML21054A0922021-03-0404 March 2021 Summary of Public Meeting to Discuss the Status of the Westinghouse Columbia Fuel Fabrication Facility License Renewal ML20254A1622020-09-11011 September 2020 Summary of the September 1, 2020 Closed Meeting with Westinghouse to Discuss Staff'S Draft RAIs on Alternate Disposal Approval of Specified Low Activity Radioactive Materials ML20121A2592020-04-30030 April 2020 Westinghouse License Renewal - ISA Review- Conference Call Summary Dec 2017 ML20115E3972020-04-29029 April 2020 Summary of April 23, 2020, Pre-Submittal Meeting with Westinghouse Electric Company (WEC) Regarding WEC Quality Management System(Qms) Changes Due to COVID-19 ML20100H1432020-04-16016 April 2020 Summary of Closed Pre-Submittal Meeting for the Future Submittal of Westinghouse Electric Company (Westinghouse) WCAP-18482-P, Westinghouse Advanced Doped Pellet Technology(Adopt Tm) Fuel ML20083H9552020-04-10010 April 2020 Summary of September 18-19, 2019, Partially Closed Meeting to Discuss Westinghouse Electric Company Encore Accident Tolerant Fuel: Chromium Coated Cladding ML20094L4682020-04-0303 April 2020 Summary of Meeting with Westinghouse to Discuss Nrc'S Evaluation of Performance in Four Major Areas of Safety Operations, Radiological Controls, Facility Support and Safeguards During Calendar Year 2019 ML19304A0932020-02-0505 February 2020 Summary of Closed Pre-Submittal Meeting with Westinghouse Electric Company to Discuss the Topical Report Related to Removing the Technical Specification Requirements for the Common Qualification System ML19218A1682019-08-16016 August 2019 Memo: Summary of June 27, 2019, Closed Meeting with the Westinghouse Electric Company to Discuss Future Submittal of WCAP-18446-P, Incremental Extension of Burnup Limit for Westinghouse Fuel with Zirlo Cladding and Optimized Zirlo Cladding ML19218A2232019-08-16016 August 2019 Summary of June 27, 2019, Closed Meeting with Westinghouse Electric Company to Discuss Future Submittal of WCAP-18443-P/NP, Qualification of the Two-Dimensional Transport Code Paragon2 ML19175A1602019-07-0909 July 2019 04/01-04/15/2019 Summary of Closed Audit of the Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) ML19150A5572019-06-24024 June 2019 Summary of Closed Meeting with Westinghouse Electric Company to Discuss Common Qualified Platform Topic Report (WCAP-16097) Watchdog Timer Changes ML19143A1362019-06-12012 June 2019 Summary of Closed Meeting with Westinghouse Electric Company to Discuss Future Submittal of WCAP-10965-P-A, Addendum 3, Updated Nexus Cross-Section Methodology (EPID-L-2019-TOP-0009) ML19092A3082019-05-0101 May 2019 03/27/19 Summary for Public Meeting to Discuss the Responses to the RAIs Regarding the WEC License Renewal with Enclosures ML19028A1242019-02-14014 February 2019 Summary of January 17, 2019 Closed Meeting to Discuss Westinghouse Electric Company Accident Tolerant Fuel Technology ML19022A0722019-01-28028 January 2019 Summary of Meeting with Westinghouse Electric Company to Discuss RAI Response Related to NRC Review of WCAP-16260-P/WCAP-16260-NP, Revision 2, the Spatially Corrected Inverse Count Rate (Scicr) Method for Subcritical Reactivity Measurement. ML18361A6652019-01-25025 January 2019 Summary of December 4-5, 2018, Closed Audit of the Westinghouse Electric Company Topical Report WCAP-17794-P, Revision 0, and WCAP-17794-NP, Revision 0, 10x10 Svea Fuel Critical Power Experiments and New CPR Correlation: D5 for SVEA-96 Opti ML18330A2552018-12-18018 December 2018 Summary for Public Meeting and Enclosures 1-3: Held November 8, 2018, to Discuss the License Renewal, Environmental Analysis and Leaks at the Westinghouse Columbia Fuel Fabrication Facility ML18278A0262018-10-16016 October 2018 Summary of Closed Meeting to Discuss Westinghouse Electric Company Accident Tolerant Fuel Licensing Plan ML18177A2392018-07-0202 July 2018 Summary of Closed Meeting with Westinghouse Electric Company to Discuss Restart of WCAP-15942-P-A/WCAP-15942-NP-A, Supplement 1, Revision 1, Material Changes for SVEA-96 Optima2 Fuel Assemblies, Topical Report ML18156A2282018-06-15015 June 2018 Summary of April 13-18, 2018, Closed Pre-Submittal Meeting with Westinghouse Electric Company to Discuss Future Submittal of WNG-2 Topical Report ML18130A7332018-05-10010 May 2018 Westinghouse Public Meeting Summary May 2018 ML18057A0382018-03-19019 March 2018 Summary of Closed Meeting to Discuss Implementation Plan for the Westinghouse Electric Company Topical Report WCAP-17642-P-A/WCAP-17642-NP-A, Revision 1 ML18036A4672018-02-0808 February 2018 Meeting Summary on Westinghouse Sale and License Transfer Application ML18039A0012018-02-0707 February 2018 Westinghouse Public Meeting Summary February 2018 ML17353A0802018-01-24024 January 2018 December 13, 2017 Summary of Teleconference with South Carolina Department of Health and Environmental Control Related to the Rc Review of Westinghouse'S Columbia Fuel Fabrication Facility License Renewal Application ML17332A4452018-01-17017 January 2018 Summary of the December 12, 2017, Meeting with Westinghouse Regarding the AC160 Controller Watchdog Timer Issue Causal Analysis 2022-03-14
[Table view] |
Text
Westinghouse Electric Company Nuclear Fuel Columbia Fuel Fabrication Facility 5801 Bluff Road Hopkins, South Carolina 29061 USA SCDHEC, BLWM Direct tel: 803.647.1920 Kim Kuhn Direct fax: 803.695.3964 2600 Bull Street e-mail: joynerdp@westinghouse.com Columbia, SC 29201 Your ref:
Our ref: LTR-RAC-21-71 October 18, 2021
Subject:
September 2021 Virtual Meeting Summary & Proposed Actions Ms. Kuhn:
On September 16, 2021, personnel from the South Carolina Department of Health and Environmental Control (DHEC), the Westinghouse Columbia Fuel Fabrication Facility (CFFF) and AECOM met to discuss the Phase II remedial investigation (RI) work completed at the CFFF. In attendance were Ken Taylor, Lucas Berresford, Kim Kuhn and Carolyn Moores of DHEC, Nancy Parr, Diana Joyner and David Wagoner of CFFF, and Jeremy Grant, Chuck Suddeth and Robin Mikeal of AECOM. The following agenda items were discussed during the meeting:
- Updated Conceptual Site Model (CSM) including plume analytics introduction
- Updated top of Black Mingo map
- New groundwater wells and analytical results
- Groundwater-surface water interaction
- Soil grain size analysis results
- 1) Updated CSM The discussion about the updated CSM included the following:
a) The most recent revision to the CSM includes additional lithologic data from Phase II of the RI as well as the addition of a new visual category for silty or clayey sands. AECOM has been working to show this new visual category within the CSM cross sections to assist in a better understanding of how the lower permeability sands may affect groundwater flow onsite at the CFFF.
b) Statistical plume analytics were incorporated into the 2020/2021 Annual Groundwater Monitoring Report to evaluate changes in plume behavior over time.
Page 2 of 4
- 2) Top of Black Mingo Map Survey of the RI Phase II borings and monitoring wells contributed additional data to update the top of the Black Mingo confining clay contour map. The pertinent changes to the map were presented by AECOM personnel, and the updated map will be included in the Final RI Report.
- 3) New groundwater wells, analytical results, and related plume figures The discussion about the latest groundwater data included the following:
a) Chlorinated volatile organic compounds - As demonstrated in the results of the groundwater screening samples, there is a connection between impacted groundwater in the plant area and impacted groundwater from the Western Groundwater Area of Concern. The new monitoring wells needed to close this data gap were installed after the end of the 2nd quarter of 2021; therefore, this new understanding of CVOC impact is not depicted on figures in the 2020/2021 Annual Groundwater Monitoring Report. The connection will be depicted on figures resulting from the October 2021 groundwater sampling campaign.
b) Other constituents of potential concern - Groundwater from well W-123 contained nitrate and fluoride above its maximum contaminant level (MCL) and Technetium-99 below its MCL. The additional data from monitoring well W-123 will result in very little change to the fluoride and nitrate plume figures but will allow closure of the inferred plume line on the eastern side of the Tc-99 impact.
c) With the groundwater analytical results from the new monitoring wells, the horizontal and vertical extent of COPC plumes are fully defined.
- 4) Groundwater-surface water interaction There are currently six pressure transducers in Mill Creek, one pressure transducer in the Gator Pond, ten pressure transducers in monitoring wells and one pressure transducer in a piezometer to measure surface water and groundwater levels on an hourly basis. Data collected from these pressure transducers is being used to assess the groundwater-surface water interaction. Water, both at the surface and within the ground, flows from points with higher elevations to points with lower elevations. Discussion of water elevations primarily focused on the period of time around August 22, 2021 when the site received 4.76 inches of rainfall. Multiple hydrographs of this data were presented to DHEC personnel from several areas of the site. These areas included:
a) Gator Pond Area - There are four pressure transducers installed in upper zone of the surficial aquifer monitoring wells (W-4R, W-15,W-16 and W-27), one pressure transducer in a lower zone of the surficial aquifer monitoring well (W-92), and one pressure transducer in the Gator Pond. In general, the water table in the Gator Pond area is lower than the elevation of the surface of the Gator Pond, except for the water table elevation in monitoring well W-16. Data from monitoring well W-16 showed greater fluctuations in the water table elevation than the other upper zone wells of the surficial aquifer. AECOM personnel concluded that water was likely infiltrating into the well during rain events. Repairs to the well were conducted by AECOM personnel on September 16 to stop rainwater infiltration. Prior to the October 2021 groundwater sampling event, this well was redeveloped to prevent potential foreign material from clogging the well screen.
Page 3 of 4 b) Mill Creek Area - There are six pressure transducer locations within Mill Creek from the man-made diversion canal to near the spillway of the Lower Sunset Lake Dike. In general, the surface water elevations in Upper Sunset Lake are higher than the other surface water (e.g. Lower Sunset Lake, canal) elevations. The stormwater ditches on the property empty into Upper Sunset Lake and serve as the primary source of water because the majority of Mill Creek flow bypasses the Sunset Lakes through the diversion canal. Water from Upper Sunset Lake can flow both to the east into Lower Sunset Lake and to the west through the Entrance Dike towards the canal, depending upon the surface water elevation in Upper Sunset Lake and how much flow is coming down Mill Creek beyond the diversion canal.
c) Lower Sunset Lake and Congaree River Floodplain Area - AECOM presented hydrographs from six monitoring wells (W-92, W-96, W-105, W-124, W-125, and W-126) and one piezometer (PZ-
- 1) in relation to Lower Sunset Lakes hydrograph. The elevation of the surface water in Lower Sunset Lake is consistently higher than water elevations in the surficial aquifer. In general, the lower zone of the surficial aquifer saw a greater increase in water elevation compared to the upper zone in response to the August 22, 2021 precipitation event except for the water level in piezometer PZ-1 screened in the upper zone. Additional data and evaluation are needed to continue to refine the understanding of groundwater-surface water interaction in this area.
- 5) Soil grain size analysis In response to the Nuclear Regulatory Commissions request for surficial soil properties, soil within the upper five feet of the subsurface from across a large portion of the property was collected during Phase II of the RI and submitted for grain size analysis with hydrometer. AECOM shared three observations as follows regarding the grain size analysis results.
a) The analysis illustrated the fraction of sand, silt and clay in surficial soils.
b) The field geologists description of silt versus clay is based upon the cohesive properties of the soil and its ability to be rolled out like play dough. Actual percentages of these lower permeability soils can vary from the field descriptions.
c) In general, soils near the surface contained more silt and clay content than soils deeper in the subsurface.
The discussions resulted in the parties agreeing to the following actions:
- Addition of a new east-west trending cross section to the CSM that goes through the Gator Pond and is roughly parallel to the bluff.
- CFFF will evaluate how best to perform plume analytics using historical gross beta data.
- Continue gathering data from the pressure transducers to gain additional understanding of the groundwater to surface water interactions and influence of rainfall events and river levels (if a flood event occurs).
- Submission of the most recent survey data by AECOM to SCDHEC via an Excel file.
- Submission of water level data by CFFF to SCDHEC following the October 2021 groundwater sampling campaign.
Page 4 of 4 At the end of the meeting, CFFF inquired whether DHEC concurred that Remedial Investigation Work Plan activities (i.e., fieldwork) had been completed in accordance with the Consent Agreement to assess the source(s), nature and extent of impact by historical releases. CFFF proposed that the next step was to complete the RI Report, including a risk assessment. DHEC concurred, stating they do not currently see any data gaps, however a complete review of the site data included in the RI Report would be needed to make a final determination. The parties in attendance agreed that submittal of a Remedial Investigation Report was the next step. CFFF will work on an outline and schedule for the report.
Respectfully, Diana P. Joyner Principal Environmental Engineer Westinghouse Electric Company, CFFF 803.497.7062 (m) cc: N. Parr, Environmental Manager J. Ferguson, EH&S Manager J. Grant, AECOM Project Manager ENOVIA Records