P.O. Box 411 l Burlington, KS 66839 l 620-364-8831 Michael T. Boyce Vice President Engineering May 31, 2022 ET 22-0011 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
References:
Letter ET 22-0002, dated April 4, 2022, from M. T. Boyce, WCNOC, to USNRC
Subject:
Docket No. 50-482: Withdrawal of 10 CFR 50.55a Request I4R-08, Relief for Extension of Follow-up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peened Surface Commissioners and Staff:
The purpose of this submittal is to withdraw Wolf Creek Nuclear Operating Corporation (WCNOC) 10 CFR 50.55a Request originally provided by the Reference. The Reference transmitted 10 CFR 50.55a Request I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peened Surface. WCNOC plans to modify this request and resubmit. Therefore, WCNOC is withdrawing the proposed request and is no longer seeking NRC review and approval of I4R-08.
This letter contains no commitments. If you have any questions concerning this matter, please contact me at (620) 364-8831 x8687, or Ron Benham at (620) 364-4204.
Sincerely, Michael T. Boyce MTB/