3F0522-03, Notification of Revised Decommissioning Cost Estimate

From kanterella
(Redirected from ML22148A001)
Jump to navigation Jump to search
Notification of Revised Decommissioning Cost Estimate
ML22148A001
Person / Time
Site: Crystal River  Duke Energy icon.png
Issue date: 05/26/2022
From: State S
ADP CR3
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
3F0522-03
Download: ML22148A001 (5)


Text

ADP CR3, LLC 17103 Preston Road, Suite 200 l Dallas, TX 75248 Scott E. State, P.E., Chief Nuclear Officer sstate@NorthStar.com l o.682.503.2240 l c.303.898.8035 10 CFR 50.82(a)(7)

May 26, 2022 3F0522-03 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Crystal River Unit 3 - Notification of Revised Decommissioning Cost Estimate

References:

1. CR-3 to NRC, dated June 26, 2019, Notification of Revised Post-Shutdown Decommissioning Activities Report (Revised PSDAR), (ADAMS Accession No. ML19177A232)
2. CR-3 to NRC, dated December 26, 2019, Supplemental Information in Support of Crystal River Unit 3 (CR3) - Revised Post Shutdown Decommissioning Activities Report and Decommissioning Cost Estimate, (ADAMS Accession No. ML20006F022)

Dear Sir or Madam:

Pursuant to 10 CFR 50.82(a)(7), ADP CR3, LLC, (ADP CR3) is submitting updated Decommissioning Cost Estimate (DCE) tables. In reference 1, ADP CR3 submitted a Revised Post-Shutdown Decommissioning Activities Report (Revised PSDAR) which contained revised DCE tables. In reference 2, ADP CR3 submitted Supplemental Information in Support of the Revised Post Shutdown Decommissioning Activities Report and Decommissioning Cost Estimate (Reference 1).

The DCE has been updated using actual cost for the first two years of active decommissioning described in the DCE (2020 and 2021). The revised tables reflect no change to the original Non-ISFSI O&M SubTotal costs, but only reflect actual ADP Costs for the first two years with revised projects for the remaining periods. The ISFSI O&M SubTotal has been updated to reflect the December 31, 2021, Site Specific Cost Estimate. The revised DCE tables are attached.

This letter contains no new regulatory commitments.

U. S. Nuclear Regulatory Commission Page 2 of 2 May 26, 2022 3F0522-03 If you have any questions regarding this submittal, please contact Mr. Mark Van Sicklen, ADP CR3, LLC Licensing Manager, at (352) 436-5572.

Sincerely, ADP CR3, LLC Scott E. State, P.E.

Chief Nuclear Officer Attachments:

Attachment 1 - Revised Decommissioning Cost Estimate Tables cc: NMSS Project Manager Regional Administrator, Region I

ADP CR3, LLC DOCKET NUMBERS 50-302 / 72-035 LICENSE NUMBER DPR - 72 ATTACHMENT 1 REVISED DECOMMISSIONING COST ESTIMATE TABLES

U. S. Nuclear Regulatory Commission Attachment 1 May 26, 2022 Page 1 of 2 3F0522-03 Table 1 - Decommissioning Cost Summary Thousands of Period of Performance Dollars TOTAL ADP COSTS - POST-CLOSING (2020-2037)

(Includes ADP CR3 and SF1) 2020-2026 2020-2026 2020-2026 2020-2037 License Site Spent Fuel Termination Restoration SubTotal Management Total (10 CFR 50.75) (Non 10 CFR 50.75 Costs) (10 CFR 50.54(bb))

Facility Management $70,705 $5,670 $76,375 $76,375 Decontamination and Decommissioning $220,175 $26,214 $246,389 $246,389 Large Component Removal $106,710 $0 $106,710 $12,953 $119,664 GTCC T&D $37,396 $37,396 Project Management $102,319 $8,205 $110,525 $110,525 ISFSI Decommissioning $4,587 $4,587 Non-ISFSI O&M SubTotal $499,910 $40,090 $540,000 $54,936 $594,936 ISFSI Operations & Fuel Mgt. (2020 - 2037) 2020-2037 Facility Management $183,442 $183,442 ISFSI to DOE Fuel Loading $21,415 $21,415 ISFSI O&M SubTotal $0 $0 $0 $204,857 $204,857 Total Decommissioning Costs $499,910 $40,090 $540,000 $259,793 $799,793

U. S. Nuclear Regulatory Commission Attachment 1 May 26, 2022 Page 2 of 2 3F0522-03 Table 2 - Decommissioning Annual Spend Plan Thousands of Period of Performance Dollars ANNUAL COST PROFILE (2020-2037)

(Includes ADP CR3 and SF1)

Total ADP Costs 2020 2021 (11 yea rs )

(Actual) (Actual) 2022 2023 2024 2025 2026 2027-2037 TOTAL Facility Management $9,692 $14,221 $15,655 $14,905 $9,444 $7,219 $5,239 $76,375 Decontamination and Decommissioning $43,323 $25,619 $38,070 $38,120 $43,660 $33,377 $24,220 $246,389 Large Component Removal $1,483 $40,127 $34,309 $30,791 $0 $0 $0 $106,710 Project Management $14,025 $20,579 $22,655 $21,570 $13,666 $10,447 $7,581 $110,525 Non-ISFSI O&M SubTotal $68,523 $100,546 $110,689 $105,387 $66,770 $51,044 $37,040 $0 $540,000 ISFSI Operations & Spent Fuel Mgt. (2020 - 2037)

Facility Management $1,509 $6,933 $7,212 $7,292 $7,518 $7,669 $7,822 $137,487 $183,442 GTCC Packaging, Transportation, Disposal $1,295 $7,124 $4,534 $0 $0 $0 $0 $37,396 $50,349 ISFSI to DOE Fuel Loading $21,415 $21,415 ISFSI Decommissioning $4,587 $4,587 ISFSI O&M SubTotal $2,804 $14,057 $11,746 $7,292 $7,518 $7,669 $7,822 $200,885 $259,793 Total Decommissioning Costs $71,327 $114,603 $122,435 $112,679 $74,289 $58,713 $44,862 $200,885 $799,793