Slides - Pre-Submittal Meeting for February 23 with Nextera Energy Seabrook, LLC Regarding Planned Submittal of License Amendment Request to Update Pressure-Temperature Limits Curves Period of Applicability
ML22146A347
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 02/23/2022
From:
NextEra Energy Seabrook
To:
Office of Nuclear Reactor Regulation
Poole J, NRR/DORL/LPL1
Shared Package
ML22146A340 List:
References
EPID L-2022-LRM-0016
Download: ML22146A347 (6)


Text

Seabrook Station Unit 1 Pre-Submittal Meeting License Amendment Request Update Pressure-Temperature Limits (PTL) Curves Period of Applicability Based on Latest Fluence Projections February 23, 2022

Agenda

  • License Amendment Request (LAR) Purpose
  • Surveillance Capsule X

- Applicable standards, guidance

- Fluence Projection

- Period of Applicability

  • Schedule / Implementation
  • Questions, Follow-up Items 2

Purpose Update RCS PTL curves

  • Change Period of Applicability from 55 EFPY to 52.6 EFPY where specified
  • Address Non-Conservative TS per RG 1.239.

- Currently in Seabrook CAP

- Seabrook was at 26.46 EFPY at EOC 20 (Spring 2020)

  • No other proposed changes
  • Process as normal LAR 3

Surveillance Capsule X

- 10 CFR Part 50, Appendix H

  • Applicable standards, guidance

- WCAP-17441-NP (55 EFPY PT Limit curves & fluence basis)

- 55 EFPY fluence projection was 3.05E19 n/cm2

  • Revised Fluence Projection

- WCAP-18607 Capsule X revised the fluence

- 3.05 n/cm 2 reached at 52.6 EFPY

- Period of Applicability 4

Schedule / Implementation

  • Submit 4th Quarter 2022
  • Request LAR approval within one year
  • Request 90-day implementation period 5