ML22139A287

From kanterella
Jump to navigation Jump to search
Retake ES-201-1
ML22139A287
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 07/24/2019
From: Randy Baker
NRC/RGN-III/DRS/OLB
To:
Baker R
Shared Package
ML19161A064 List:
References
Download: ML22139A287 (1)


Text

ES-201 Examination Preparation Checklist Form ES-201-1 Facility: QUAD CITIES NUCLEAR STATION Date of Retake Examination: 25-Jul-19 Developed: Written: Facility: NRC: // Operating: Facility: NRC:

Days from Chief Examiner's Target Date* Task Description (Reference)

Exam Initials

1. Examination administration date confirmed (C.1.a; C.2.a-b). For NRC-prepared exams,

-240 06/13/2019 JD 6/13/2019 arrangements are made for the facility to submit reference materials (C.1.e; C.3.c; Attachment 3)

-210 06/12/2019 2. NRC examiners and facility contact assigned (C.1.d; C.2.f). JD 6/12/2019

3. Facility contact briefed on security and other requirements (C.2.c). As applicable, the facility

-210 06/13/2019 contact submits to the NRC any prescreened K/As for elimination from the written examination JD 6/13/2019 outline, with a description of the facilitys prescreening process (ES-401, D.1.b).

-210 N/A 4. Reference material due for NRC-prepared exams (C.1.e; C.3.c; Attachment 3). N/A

-210 06/17/2019 5. Corporate notification letter sent (C.2.e). JD 6/17/2019

6. NRC-developed written examination outline (ES-401-1/2 or ES-401N-1/2 and ES-401-3 or

-195 N/A ES-401N-3) sent to facility contact (must be on the exam security agreement) (C.1.e-f; C.2.h; N/A C.3.d-e).

7. Operating test outline(s) and other checklists due, including Forms ES-201-2, ES-201-3,

-150 06/24/2019 JD 6/21/2019 ES-301-1, ES-301-2, ES-301-5, and ES-D-1, as applicable (C.1.e-f; C.3.d-e).

8. Operating test outline(s) reviewed by the NRC and feedback provided to facility licensee (C.2.h; RDB

-136 07/03/2019 C.3.d-e). 6/24/2019

9. Proposed examinations (written, JPMs, and scenarios, as applicable) and outlines (Forms ES-301-1, ES-301-2, ES-D-1, ES-401-1/2 or ES-401N-1/2, and ES-401-3 or ES-401N-3); supporting

-75 06/24/2019 JD 6/21/2019 documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, ES-401-6, ES-401N-6, and any Form ES-201-2 and ES-201-3 updates); and reference materials due (C.1.e-h; C.3.d).

10. Examinations prepared by the NRC are approved by the NRC supervisor and forwarded for

-75 N/A N/A facility licensee review (C.1.i; C.2.h; C.3.f-g).

RDB

-60 06/25/2019 11. Preliminary waiver/excusal requests due (C.1.m; C.2.c; ES-202).

6/24/2019 RDB

-50 07/03/2019 12. Written exam and operating test reviews completed (C.3.f).

6/28/2019 13a. Examination review results discussed between the NRC and facility licensee (C.1.i; C.1.k-l; RDB

-35 07/10/2019 C.2.h; C.3.g). 7/02/2019 13b. The NRC and the facility licensee conduct exam preparatory week. Scheduled for week of RDB

-35 07/23/2019 7/22/2019. 7/23/2019

14. Preliminary license applications and waiver/excusal requests, as applicable (NRC Form 398) due RDB

-30 06/25/2019 (C.1.m; C.2.i; ES-202). 6/24/2019

15. Final license applications and waiver/excusal requests, as applicable (NRC Form 398), due and RDB

-14 07/11/2019 Form ES-201-4 prepared (C.1.m; C.2.k; ES-202). 7/08/2019 RDB

-7 07/15/2019 16. Written examinations and operating tests approved by the NRC supervisor (C.2.j-k; C.3.h).

7/12/2019 RDB

-7 07/15/2019 17. Request facility licensee management feedback on the examination (C.2.l).

7/18/2019

18. Final applications reviewed; one or two (if more than 10) applications audited to confirm RDB

-7 07/15/2019 qualifications/eligibility; and examination approval and waiver/excusal letters sent (C.2.k; Attachment 7/24/2019 5; ES-202, C.3.j; ES-204).

-7 N/A 19. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k). N/A RDB

-7 07/18/2019 20. Approved scenarios and job performance measures distributed to NRC examiners (C.3.i).

7/24/2019

  • Target dates are based on facility prepared examinations and the examination date identified in the corporate notification Exam Date: 07/25/2019 letter. These dates are for planning purposes and may be adjusted on a case by case basis in coordination with the facility licensee.