MONTHYEARML24145A0012024-05-24024 May 2024 5/29/2024, Annual Assessment Meeting for Seabrook Station - NRC Presentation Slides ML24121A1512024-04-30030 April 2024 Pre-Submittal Meeting to Discuss Upcoming NextEra Energy License Amendment Request for a One-Time Extension to TS 3.8.1.1.a Completion Time ML24073A3372024-03-13013 March 2024 NextEra - NRC Slides for the Public Meeting on March 19, 2024 Regarding Emergency Plan Licensing Amendment ML23177A1142023-06-26026 June 2023 Annual Assessment Meeting Reactor Oversight Process – 2023 ML23066A2472023-03-0707 March 2023 Presubmittal Meeting Slides for March 7, 2023, Public Meeting ML22130A1282022-05-10010 May 2022 Annual Assessment Meeting for Seabrook Station - NRC Presentation Slides ML22146A3472022-02-23023 February 2022 Slides - Pre-Submittal Meeting for February 23 with Nextera Energy Seabrook, LLC Regarding Planned Submittal of License Amendment Request to Update Pressure-Temperature Limits Curves Period of Applicability ML21168A1452021-06-22022 June 2021 Annual Assessment Meeting Slides ML20161A0812020-06-0303 June 2020 Annual Assessment Meeting June 3, 2020 Slides ML19042A1102019-02-13013 February 2019 Presentation Slides - 2019 Seabrook Public Meeting ML18136A4822018-05-0202 May 2018 Annual Assessment Meeting 05-02-2018 Presentation ML18086A7742018-02-21021 February 2018 LOR Program Biennial Inspection 71111.11B Exam Overlap Issues ML17341A0622017-11-17017 November 2017 NextEra Energy Seabrook Presentation Slides - Seabrook Station ASR Methodology LAR: Structural Deformation - LAR 16-03, Methodology and Responses to Rais D2-D8 - for November 17, 2017, Public Meeting ML17310B2322017-11-0707 November 2017 Presentation Slides - NextEra Energy/Fpl - GSI-191 Issue Resolution, Pre-submittal Meeting, September 20, 2017 ML17278A7482017-10-13013 October 2017 Summary of August 24, 2017, Meeting with NextEra Energy Regarding License Amendment Request on Alkali Silica Reaction (CAC No. MF8260; EPID L-2016-LLA-0007) ML17283A0402017-10-10010 October 2017 Enclosure 2 - Nrc'S Presentation Slides-Seabrook Station, License Amendment Request, Stage 3 Methodology ML17283A0412017-08-24024 August 2017 Enclosure 3 - Licensee'S Presentation-Seabrook Station, License Amendment Request 16-03 ASR Structural Evaluation Methodology ML17164A2712017-06-0707 June 2017 Presentation Slides for Annual Assessment Meeting 2017 ML16176A0542016-06-21021 June 2016 6/21/2016 - Seabrook Station Annual Assessment Meeting - NRC Presentation Slides (Assessment and ASR Update) ML16168A4122016-06-15015 June 2016 Slides for Public Meeting with NextEra Energy Regarding Seabrook Station ASR License Amendment ML16146A2002016-04-28028 April 2016 License Renewal Application, April 28, 2016, Public Meeting NextEra Presentation ML14190B0432014-07-0909 July 2014 Annual Assessment Meeting Performance Slides - June 24 2014 ML13357A0432013-12-23023 December 2013 ASR at Seabrook Station Update on Testing Program ML13357A0412013-12-23023 December 2013 Public Meeting on Seabrook Station Testing Program ML13357A0462013-12-23023 December 2013 Update on ASR ML13133A2492013-05-29029 May 2013 Slides from May 9, 2013, Meeting with NextEra Energy Seabrook, LLC on Pre-Submittal of a Fixed Incore Detector License Amendment Request ML13066A4882013-03-21021 March 2013 Summary of Meeting Held on February 21, 2013, Between the NRC and NextEra Energy Seabrook, LLS Regarding License Renewal Application, Seabrook Station ML12356A0432012-12-11011 December 2012 Safety Implications and Status of ASR Condition - Public Meeting on 12/11/2012 ML12236A3852012-08-23023 August 2012 Memo Summary of NextEra Energy Seabrook Drop in Visit and Slides, August 22, 2012 ML12132A3442012-05-11011 May 2012 NRC-AERB Bilateral Meeting Slide Presentation (Nro/De), Aerb, India - May 16-17, 2012 ML12131A4312012-05-10010 May 2012 Aam ROP-12 Slides-Safety Performance & Alkali-Silica Reaction - r9 Revised Format ML1211604142012-04-23023 April 2012 Structural Assessment of Seabrook Station - Role of Concrete Material Testing ML1204402842012-02-16016 February 2012 Public Meeting Construction Experiences - Evaluate Impact of Concrete Degradation ML12026A4592012-01-26026 January 2012 EDG Ifr ML11343A4482011-12-0909 December 2011 NextEra Drop in Meeting Summary and Slides from 11-14-2011 Meeting with Region-I SBK-L-11190, Supplement to Request for Closed Meeting to Discuss Proprietary Test2011-09-19019 September 2011 Supplement to Request for Closed Meeting to Discuss Proprietary Test ML11259A0022011-09-15015 September 2011 Meeting Slides Preliminary Site-Specific Results of the License Renewal Environmental Review for Seabrook Station. ML1116500382011-06-0808 June 2011 Aam Slides, June 8, 2011 ML12054A6412011-05-24024 May 2011 Concrete Degradation - Alkali Silica Reaction, W/Handwritten Notes ML1108206992011-03-22022 March 2011 3/22/11 Revised Pre-application Meeting Slides Regarding NFPA 805 License Amendment Request ML1022205712010-08-10010 August 2010 License Renewal Process Overview and Scoping Public Meeting Slides ML1019703702010-07-19019 July 2010 License Renewal Process Overview ML1013901282010-05-17017 May 2010 License Renewal Overview Presentation for Seabrook Station ML1011004582010-04-20020 April 2010 NRC Slides for Seabrook Annual Assessment Meeting, April 14, 2010 ML0927403042009-09-22022 September 2009 NextEra Letter and Slide Presentation to NRC Seabrook Regulatory Conference, Dated 9/22/09 ML0910604982009-04-30030 April 2009 NRC Slides for Annual Assement Meeting, 4/30/09 ML0809300252008-04-0202 April 2008 NRC Slides - Seabrook Aam 2008 ML0710002082007-03-29029 March 2007 Aam Slides for EOC 2006-07 ML0708001192007-03-21021 March 2007 Slides, End of the Presentation, from Seabrook Station Annual Assessment Meeting for EOC 2006-07 ML0727105992006-06-0505 June 2006 Viewgraphs of Use of Ultrasonic Flow Measurement to Determine Reactor Power 2024-05-24
[Table view] |
Text
Seabrook Station Annual Assessment Meeting
Welcome!
This meeting will start at 5:30pm.
Seabrook Station Annual Assessment Meeting
Reactor Oversight Process - 2021
May 12, 2022
2 Seabrook Annual Assessment Meeting
Meeting Facilitator
Brett Klukan Regional Counsel, Region I
3 Meeting Conduct
- Please respect other members of the public
- Please be conscious of your speaking time
- Questions will be addressed during the Question-and-Answer session following the presentation.
4 Agenda - Seabrook
Dan Collins Director, Region I Division of Operating Reactor Safety
- 2021 ROP Plant Performance Assessment and Inspection Activities
- NRC Inspection of Alkali -Silica Reaction (ASR)
- Public Question and Answer Session
5 NRC Panelists
Chris Newport Travis Daun Nik Floyd Sr. Resident InspectorResident Inspector Senior Inspector
Mel Gray Matt Young Engineering Branch Chief Branch Chief 6
NRC Independent Safety Inspections
Reactor Oversight Process
- Full-time NRC resident inspectors
- NRC specialists conduct additional inspections at each nuclear plant
- NRC inspectors have unfettered access to all plant activities related to nuclear safety and security
7 NRC Independent Safety Inspections
Action Matrix Concept
8 2021 ROP Plant Performance Assessment at Seabrook
- Operated safely and in a manner that preserved the public health and safety and protected the environment
- All Green Performance Indicators
- All Very Low Safety Significance Findings
- The plant will receive the baseline level of inspection in 2022
9 2021 NRC Inspection Activities at Seabrook
- ~6000 hours of inspection and related activities
- Examples of Resident Inspections
- operator performance in the simulator
- 2021 Team Inspections
- Evaluation of Modifications (50.59)
- Refueling Outage Activities
10 NRC Actions in Response to COVID-19
- Monitored plant activities through inspections and oversight
- Maintained emergency response capabilities within Regional Incident Response Centers and NRC HQ
- NRC resident inspectors currently full time on-site
11 NRC Inspection of ASR at Seabrook
- In 2021, the NRC completed inspections to assess NextEras performance to manage the effects of ASR in Seabrook structures
- ASR inspections completed in each quarter
- Resident inspectors and specialists from Region I and NRC Headquarters involved
- Focused on compliance w ith NRC-approved methodology and license conditions
- NRC inspections in 2021 determined Seabrook structures remain capable of performing their safety functions
- NRC inspectors identified tw o findings of very low safety significance
12 NRC Inspection of ASR at Seabrook
- 4Q2021 - Finding related to not properly evaluating ASR -related indications in the Containment Internal Structure per the Structures Monitoring Program
13 Seabrook Annual Assessment Meeting
Closing Remarks
14 NRC Social Media Channels
- Facebook: www.facebook.com/nrcgov
- Flickr: www.flickr.com/photos/nrcgov/
- Tw itter: tw itter.com/#!/nrcgov
- YouTube: www.youtube.com/user/NRCgov
- RSS: w ww.nrc.gov/publicinvolve/listserver.html#rss
- LinkedIn:www.linkedin.com/company/u-s--nuclearregulatory -
commission/
15 Annual Assessment Meeting Feedback
- 1. Mail in NRC 2. Scan QR Code on feedback form that - OR -back of form with will be emailed to smar t device all attendees - OR -
- 3. At any computer, go to the Public Meeting Schedule and press the Meeting Feedback link for this meeting - or - press the
[more] link for this meeting and then press the Meeting Feedback link on the Meeting Details page.
16 - OR -
- 4. Email Public Affairs - opa1.resource@nrc.gov
16 Question & Answer Session
Question & Answer Session
17 Thank you for your participation REFERENCE SLIDES NextEra Methodology for ASR
Methodology Document
Structural Analysis & Evaluation
Monitoring Parameters and Limits
Structures Monitoring Program
Corrective Action
20 Reactor Cavity Diagram
N West East Wall Wall
Deck Keyway Grate /
Wall Floor Slab Opening
Reactor Cavity Pit Overhead View Containment Side View
21 Structural Modification Examples
Example 1 - Example 2 -
Strong backs Corner Braces
22