KP-NRC-2204-011 Kairos Power LLC www.kairospower.com 707 W Tower Ave, Suite A 5201 Hawking Dr SE, Unit A 2115 Rexford Rd, Suite 325 Alameda, CA 94501 Albuquerque, NM 87106 Charlotte, NC 28211 April 27, 2022 Docket No. 50-7513 US Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Kairos Power LLC Transmittal of Changes to Hermes Environmental Report Resulting from NRC Environmental Review Audit
References:
- 1. Letter, Kairos Power LLC to Document Control Desk Submittal of the Environmental Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), October 31, 2021 (ML21306A131)
- 2. Email, Nuclear Regulatory Commission, Tamsen Dozier to Kairos Power LLC, Kairos Power, LLC Hermes Environmental Report Audit Plan, February 2, 2022 (ML22052A008)
By letter dated October 31, 2021 (Reference 1), Kairos Power LLC submitted its Environmental Report (ER) in support of the construction permit application (CPA) for the Hermes test reactor. As part of the Nuclear Regulatory Commission (NRC) review of the information contained in the ER, NRC staff announced (Reference 2) and conducted an audit of the Hermes ER.
During the audit, Kairos Power agreed to revise the Environmental Report to address NRC information needs identified during the audit. Enclosure 1 provides changes to the Hermes Environmental Report that were discussed during the audit. Kairos Power requests NRC staff review of these changes in support of continued review of the Hermes CPA.
If you have any questions or need any additional information, please contact Marty Bryan at bryan@kairospower.com or (865) 369-1136, or Darrell Gardner at gardner@kairospower.com or (704) 769-1226.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on April 27, 2022.
Peter Hastings, PE Vice President, Regulatory Affairs and Quality
Enclosure:
Changes to Hermes Environmental Report Resulting from NRC Environmental Review Audit
KP-NRC-2204-011 Page 2 xc (w/enclosure):
William Kennedy, Acting Chief, NRR Advanced Reactor Licensing Branch Benjamin Beasley, Project Manager, NRR Advanced Reactor Licensing Branch Tamsen Dozier, Environmental Project Manager, NMSS, Environmental Review Branch Daniel Barnhurst, Deputy Environmental Project Manager, NMSS, Environmental Review Branch