KP-NRC-2204-008 Kairos Power LLC www.kairospower.com 707 W Tower Ave, Suite A 5201 Hawking Dr SE, Unit A 2115 Rexford Rd, Suite 325 Alameda, CA 94501 Albuquerque, NM 87106 Charlotte, NC 28211 April 27, 2022 Docket No. 50-7513 US Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Kairos Power LLC Transmittal of Supplemental Information for NRC Information Need HCUL-10 for the Hermes Environmental Review
References:
- 1. Letter, Kairos Power LLC to Document Control Desk Submittal of the Environmental Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), October 31, 2021 (ML21306A131)
- 2. Email, Nuclear Regulatory Commission, Tamsen Dozier to Kairos Power LLC, Kairos Power, LLC Hermes Environmental Report Audit Plan, February 2, 2022 (ML22052A008)
By letter dated October 31, 2021 (Reference 1), Kairos Power LLC submitted its Environmental Report (ER) in support of the construction permit application (CPA) for the Hermes test reactor. As part of the Nuclear Regulatory Commission (NRC) review of the information contained in the ER, NRC announced (Reference 2) and conducted an audit of the Hermes ER.
During the audit, the NRC requested that Kairos Power provide supplemental information related to audit information need HCUL-10 (Reference 2). The enclosure to this letter submits photographs taken in the Hermes site vicinity, specifically requested by NRC staff during the audit. Kairos Power requests NRC staff review of this information in support of continued review of the Hermes non-power test reactor CPA.
If you have any questions or need any additional information, please contact Marty Bryan at bryan@kairospower.com or at (865) 369-1136, or Darrell Gardner at gardner@kairospower.com or (704) 769-1226.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on April 27, 2022.
Peter Hastings, PE Vice President, Regulatory Affairs and Quality
Enclosure:
Supplemental Information for HCUL-10 for Hermes Environmental Review
KP-NRC-2204-008 Page 2 xc (w/enclosure):
William Kennedy, Acting Chief, NRR Advanced Reactor Licensing Branch Benjamin Beasley, Project Manager, NRR Advanced Reactor Licensing Branch Tamsen Dozier, Environmental Project Manager, NMSS, Environmental Review Branch Daniel Barnhurst, Deputy Environmental Project Manager, NMSS, Environmental Review Branch