2022 National State Liaison Officer Conference Presentation:

Nonemergency Event Notifications Rulemaking George Tartal NRC Project Manager ADAMS Accession No. ML21337A345

=

Background===

  • The NRC requires all operating nuclear power reactors to report to the NRC emergency and certain non-emergency events.
  • In 2018, NEI submitted a petition for rulemaking to eliminate all non-emergency event reports.
  • In 2020, the NRC staff recommended rulemaking.
  • In 2021, the Commission directed the NRC staff to pursue rulemaking with certain conditions.

2

Rulemaking Process 3

Regulatory Basis

  • A regulatory basis document helps the NRC decide whether rulemaking is the right solution to the problem being addressed.
  • A regulatory basis document:

- Discusses the scope of the problem and possible options

- Considers legal, policy, technical, and cost-benefit analysis

- Identifies the preferred regulatory action

  • Possible options:

- Maintain status quo

- Revise regulations

- Revise guidance

- Other?

4

Public Meetings

  • The NRC staff held public meetings in November and December 2021 on this rulemaking.
  • Feedback was requested on issues to be considered in the regulatory basis.
  • Several SLOs attended these public meetings.
  • All feedback was documented in the meeting summary.
  • NRC is considering all feedback it received as it develops the regulatory basis.

5

Project Status / Next Steps

  • The NRC staff is developing a regulatory basis.
  • There will be a public comment opportunity later this year.
  • A proposed rule and final rule would follow if the regulatory basis recommends moving forward through rulemaking.

6

References 10 CFR 50.72(b), Immediate notification requirements for operating nuclear power reactors https://www.ecfr.gov/current/title-10/chapter-I/part-50/subject-group-ECFReadbe827381d095/section-50.72 The rulemaking process (from NRCs public Web site) https://www.nrc.gov/about-nrc/regulatory/rulemaking/rulemaking-process.html PRM-50-116, Elimination of Immediate Notification Requirements for Operating Nuclear Power Reactors, dated August 2, 2018 ADAMS Accession No. ML18247A204 SECY-20-0109, Petition for Rulemaking and Rulemaking Plan on Immediate Notification Requirements for Nonemergency Events (PRM-50-116; NRC-2018-0201), dated November 30, 2020 ADAMS Accession No. ML20073G008 SRM-SECY-20-0109, Petition for Rulemaking and Rulemaking Plan on Immediate Notification Requirements for Nonemergency Events, dated July 28, 2021 ADAMS Accession No. ML21209A947 November 2021 public meeting summary ADAMS Accession No. ML21341B452 December 2021 public meeting summary ADAMS Accession No. ML21350A033 7

Questions?

8