MONTHYEARML24261C0092024-09-16016 September 2024 Kairos Power LLC - Charlotte Office Address ML24158A2322024-08-30030 August 2024 Letter to Kairos, Inc., Exemption and Final EA ML24200A1172024-07-19019 July 2024 Transmittal Letter for the Hermes 2 Safety Evaluation ML24155A0612024-06-0303 June 2024 Kairos Power LLC, Presentation Materials for the Kairos Power Meeting with the Nuclear Regulatory Commission on the Hermes Foundation Design ML24150A2442024-05-29029 May 2024 Kairos Power, LLC - Presentation Materials for Kairos Power Briefing to the Advisory Committee on Reactor Safeguards, Kairos Power Subcommittee on Hermes 2 Preliminary Safety Analysis Report, Chapters 2, 3, 5, 9, and 13 ML24150A2172024-05-28028 May 2024 Kairos Power, LLC - Request for Documents Related to Non-Power Security ML24144A0912024-05-23023 May 2024 Kairos Power, LLC - Submittal of the Hermes 2 Preliminary Safety Analysis Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor, Revision 1, and the Postulated Event Analysis Methodology Technical Report, Revi ML24138A2122024-05-16016 May 2024 Kairos Power LLC Transmittal of Changes to Hermes 2 Construction Permit Application – PSAR Chapters 3, 5, and 13 ML24136A2542024-05-15015 May 2024 Kairos Power LLC - Transmittal of Changes to Hermes 2 Construction Permit Application - PSAR Chapter 9 ML24135A3832024-05-14014 May 2024 Kairos Power, LLC - Transmittal of Response to NRC Request for Confirmation of Information for the Review of the Hermes 2 PSAR Chapter 5 ML24131A1262024-05-10010 May 2024 Kairos Power, LLC - Presentation Materials for Kairos Power Briefing to the Advisory Committee on Reactor Safeguards, Kairos Power Subcommittee on Hermes 2 Preliminary Safety Analysis Report Chapters 1, 4, 6-8, 10-12, 14, and 16-18 ML24101A0772024-04-23023 April 2024 Hermes 2 NPS Dea ML24101A0782024-04-23023 April 2024 Hermes 2 SHPO Dea ML24101A0722024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Johnson, J ML24113A1732024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Hill, D ML24113A1702024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Bunch, J ML24113A1692024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Bryan, a ML24113A1682024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Barnes, B ML24113A1712024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Cernek, J ML24113A1722024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Hicks, M ML24113A1742024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Hoskin, Jr., C ML24113A1752024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Johnson, L J ML24113A1762024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Morrow, R K ML24113A1782024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Rogers, L ML24113A1772024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Osceola, Jr. M W ML24113A1792024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Sylestine, R ML24113A1822024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Yargee, W ML24113A1802024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Wallace, G J ML24113A1812024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Yahola, ML24101A2172024-04-19019 April 2024 Letter to Kairos Power, LLC-Notice of Availability of the Draft Environmental Assessment for the Construction Permit for Hermes 2 Test Reactors ML24109A2952024-04-16016 April 2024 Kairos Power, LLC - Slides to Support April 22, 2024, Public Meeting About Hermes Physical Security ML24103A2422024-04-12012 April 2024 Kairos Power, LLC, Transmittal of Reponses to NRC Requests for Confirmation of Information for the Review of the Hermes 2 PSAR Chapter 5 ML24103A2452024-04-12012 April 2024 Kairos Power, LLC, Transmittal of Changes to Construction Permit Application - Financial Information Enclosure and PSAR Chapter 15 ML24206A0852024-03-20020 March 2024 NPS Section 106 Initiation Response - Hermes 2 ML24073A3182024-03-13013 March 2024 Kairos Power LLC, Transmittal of Changes to Hermes 2 Construction Permit Application - PSAR Chapter 13 and KP-TR-022 ML24072A2982024-03-12012 March 2024 Kairos Power LLC - Transmittal of Changes to Hermes 2 Construction Permit Application – PSAR Chapter 7 ML24065A1012024-03-0404 March 2024 Kairos Power LLC, Transmittal of Reponses to NRC Requests for Confirmatory Information for the Review of the Hermes 2 Environmental Report ML24039A1902024-02-0808 February 2024 Kairos Power LLC, Transmittal of Changes to Hermes 2 Construction Permit Application – PSAR Chapter 2 ML24032A1892024-02-0202 February 2024 Ltr Hon Glenna J Wallace Chief Eastern Shawnee Tribe of Oklahoma Re Hermes 2 ML24032A2002024-02-0202 February 2024 Ltr Libby Rogers, Principal Chief, Jena Band of Choctaw Indians Re Hermes 2 ML24032A1992024-02-0202 February 2024 Ltr Hon Wilson Yargee, Chief Alabama-Quassarte Tribal Town Re Hermes 2 ML24032A1982024-02-0202 February 2024 Ltr Hon Stephanie Yahola, Mekko Kialegee Tribal Town Re Hermes 2 ML24032A1972024-02-0202 February 2024 Ltr Hon Stephanie a Bryan Chairwoman Poarch Band of Creek Indians Re Hermes 2 ML24032A1962024-02-0202 February 2024 Ltr Hon Ryan K Morrow Town King Thlopthlocco Tribal Town Re Hermes 2 ML24032A1952024-02-0202 February 2024 Ltr Hon Rick Sylestine, Chairman, Alabama-Coushatta Tribe of Tx Re Hermes 2 ML24032A1942024-02-0202 February 2024 Ltr Hon Michell Hicks Principal Chief Eastern Band of Cherokee Indians Re Hermes 2 ML24032A1932024-02-0202 February 2024 Ltr Hon Marcellus W Osceola Jr Chairman Seminole Tribe of Fl Re Hermes 2 ML24032A1922024-02-0202 February 2024 Ltr Hon Lewis J Johnson Chief Seminole Nation of Oklahoma Re Hermes 2 ML24032A1912024-02-0202 February 2024 Ltr Hon Jonathan Cernek Chairman Coushatta Tribe of Louisiana Re Hermes 2 ML24032A1902024-02-0202 February 2024 Ltr Hon Joe Bunch Chief United Keetoowah Band of Cherokee Indians Re Hermes 2 2024-09-16
[Table view] |
Text
KP-NRC-2202-002
February 18, 2022 Docket No. 50- 7513
US Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Kairos Power LLC Transmittal of Kairos Power CPA Changes
References:
- 1. Letter, Kairos Power LLC to Document Control Desk, Submittal of the Preliminary Safety Analysis Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), Septe mber 29, 2021 (ML21272A376)
- 2. Letter, Kairos Power LLC to Document Control Desk, Submittal of the Environmental Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), October 31, 2021 (ML21306A13 1)
- 3. Kairos Power LLC to Document Control Desk, Metallic Materials Qualification for the Kairos Power Fluoride Salt-Cooled High Temperature Reactor, KP -TR-013, Revision 0, June 30, 2020 (ML20182A800)
- 4. Kairos Power LLC to Document Control Desk, Graphite Material Qualification for the Kairos Power Fluoride Salt-Cooled High-Temperature Reactor, KP -TR-014, Revision 1, July 8, 2021 (ML21190A220)
In September and October 2021, Kairos Power submitted a Construction Permit Application (CPA) for the Hermes non-power reactor, including a Preliminary Safety Analysis Report (PSAR) (Reference 1) and an Environmental Report (ER) (Reference 2). Subsequent to the submittal of these documents, Kairos Power made a decision to eliminate the intermediate nitrate salt coolant loop and remove pr imary system heat directly through an air h eat rejection subsystem. This change has a negligible impact on the conclusions of the CPA but has a minor effect on content in several c hapters of the PSAR, the ER, and the Postulated Event Analysis Methodology Technical Report (KP-TR-018, which was also submitted in Reference 1).
Changes to the pages of the PSAR, ER, and Technical Report affected by this decision are provided in Enclosures 1, 2, and 3, respectively. A small number of minor changes unrelated to the revised heat removal strategy are also included in these enclosures. Kairos Power requests NRC review of these changes as part of continued review of the Hermes CPA.
This change also impacts two topical reports referenced in the CPA that are currently under review by NRC staff, KP-TR-013 (Reference 3) and KP-TR-014 (Reference 4). Kairos Power will provide updates to these reports as part of changes to these documents that are occurring as part of the review process.
Kairos Power LLC www.kairospower.com 707 W Tower Ave, Suite A 5201 Hawking Dr SE, Unit A 2115 Rexford Rd, Suite 325 Alameda, CA 94501 Albuquerque, NM 87106 Charlotte, NC 28211
KP-NRC-2202-004 Page 2
If you have any questions or need any additional information, please contact Drew Peebles at peebles@kairospower.com or at (704) 275-5388 or Darrell Gardner at gardner@kairospower.com or (704) 769-1226.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on February 18, 2022
Peter Hastings, PE Vice President, Regulatory Affairs and Quality
Enclosures:
- 1) Changes to the PSAR
- 2) Changes to the ER
- 3) Changes to the Postulated Event Technical Report
xc (w/enclosure):
William Kennedy, Acting Chief, NRR, Advanced Reactor Licensing Branch Benjamin Beasley, Project Manager, NRR, Advanced Reactor Licensing Branch Edward Helvenston, Project Manager, NRR Advanced Reactor Licensing Branch Samuel de Jesus Cuadrado, Project Manager, NRR Advanced Reactor Licensing Branch Tamsen Dozier, Environmental Project Manager, NMSS, Environmental Review Branch Peyton Doub, Environmental Project Manager, NMSS, Environmental Review Branch Enclosure 1 Changes to the PSAR
(Non-Proprietary)
Enclosure 2 Changes to the ER
(Non-Proprietary)
Enclosure 3 Changes to the Postulated Event Technical Report
(Non-Proprietary)