MONTHYEARIR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 IR 05000280/20230102024-01-18018 January 2024 Age Related Degradation Inspection Report 05000280-2023010 and 05000281-2023010 ML23312A1922024-01-18018 January 2024 Issuance of Amendment Nos. 316 & 316 Regarding a Risk Informed Approach for Tornado Classification of the Fuel Handling Trolley Support Structure ML24003A9022024-01-0303 January 2024 Stations, Units 1 and 2, Emergency Plan Revision - Relocation of the Technical Support Center (TSC) - Editorial Correction IR 05000280/20233012023-12-28028 December 2023 NRC Operator License Examination Report 05000280/2023301 and 05000281/2023301 ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23352A3692023-12-18018 December 2023 Associated Independent Spent Fuel Storage Installation, Revision to Emergency Plan Report of Change ML23324A4032023-12-0606 December 2023 Request for Additional Information for Review of the Tn Americas Application for Certificate of Compliance No. 1042, Amendment No. 4, to NUHOMS Eos System ML23334A2342023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23317A3432023-11-21021 November 2023 Inspection Report No. 72-1042/2023-201 - Eos 1042 Horizontal Storage Modules at Millstone Power Station ML23242A2292023-11-0707 November 2023 Issuance of Amendment Nos. 315 and 315, Regarding Emergency Procedure Relocation of the Technical Support Center ML23200A2622023-11-0202 November 2023 Issuance of Amendment Nos. 314 and 314, Regarding Technical Specification and Spent Fuel Pool Criticality Change IR 05000280/20230032023-10-25025 October 2023 Integrated Inspection Report 05000280/2023003 and 05000281/2023003 ML23286A0372023-10-13013 October 2023 Annual Submittal of Technical Specifications Bases Changes Pursuant to Technical Specification 6.4.J ML23285A0922023-10-12012 October 2023 Inservice Testing Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests ML23277A1172023-10-0303 October 2023 Operator Licensing Examination Approval 05000280/2023301 and 05000281/2023301 ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23264A8682023-09-21021 September 2023 Independent Spent Fuel Storage Installation Registration of Dry Storage Canister WC-EOS-37PTH-008-B4L, WC-EOS-37PTH-007-B4L, and WC-EOS-37PTH-002-B4L ML23256A2672023-09-21021 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23244A2352023-09-18018 September 2023 Request to Use a Subsequent Edition of the ASME Code, Section XI ML23230A0012023-09-15015 September 2023 Request to Use a Provision of a Previous Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for Non-Destructive Examinations IR 05000280/20220042023-09-0101 September 2023 Reissue - Surry Power Station - Integrated Inspection Report 05000280/2022004 and 05000281/2022004 ML23244A0142023-08-30030 August 2023 Inservice Inspection Owner'S Activity Report IR 05000280/20230052023-08-23023 August 2023 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2023005 and 05000281/2023005) ML23235A0662023-08-23023 August 2023 Proposed Additional Alternative to the ACI Code, Concrete Temperature Limits, Docket 72-1042, CoC 1042 Amendments 1, 2, and 3 ML23226A1862023-08-10010 August 2023 Proposed License Amendment Request - Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection Flow Instrumentation ML23220A1492023-08-0707 August 2023 Independent Spent Fuel Storage Installation - Submittal of Cask Registrations for Spent Fuel Storage ML23220A1482023-08-0707 August 2023 Proposed Emergency Plan Revision - Relocation of the Technical Support Center (TSC) Response to Request for Additional Information IR 05000280/20230022023-08-0404 August 2023 Integrated Inspection Report 05000280/2023002 and 05000281/2023002 ML23207A0352023-07-27027 July 2023 Acceptance of Tn Americas LLC Request for Amendment No. 4 to Certificate of Compliance No. 1042 for the NUHOMS Eos System - Cost Activity Code 001028/Enterprise Project Identification Number L-2022-LLA0017 ML23207A1102023-07-26026 July 2023 NRC Regulatory Issues Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations ML23208A0922023-07-26026 July 2023 Request for Approval of Appendix F of Fleet Report DOM-NAF-2-P Qualification of Framatome ORFEO-GAIA and OORFE-NMGRID CHF Correlations in the Dominion Energy Vipre-D Computer Code Response ML23198A0322023-07-18018 July 2023 Regulatory Audit Report Regarding Review of License Amendment to Modify Emergency Plan Staff Augmentation Times ML23193A9382023-07-18018 July 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML23198A2892023-07-17017 July 2023 Certificate of Compliance 1042, NUHOMS Eos System Updated Final Safety Analysis Report (Ufsar), Revision 5 Docket 72-1042 and Biennial Report of 10 CFR 72.48 Evaluations Performed for the NUHOMS Eos System, CoC 1042, for the Period 01/31/22 ML23173A0602023-07-11011 July 2023 Audit Summary for License Amendment Request Revision of the Emergency Plan to Support Relocation of the Technical Support Center 2024-02-06
[Table view] |
Text
VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 January 27, 2022 10 CFR 72.212 Attention: Document Control Desk Serial No.: 22-007 Director, Division of Spent Fuel Management, NRA/MLW: RO Office of Nuclear Material Safety and Safeguards Docket Nos.: 50-280/281 U.S. Nuclear Regulatory Commission 72-55 Washington, DC 20555-0001 License Nos.: DPR-32/37 VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 AND ISFSI NOTIFICATION PURSUANT TO 10 CFR 72.212(b}{1) PRIOR TO FIRST STORAGE OF SPENT FUEL UNDER A GENERAL LICENSE Pursuant to 10 CFR 72.212, "Conditions of general license issued under 72.210,"
paragraph (b)(1 ), Virginia Electric and Power Company (Dominion Energy Virginia) is notifying the Nuclear Regulatory Commission (NRC) of our intent to begin loading Surry Power Station (SPS) Units 1 and 2 spent fuel into Transnuclear (TN) Americas NUHOMS EOS storage casks under the general license at SPS. Loading activities are scheduled to commence on or about May 2, 2022. Dominion Energy Virginia will use the TN Americas NUHOMS EOS storage system in accordance with the NRG issued Certificate of Compliance No. 1042.
Licensee Name: Virginia Electric and Power Company Licensee Address: 5000 Dominion Boulevard Glen Allen, VA 23060 Reactor License Nos.: DPR-32/37 Reactor Docket Nos.: 50-280/281 General License Point of
Contact:
Richard L. Ridder (804) 273-2415 If you have any questions, please contact Michael Whitlock, Corporate Nuclear Regulatory Affairs, at (804) 273-3123.
Doug as C. Lawrence Vice esident - Nuclear Engineering and Fleet Support Commitments made by this letter: None
Serial No.22-007 Notification prior to first storage of spent fuel Page 2 of 2 cc: U.S. Nuclear Regulatory Commission - Region II Regional Administrator Marquis One Tower 245 Peachtree Center Avenue N.E., Suite 1200 Atlanta, Georgia 30303-3415 Mr. L. John Klos NRG Project Manager -Surry U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 9 E3 11555 Rockville Pike Rockville, Maryland 20852-2738 Ms. Yen-Ju Chen Senior Project Manager U.S. Nuclear Regulatory Commission Two White Flint North Mail Stop 4834 11545 Rockville Pike Rockville, MD 20852-2738 NRG Senior Resident Inspector Surry Power Station