ISFSI - Notification Pursuant to 10 CFR 72.212(b)(1) Prior to First Storage of Spent Fuel Under a General License
ML22027A831
Person / Time
Site: Surry, 07200055, 07201042  Dominion icon.png
Issue date: 01/27/2022
From: Lawrence D
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
22-007
Download: ML22027A831 (2)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 January 27, 2022 10 CFR 72.212 Attention: Document Control Desk Serial No.: 22-007 Director, Division of Spent Fuel Management, NRA/MLW: RO Office of Nuclear Material Safety and Safeguards Docket Nos.: 50-280/281 U.S. Nuclear Regulatory Commission 72-55 Washington, DC 20555-0001 License Nos.: DPR-32/37 VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 AND ISFSI NOTIFICATION PURSUANT TO 10 CFR 72.212(b}{1) PRIOR TO FIRST STORAGE OF SPENT FUEL UNDER A GENERAL LICENSE Pursuant to 10 CFR 72.212, "Conditions of general license issued under 72.210,"

paragraph (b)(1 ), Virginia Electric and Power Company (Dominion Energy Virginia) is notifying the Nuclear Regulatory Commission (NRC) of our intent to begin loading Surry Power Station (SPS) Units 1 and 2 spent fuel into Transnuclear (TN) Americas NUHOMS EOS storage casks under the general license at SPS. Loading activities are scheduled to commence on or about May 2, 2022. Dominion Energy Virginia will use the TN Americas NUHOMS EOS storage system in accordance with the NRG issued Certificate of Compliance No. 1042.

Licensee Name: Virginia Electric and Power Company Licensee Address: 5000 Dominion Boulevard Glen Allen, VA 23060 Reactor License Nos.: DPR-32/37 Reactor Docket Nos.: 50-280/281 General License Point of

Contact:

Richard L. Ridder (804) 273-2415 If you have any questions, please contact Michael Whitlock, Corporate Nuclear Regulatory Affairs, at (804) 273-3123.

Doug as C. Lawrence Vice esident - Nuclear Engineering and Fleet Support Commitments made by this letter: None

Serial No.22-007 Notification prior to first storage of spent fuel Page 2 of 2 cc: U.S. Nuclear Regulatory Commission - Region II Regional Administrator Marquis One Tower 245 Peachtree Center Avenue N.E., Suite 1200 Atlanta, Georgia 30303-3415 Mr. L. John Klos NRG Project Manager -Surry U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 9 E3 11555 Rockville Pike Rockville, Maryland 20852-2738 Ms. Yen-Ju Chen Senior Project Manager U.S. Nuclear Regulatory Commission Two White Flint North Mail Stop 4834 11545 Rockville Pike Rockville, MD 20852-2738 NRG Senior Resident Inspector Surry Power Station