MONTHYEARML22012A3012022-01-12012 January 2022 Incoming Request-Davis-Besse-Energy Harbor Nuclear Corp Project stage: Request ML22013B1752022-01-13013 January 2022 Response to Request for Additional Information Related to Request for Exemption from Specific Requirements of 10 CFR 26, Fitness for Duty Programs (COVID-19) Project stage: Response to RAI ML22012A3992022-01-14014 January 2022 Exemption from Specific Requirements of 10 CFR Part 26 (EPID L-2022-LLE-0002 (COVID-19)) Project stage: Approval 2022-01-13
[Table View] |
|
---|
Category:Exemption from NRC Requirements
MONTHYEARML22034A9832022-02-15015 February 2022 FRN - Notice of Issuance of COVID-19 Exemptions Issued in January 2022 ML22012A3992022-01-14014 January 2022 Exemption from Specific Requirements of 10 CFR Part 26 (EPID L-2022-LLE-0002 (COVID-19)) ML22012A3012022-01-12012 January 2022 Incoming Request-Davis-Besse-Energy Harbor Nuclear Corp ML21098A1802021-04-19019 April 2021 Temporary Exemption from Certain Biennial Emergency Preparedness Exercise Requirements of 10 CFR Part 50, Appendix E, Section Iv.F L-21-070, Request for One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic2021-03-15015 March 2021 Request for One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic ML20335A0902020-12-21021 December 2020 Federal Register Notice - November 2020 COVID-19 Exemptions ML20345A2052020-12-15015 December 2020 Exemption from Annual Force-on-Force Exercise Requirement of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Subsection VI.C.3(I)(1) (EPID L-2020-LLE-0175 (COVID-19)) L-20-313, Response to Request for Additional Information Regarding Request for Exemption -Part 73 Force-on-Force2020-12-0707 December 2020 Response to Request for Additional Information Regarding Request for Exemption -Part 73 Force-on-Force ML20323A4122020-11-19019 November 2020 Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2020-LLE-0208 (COVID-19)) ML20323A1692020-11-18018 November 2020 Incoming Request-Davis-Besse-Energy Harbor Nuclear Corp L-20-280, Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-10-29029 October 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic ML20119B0682020-05-0808 May 2020 Exemption ML20119B0702020-05-0808 May 2020 Federal Register Notice ML20119B0722020-05-0808 May 2020 Request for Temporary Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (Epids L-2020-LLE-0026 Through L-2020-LLE-0032) L-20-141, Exemption Request Due to COVID-19 Pandemic2020-04-23023 April 2020 Exemption Request Due to COVID-19 Pandemic ML19067A0212019-06-0404 June 2019 FENOC Fleet - Exemption from the Requirements of 10 CFR 73.55(p)(1)(i) and (II) Related to the Suspension of Security Measures in an Emergency or During Severe Weather ML1030602082010-12-14014 December 2010 Exemption from the Requirements of 10 CFR Part 50.61 and 10 CFR Part 50, Appendix G Letter NRC-2010-0240, One-time Exemption from the Requirements of 10 CFR Part 26, Section 26.205(d)(3)2010-06-24024 June 2010 One-time Exemption from the Requirements of 10 CFR Part 26, Section 26.205(d)(3) ML1017304822010-06-24024 June 2010 One-time Exemption from the Requirements of 10 CFR Part 26, Section 26.205(d)(3) ML1017304572010-06-24024 June 2010 One-time Exemption from the Requirements of 10 CFR Part 26, Section 26.205(d)(3) Ltr L-10-166, Request for One-Time Exemption from the Requirements of 10 CFR 26.205(d)(3)2010-05-28028 May 2010 Request for One-Time Exemption from the Requirements of 10 CFR 26.205(d)(3) ML1007407042010-03-26026 March 2010 Exemption from the Requirements of 10 CFR Part 73, Section 73.55 ML0509701362005-07-21021 July 2005 Exemption from the Requirements of 10 CFR Part 50, Appendix R, Section III.G.3 ML0425906412004-11-29029 November 2004 Exemption, Authorize New Method of Preventing Boric Acid Precipitation within the Reactor Vessel Core Region Following Certain Loss-of-Coolant Accidents ML0201003662002-12-26026 December 2002 Exemption from Requirements of 10 CFR Part 50, Section Iii.G of Appendix R 2022-02-15
[Table view] |
Text
COVID-19 Related Request for Exemption from Part 26 Work Hours Requirements Submitted: Jan 12, 2022
- 1. Submitter Name/Title:
Terry J. Brown, Site Vice President, DavisBesse Nuclear
- 2. Email Address Please enter the email address for which you would like to receive communications regarding this request.
rwoesterle@energyharbor.com
- 3. Organization Energy Harbor Nuclear Corp
- 4. Plant Name Davis-Besse
- 5. Plant Unit(s): 1
- 6. Need By Date 2022-01-14
- 7. Docket Number(s)
Example: 05000313 05000346
- 8. License Number(s)
Example: DPR-51 NPF-3
- 9. NRC Licensing Project Manager B. PURNELL
- 10. Statement that the licensee above can no longer meet the work hour controls of 10 CFR 26.205(d) for certain personnel or groups of personnel specified in 10 CFR 26.4(a) because of site specific issues as a result of the COVID-19 public health emergency (PHE).
Energy Harbor Nuclear Corp. has determined that DavisBesse Nuclear Power Station personnel can no longer effectively meet the workhour controls of 10 CFR 26.205(d) for the covered workers. Energy Harbor Nuclear Corp. only plans to implement the alternative controls when warranted by the COVID19 conditions during the exemption period, that is, normal work hour controls would be continued or restored as conditions allow. Groups covered by the exemption request include 26.4(a)(1) Operators, 26.4(a)(2)
Health Physics and Chemistry, 26.4(a)(3) Fire Brigade, 26.4(a)(4) Maintenance, and 26.4(a)(5) Security.
- 11. List of personnel or groups of personnel specified in 10 CFR 26.4(a) for which the licensee will maintain current work hour controls under 10 CFR 26.205(d)(1)-(d)(7).
None
- 12. List and description of alternative controls for the management of fatigue to address site specific issues as a result of the COVID-19 PHE.
Energy Harbor Nuclear Corp. will continue to follow the fatigue management controls, behavioral observation requirements, and selfdeclaration allowances currently delineated within the Energy Harbor Nuclear Corp. work hour control program and procedure.
- 13. Date when the licensee will begin implementing its site-specific COVID-19 PHE fatigue-management controls for personnel specified in 10 CFR 26.4(a) 2022-01-14
- 14. The time when the licensee will begin implementing its alternative controls for the management of fatigue for personnel (or group of personnel) specified in 10 CFR 26.4(a).
0700
- 15. Statement that the licensees site specific alternative controls for the management of fatigue are consistent with the minimum alternative controls listed below.
DavisBesse Nuclear Power Station sitespecific COVID19 PHE fatiguemanagement controls are consistent with the constraints outlined in the March 28, 2020, letter.
- 16. Does Licensee continue to meet the requirements of 10 CFR 26.33, Behavioral observation; 10 CFR 26.209, Self declarations; and 26.211, Fatigue assessments.
Yes
- 17. The alternative controls include the following, as a minimum:
- 1. Individuals will not work more than 16 work-hours in any 24-hour period and not more than 86 work-hours in any 7-day period, excluding shift turnover;
- 2. A minimum 10-hour break is provided between successive work periods;
- 3. 12-hour shifts are limited to not more than 14 consecutive days;
- 4. A minimum of 6-days off are provided in any 30-day period; and
- 5. Changes in actions to meet requirements for behavioral observation for both acute and cumulative fatigue and self declaration during the period of the
exemption as appropriate due to potential for increased worker fatigue.
Yes
- 18. Additional Information:
Use the area below to provide any additional information related to your exemption request.
Should you have any questions or require additional information, please contact Mr.
Robert W. Oesterle, Manager, Site Regulatory Compliance and Emergency Response, at (419) 3217462.