ML22010A243

From kanterella
Jump to navigation Jump to search
Cyber-Security RFI and Notification Letter - Template
ML22010A243
Person / Time
Issue date: 05/25/2022
From: Michael Brown
NRC/NSIR/DPCP/CSB
To:
Brown M
References
Download: ML22010A243 (13)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION [Insert; I, II, III or IV]

[Insert Region Address; Street, Suite #]

[Insert Region Address; City, State, Zip Code]

[Month Day], 2022

[Name Title]

[Address]

SUBJECT:

[PLANT NAME] - INFORMATION REQUEST FOR THE CYBER-SECURITY BASELINE INSPECTION, NOTIFICATION TO PERFORM INSPECTION 05000[XXX]/403[XXXX]; 05000[XXX]/403[XXXX]

Dear [Name]:

On [date, first day onsite], the U.S. Nuclear Regulatory Commission (NRC) will begin a baseline inspection in accordance with Inspection Procedure (IP) 71130.10 Cyber-Security, Revision 0 at your

[Plant Name]. The inspection will be performed to evaluate and verify your ability to meet the Milestone 8 (i.e., full implementation) requirements of the NRCs Cyber-Security Rule, Title 10, Code of Federal Regulations (CFR), Part 73, Section 54, Protection of Digital Computer and Communication Systems and Networks. The onsite portion of the inspection will take place during the weeks of

[provide dates], and [provide dates].

Experience has shown that baseline inspections are extremely resource intensive, both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for documents needed for the inspection. These documents have been divided into four groups.

The first group specifies information necessary to assist the inspection team in choosing the focus areas (i.e., sample set) to be inspected by the cyber-security IP. This information should be made available via compact disc and delivered to the regional office no later than [provide date - twelve weeks prior to the start of the inspection]. The inspection team will review this information and, by [provide date -

eight weeks prior to the start of the inspection], will request the specific items that should be provided for review.

The second group of additional requested documents will assist the inspection team in the evaluation of the critical systems and critical digital assets (CSs/CDAs), defensive architecture, and the areas of the licensees CSP selected for the cyber-security inspection. This information will be requested for review in the regional office prior to the inspection by [provide date - four weeks prior to the start of the inspection], as identified above.

[Name] The third group of requested documents consists of those items that the inspection team will review, or need access to, during the inspection. Please have this information available by the first day of the onsite inspection, [provide date].

The fourth group of information is necessary to aid the inspection team in tracking issues identified as a result of the inspection. It is requested that this information be provided to the lead inspector as the information is generated during the inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.

The lead inspector for this inspection is [Lead inspector name]. We understand that our regulatory contact for this inspection is [provide name of plant contact] of your organization. If there are any questions about the inspection or the material requested, please contact the lead inspector at [provide phone number] or via e-mail at [provide email address].

This letter contains mandatory information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB) approved these information collections under approval number 3150-0011. The burden to the public for these information collections is estimated to average 40 hour4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br />(s) per response. Send comments regarding this information collection to the FOIA, Library and Information Collection Branch, Office of the Chief Information Officer, Mail Stop: T6-A10M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by email to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0011) OMB, Washington, DC 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number In accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

Inspector name, title Engineering Branch 3 Division of Reactor Safety Docket Nos. 50-[XXX]; 50-[XXX]

License Nos. [XXX]-[XX]; [XXX]-[XX]

Enclosure:

[Plant Name]

Cyber-Security Inspection Document Request cc w/encl: Distribution via LISTSERV

[PLANT NAME] CYBER-SECURITY INSPECTION DOCUMENT REQUEST Inspection Report: 05000[xxx]/403[xxx]; 05000[xxx]/403[xxx]

Inspection Dates: Weeks of [provide dates], and [provide dates]

Inspection Procedure: IP 71130.10, Cyber-Security, Revision 0

Reference:

MLXXXXXXXX, Guidance Document for Development of the Request for Information (RFI) and Notification Letter for Full-Implementation of the Cyber-Security Inspection, Revision 1 NRC Inspectors: [NRC Inspector Name], Lead [NRC Inspector Name]

xxx-xxx-xxxx xxx-xxx-xxxx

[E-mail address] [E-mail address]

NRC Contractors: [NRC Contractor Name] [NRC Contractor Name]

301-xxx-xxxx 301-xxx-xxxx

[E-mail address] [E-mail address]

I. Information Requested for In-Office Preparation The initial request for information (i.e., first RFI) concentrates on providing the inspection team with the general information necessary to select appropriate components and CSP elements to develop a site-specific inspection plan. The first RFI is used to identify the list of critical systems and critical digital assets (CSs/CDAs) plus operational and management (O&M) security control portions of the CSP to be chosen as the sample set required to be inspected by the cyber-security IP. The first RFIs requested information is specified below in Table RFI #1. The Table RFI #1 information is requested to be provided to the regional office by [provide date -

twelve weeks prior to the start of the inspection], or sooner, to facilitate the selection of the specific items that will be reviewed during the onsite inspection weeks.

The inspection team will examine the returned documentation from the first RFI and identify/select specific systems and equipment (e.g., CSs/CDAs) to provide a more focused follow-up request to develop the second RFI. The inspection team will submit the specific systems and equipment list to your staff by [provide date - eight weeks prior to the start of the inspection], which will identify the specific systems and equipment that will be utilized to evaluate the CSs/CDAs, defensive architecture, and the areas of the licensees CSP selected for the cyber-security inspection. We request that the additional information provided from the second RFI be made available to the regional office prior to the inspection by [provide date -

Enclosure

[PLANT NAME] CYBER-SECURITY INSPECTION DOCUMENT REQUEST four weeks prior to the start of the inspection]. All requests for information shall follow the guidance document USNRC-XXXXX referenced above.

Enclosure

[PLANT NAME] CYBER-SECURITY INSPECTION DOCUMENT REQUEST The required Table RFI 1 information shall be provided on either digital media (CD/DVD) or an online repository to the lead inspector by [provide date - twelve weeks prior to the start of the inspection]. The preferred file format for all lists is a searchable Excel spreadsheet file. The information should be indexed and hyper-linked to facilitate ease of use. If you have any questions regarding this information, please call the inspection team leader as soon as possible.

Table RFI #1 Section 3, Paragraph Number/Title: IP Ref A list of all Identified Critical Systems and Critical Digital Assets,-

highlight/note any . additions, deletions, reclassifications due to new 1 Overall guidance from white papers, changes to NEI 10-04, 13-10, etc. since the last cyber security inspection.

2 A list of EP and Security onsite and offsite digital communication systems Overall Network Topology Diagrams to include information and data flow for 3 Overall critical systems in levels 2, 3 and 4 (If available) 4 Ongoing Monitoring and Assessment program documentation 03.01(a) 5 The most recent effectiveness analysis of the Cyber Security Program 03.01(b) 6 Vulnerability screening/assessment and scan program documentation 03.01(c)

Cyber Security Incident response documentation, including incident detection, response, and recovery documentation as well as contingency 03.02(a) 7 plan development, implementation and including any program and documentation that requires testing of security boundary device 03.04(b) functionality 8 Device Access and Key Control documentation 03.02(c) 9 Password/Authenticator documentation 03.02(c) 10 User Account/Credential documentation 03.02(d)

Portable Media and Mobile Device control documentation, including kiosk 11 03.02(e) security control assessment/documentation Design change/ modification program documentation and a List of all design changes completed since the last cyber security inspection, including 12 03.03(a) either a summary of the design change or the 50.59 documentation for the change.

6

[PLANT NAME] CYBER-SECURITY INSPECTION DOCUMENT REQUEST Table RFI #1 Section 3, Paragraph Number/Title: IP Ref 03.03(a),

Supply Chain Management documentation including any security impact 13 (b) and analysis for new acquisitions (c)

Configuration Management documentation including any security impact 03.03(a) 14 analysis performed due to configuration changes since the last inspection and (b)

Cyber Security Plan and any 50.54(p) analysis to support changes to the 15 03.04(a) plan since the last inspection 16 Cyber Security Metrics tracked (if applicable) 03.06 (b)

Provide documentation describing any cyber security changes to the access 17 Overall authorization program since the last cyber security inspection.

Provide a list of all procedures and policies provided to the NRC with their 18 Overall descriptive name and associated number (if available) 19 Performance testing report (if applicable) 03.06 (a)

In addition to the above information please provide the following:

(1) Electronic copy of the UFSAR and technical specifications.

(2) Name(s) and phone numbers for the regulatory and technical contacts.

(3) Current management and engineering organizational charts.

Based on this information, the inspection team will identify and select specific systems and equipment (e.g., CSs/CDAs) from the information requested by Table RFI #1 and submit a list of specific systems and equipment to your staff by [provide date - eight weeks prior to the start of the inspection] for the second RFI (i.e., RFI #2).

II. Additional Information Requested to be Available Prior to Inspection.

As stated in Section I above, the inspection team will examine the returned documentation requested from Table RFI #1 and submit the list of specific systems and equipment to your staff by [provide date - eight weeks prior to the start of the inspection] for the second RFI (i.e., RFI #2). The second RFI will request additional information required to evaluate the CSs/CDAs, defensive architecture, and the areas of the licensees CSP selected for the cyber-security inspection. The additional information requested for the specific systems and equipment is identified in Table RFI #2. All requested information shall follow the guidance document USNRC-XXXXX referenced above.

7

[PLANT NAME] CYBER-SECURITY INSPECTION DOCUMENT REQUEST The Table RFI 2 information shall be provided to the lead inspector by [provide date - four weeks prior to the start of the inspection]. The preferred file format for all lists is a searchable Excel spreadsheet. The information should be indexed and hyper-linked to facilitate ease of use. If you have any questions regarding this information, please call the inspection team leader as soon as possible.

Table RFI #2 Section 3, Paragraph Number/Title: Items For the system(s) chosen for inspection provide:

1 Ongoing Monitoring and Assessment activity performed on the system(s) 03.01(a) 2 All Security Control Assessments for the selected system(s) 03.01(a)

All vulnerability screenings/assessments associated with or scans 3 performed on the selected system(s) since the last cyber security 03.01(c) inspection Documentation (including configuration files and rules sets) for Network-based Intrusion Detection/Protection Systems (NIDS/NIPS), Host-based 4 03.02(b)

Intrusion Detection Systems (HIDS), and Security Information and Event Management (SIEM) systems for system(s) chosen for inspection )

Documentation (including configuration files and rule sets) for intra-5 security level firewalls and boundary devices used to protect the selected 03.02(c) system(s)

Copies of all periodic reviews of the access authorization list for the 6 03.02(d) selected systems since the last inspection 7 Baseline configuration data sheets for the selected CDAs 03.03(a)

Documentation on any changes, including Security Impact Analyses, 8 03.03(b) performed on the selected system(s) since the last inspection Copies of the purchase order documentation for any new equipment 9 03.03(c) purchased for the selected systems since the last inspection Copies of any reports/assessment for cyber security drills performed since 03.02(a) 10 the last inspection. 03.04(b)

Copy of the individual recovery plan(s) for the selected system(s) including 03.02(a) 11 documentation of the results the last time the backups were executed. 03.04(b) 8

[PLANT NAME] CYBER-SECURITY INSPECTION DOCUMENT REQUEST Table RFI #2 Section 3, Paragraph Number/Title: Items Corrective actions taken as a result of cyber security incidents/issues to 12 include previous NRC violations and Licensee Identified Violations since 03.04(d) the last cyber security inspection 9

[PLANT NAME] CYBER-SECURITY INSPECTION DOCUMENT REQUEST III. Information Requested to be Available on First Day of Inspection For the specific systems and equipment identified in Section II above, provide the following RFI (i.e., Table 1ST Week Onsite) to the team by [provide date], the first day of the inspection. All requested information shall follow the guidance document USNRC-XXXXX referenced above.

The preferred file format for all lists is a searchable Excel spreadsheet file. The information should be indexed and hyper-linked to facilitate ease of use. If you have any questions regarding this information, please call the inspection team leader as soon as possible.

Table 1ST Week Onsite Section 3, Paragraph Number/Title: Items Any cyber security event reports submitted in accordance with 10 CFR 1 03.04(a) 73.77 since the last cyber security inspection Updated Copies of corrective actions taken as a result of cyber security incidents/issues, to include previous NRC violations and Licensee 2 03.04(d)

Identified Violations since the last cyber security inspection, as well as vulnerability-related corrective actions In addition to the above information please provide the following:

(1) Copies of the following documents do not need to be solely available to the inspection team as long as the inspectors have easy and unrestrained access to them.

a. Updated Final Safety Analysis Report, if not previously provided;
b. Original FSAR Volumes;
c. Original SER and Supplements;
d. FSAR Question and Answers;
e. Quality Assurance Plan;
f. Technical Specifications, if not previously provided;
g. Latest IPE/PRA Report; and (2) Vendor Manuals, Assessment and Corrective Actions:
a. The most recent Cyber-Security Quality Assurance (QA) audit and/or self-assessment; and 10

[PLANT NAME] CYBER-SECURITY INSPECTION DOCUMENT REQUEST

b. Corrective action documents (e.g., condition reports, including status of corrective actions) generate as a result of the most recent Cyber-Security Quality Assurance (QA) audit and/or self-assessment.

IV. Information Requested To Be Provided Throughout the Inspection (1) Copies of any corrective action documents generated as a result of the inspection teams questions or queries during the inspection.

(2) Copies of the list of questions submitted by the inspection team members and the status/resolution of the information requested (provided daily during the inspection to each inspection team member).

If you have any questions regarding the information requested, please contact the inspection team leader.

11

[Name]

Letter to [Name, provide First M. Last] from [Name, provide First M. Last] dated [Date, provide date]

SUBJECT:

[PLANT NAME] - INFORMATION REQUEST FOR THE CYBER-SECURITY BASELINE INSPECTION, NOTIFICATION TO PERFORM INSPECTION 05000[XXX]/403[XXXX]; 05000[XXX]/403[XXXX]

DISTRIBUTION:

[PLANT NAME] CYBER-SECURITY INSPECTION DOCUMENT REQUEST DOCUMENT NAME: G:\CSD\Milestone 8\cyber-securityRFI.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME DATE OFFICIAL RECORD COPY 13