Enclosure 1: Shine Final Safety Analysis Report (FSAR) Change Summary
ML21326A207
Person / Time
Site: SHINE Medical Technologies
Issue date: 11/22/2021
From:
SHINE Technologies
To:
Office of Nuclear Reactor Regulation
Shared Package
ML21326A205 List:
References
2021-SMT-0164
Download: ML21326A207 (1)


Text

ENCLOSURE 1 SHINE TECHNOLOGIES, LLC SHINE TECHNOLOGIES, LLC APPLICATION FOR AN OPERATING LICENSE SUPPLEMENT NO. 13 AND RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION FINAL SAFETY ANALYSIS REPORT CHANGE

SUMMARY

Summary Description of Changes FSAR Impacts Update to relocate neutron flux detection system Section 7.4, (NFDS) cabinets outside of the facility control room. Figure 7.6-1, and Section 7.8 Update to remove direct communication between Section 7.1, NFDS and the process integrated control system Figure 7.1-1, (PICS). Section 7.3, and Section 7.8 Update terminology from master-slave to primary- Section 7.4, secondary. Figure 7.4-2, Section 7.5, and Section 9b.7 Update communication logic between the PICS and Figure 7.4-1, and the target solution vessel (TSV) reactivity protection Figure 7.5-1 system (TRPS), and update communication logic between PICS and engineered safety systems actuation system (ESFAS).

Update TSV off-gas system (TOGS) flowmeter Table 7.4-1 response time.

Update to clarify failsafe switch operation for TRPS Figure 7.4-1, and and ESFAS. Figure 7.5-1 Final Safety Analysis Report (FSAR) mark-ups related to the SHINE Technologies, LLC (SHINE) responses to requests for additional information are provided as Attachment 1 to (non-public version) and Enclosure 3 (public version). FSAR mark-ups associated with the above FSAR changes are included with those mark-ups provided as Attachment 1 to and Enclosure 3.

Page 1 of 1