ML21312A101

From kanterella
Jump to navigation Jump to search
Information Request to Support Post-Approval Site Inspection for License Renewal; Inspection Report 05000387/2022011
ML21312A101
Person / Time
Site: Susquehanna Talen Energy icon.png
Issue date: 11/08/2021
From: Mel Gray
Division of Operating Reactors
To: Berryman B
Susquehanna
Gray M
References
IR 2022-011
Download: ML21312A101 (7)


See also: IR 05000387/2022011

Text

November 8, 2021

Mr. Brad Berryman

Senior Vice President and Chief Nuclear Officer

Susquehanna Nuclear, LLC

769 Salem Blvd., NUCSB3

Berwick, PA 18603

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNIT 1 - INFORMATION

REQUEST TO SUPPORT POST-APPROVAL SITE INSPECTION FOR

LICENSE RENEWAL; INSPECTION REPORT 05000387/2022011

Dear Mr. Berryman:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

Region I staff will conduct a license renewal post-approval inspection at your Susquehanna

Steam Electric Station, Unit 1. Niklas Floyd, a Senior Reactor Inspector from the NRCs

Region I office, will lead the inspection team. The inspection will be conducted in accordance

with Inspection Procedure 71003, Post-Approval Site Inspection for License Renewal, dated

July 1, 2016 (ADAMS Accession No. ML16013A260). This inspection is described as a

Phase 2 license renewal inspection in the referenced inspection procedure and is conducted

three months to one year prior to the plant entering its period of extended operation.

The inspection will assess the adequacy of the planned and/or completed activities and

programs described in the regulatory commitments and license conditions added as part of your

renewed license. This inspection will also evaluate the need for additional follow-up inspections

(Phase 3) under Inspection Procedure 71003 or as part of the Reactor Oversight Program.

Finally, an inspector will perform a license renewal inspection (Phase 1) in April 2022 to observe

implementation of aging management programs and activities that are only accessible during a

scheduled plant outage.

This onsite Phase 2 inspection is scheduled for the weeks of January 11 and January 25, 2022.

In order to minimize the impact on the site and to ensure a productive inspection for both

parties, we have enclosed a request for information needed for the inspection. It is important

that these documents are up-to-date and complete in order to minimize the number of additional

documents requested during the preparation and/or the onsite portions of the inspection.

Insofar as possible, this information should be provided electronically to the lead inspector. The

information request has been divided into two groups:

The first group lists information necessary for our initial inspection scoping and in-office

preparation activities. During the in-office preparation activities, the team will identify as

much as possible the information and activities to be reviewed during the inspection.

This information should be provided to the lead inspector by December 27, 2021.

B. Berryman

2

The second group includes the additional information required for the team to review the

selected activities. This information should be provided to the team by January 4, 2021

or made available upon arrival onsite January 11, 2022.

If there are any questions about the inspection or the information requested in the enclosure,

please do not hesitate to contact the lead inspector at 610-337-5282 or via e-mail at

Niklas.Floyd@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control Number 3150-

0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a

request for information or an information collection requirement unless the requesting document

displays a currently valid Office of Management and Budget Control Number.

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,

Exemptions, Requests for Withholding.

Sincerely,

Mel Gray, Chief

Engineering Branch 1

Division of Operating Reactor Safety

Docket No. 50-387

License No. NPF-14

Enclosure:

Information Request Post-Approval

Site Inspection for License Renewal - Phase 2

cc: Distribution via ListServ

Melvin K.

Gray

Digitally signed by Melvin

K. Gray

Date: 2021.11.08 11:17:47

-05'00'

ML21312A101

x

SUNSI Review

x

Non-Sensitive

Sensitive

x

Publicly Available

Non-Publicly Available

OFFICE RI/DORS

RI/DORS

NAME

NFloyd

MGray

DATE

11/8/21

11/8/21

INFORMATION REQUEST

POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL - PHASE II

Inspection Report: 05000387/2022011

Onsite Inspection Dates:

January 10, through January 14, 2022; and

January 24, through January 28, 2022

Inspection Procedure:

Inspection Procedure 71003, Post-Approval Site Inspection for

License Renewal, dated July 1, 2016

Lead Inspector:

Niklas Floyd, Senior Reactor Inspector

610-337-5282

Niklas.Floyd@nrc.gov

I.

Information Requested Prior to the On-site Inspection Week (General Info)

The following information is requested by December 27, 2021, or sooner, to facilitate

inspection preparation. This section of the request identifies general information that will

help the inspectors to understand the applicable administrative procedures and overall

completion status of license renewal activities. As such, the information requested herein is

not aimed to a particular regulatory commitment, license condition, aging management

program (AMP), or time-limited aging analysis (TLAA).

Feel free to contact the lead inspector as soon as possible if you have any questions

regarding this information request. Please provide the information electronically in pdf files,

Excel, or other searchable formats, preferably on some portable electronic media (e.g., CD-

ROM, DVD, etc.). The files should contain descriptive names, be indexed, and hyperlinked

to facilitate ease of use. Information in lists should contain enough information to be easily

understood by someone who has knowledge of light water reactor technology.

(1)

Sections of the quality assurance program manual applicable to license renewal

activities.

(2)

Copies of the following procedures:

Correction Action Program

Operating Experience

Regulatory Commitment Change Process

(3)

Updated Final Safety Analysis Report (UFSAR) supplement for license renewal

submitted with the license renewal application (LRA), including the latest version of the

UFSAR supplement submitted to the NRC per 10 CFR 50.71.

(4)

Post-approval evaluations or assessments performed to verify that in-scope structures,

systems, or components (SSCs) were not excluded from the LRA and appropriate

aging management has been considered in accordance with 10 CFR 54.37(b).

(5)

List of plant modifications with a brief description of the modification scope that were

approved and/or implemented from the date the LRA was submitted to the date the

renewed license was issued.

INFORMATION REQUEST

POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL - PHASE II

(6)

Self-assessments performed after the renewed license was issued associated with the

implementation of license renewal commitments, including AMPs and TLAAs.

(7)

Gap analyses performed to assess the differences between the current AMPs and

the recommendations in the latest revision of NUREG-1801, Generic Aging Lessons

Learned (GALL), and subsequent NRC Interim Staff Guidance.

(8)

Site-specific responses and/or evaluations for NRC generic communications

associated with license renewal that were issued after the renewed license was

granted.

(9)

List of your license renewal commitments with a description of the overall completion

status of action items associated with each commitment, including AMPs and TLAAs.

(10) Description of administrative controls that will be used to ensure that all activities due

prior to (and during) the period of extended operation (PEO) will be satisfactorily

completed as described in the license renewal documents.

(11) Description of plans or processes that would be used during the PEO to continuously

incorporate operating experience into license renewal activities.

(12) Internal/external self-assessment and associated corrective action documents

generated in preparation for this inspection.

(13) License renewal organizational chart and points of contact for this inspection, including

the appropriate regulatory assurance, engineering, and license renewal staff.

II. Information Requested to Be Available by January 4, 2022 (Specific Requests for each

License Renewal Commitment, including associated AMP and TLAA)

The following information should be separated for each regulatory commitment, especially if

provided electronically (e.g., a folder for each commitment named after the commitment that

includes the information requested below). The commitment should include the associated

AMP and TLAAs. This section is focused on documentation demonstrating completion of

each specific license renewal commitment.

(1)

Program basis documents and administrative procedures describing key program

attributes such as program objectives, scope, detection and monitoring methods,

administrative controls, acceptance criteria, corrective actions, and scope expansion

requirements.

(2)

Implementing procedures for program activities (e.g., visual examination procedures,

ultrasonic examination procedures, maintenance procedures, system walkdowns, etc).

(3)

Updated license renewal scoping drawings showing the SSCs within the scope of the

AMP.

(4)

Applicable sections of the LRA and the NRCs safety evaluation report.

INFORMATION REQUEST

POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL - PHASE II

(5)

Applicable Requests for Additional Information issued by NRCs technical reviewers

during the review of the LRA and corresponding responses.

(6)

Copy of or ready access to the key industry standards that will be followed during the

PEO for the implementation of the program (e.g., American Society of Mechanical

Engineers Boiler and Pressure Vessel Code, Electric Power Research Institute

Guidelines, Nuclear Energy Institute Guidelines, etc).

(7)

Description of changes made to the license renewal commitment, including the

associated technical and regulatory evaluations supporting the change.

(8)

Description of activities completed to meet license conditions, license renewal

commitments, and the UFSAR. For example, this should include completed Work

Orders with associated inspection reports describing the work done and the results of

the inspection.

(9)

Description of instances where examination scope expansion was required based on

the initial examination of an SSC for license renewal. Please describe the logic to

select the scope expansion, and any resulting changes to the AMP.

(10) Description of instances where examination scope changes were required based on

limitations encountered during the initial examination of an SSC for license renewal.

Please describe the actions taken, and any resulting changes to the AMP.

(11) Description of pending activities due prior to the PEO, which are necessary to meet

license conditions, license renewal commitments, and the activities described in the

UFSAR. For example, this may include a list of pending Work Orders with a brief

description of the work to be performed.

(12) Copy of any correspondence between the licensee and the NRC, after the license was

issued, associated with regulatory issues affecting the license renewal commitment.

For example, this may include notifications of commitment changes, or license

amendment requests, affecting a license condition or a license renewal commitment.

(13) List of Corrective Action Program documents (e.g., Condition Reports) associated with

the implementation of the AMP. This includes unacceptable aging effects identified

during the implementation of license renewal activities and programmatic deficiencies

requiring resolution.

(14) Copy of evaluations performed for applicable external/internal Operating Experience

issues associated with license renewal. This request is limited to Operating Experience

items issued after the renewed operating license was granted.

INFORMATION REQUEST

POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL - PHASE II

III. Information Requested to be Provided Throughout the Inspection

(1)

Copies of any corrective action documents generated as a result of the teams

questions or queries during this inspection.

(2)

Copies of the list of questions submitted by the team members and the

status/resolution of the information requested (please provide daily during the

inspection to each team member).