Miscellaneous Exam Material (Folder 1)
ML21293A141
Person / Time
Site: Millstone Dominion icon.png
Issue date: 09/21/2021
From:
Dominion Nuclear Connecticut
To: Thomas Setzer
Operations Branch I
Setzer T
Shared Package
ML20275A100 List:
References
EPID L-2021-OLL-0005
Download: ML21293A141 (3)


Text

Millstone 3 2021 NRC Written Exam Questions asked by applicants and answers given Question 51 (Jason Anderson): When you say Before any PEO actions are taken, do you mean before they take the actions they were dispatched to do?

Answer (Bob Royce): Yes.

Question 78 (Tim Adams): Do I assume this is the first bundle to be moved, or are there some bundles already moved?

Answer (Bob Royce): Do your best with the information given.

WRITTEN EXAM ITEM ANALYSIS MILLSTONE 3 INITIAL LICENSE EXAM SEPTEMBER 21, 2021 ADAMS package ML ML20275A100 3 questions (Q. 1, 79 & 100) had a high miss rate (>50%). All applicants were remediated. Training program changes are not required (existing objectives cover material).

Millstone 3 2021 NRC Written Exam Seating Chart Door (Closed, barricaded)

Restroom Tim Adams DSRO Empty Table Ryan Hastert DSRO Dennis Truesdale RO Brittany Wagner DSRO David Sparozic RO Rob Schmidt USRO Ryan Sherry USRO Matt Lupica RO Brian Ciezynski DSRO Jason Anderson RO Door (Locked Closed)

Stephen Lambert Jr.

RO Empty Table Paul Krabacher RO Ted DiAngelo USRO Proctor Desk