Comment (13) of Danielle Schefer on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2
ML21286A750
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 10/12/2021
From: Schefer D
- No Known Affiliation
To:
Office of Administration
References
86FR47525 00013, NRC-2020-0234
Download: ML21286A750 (1)


Text

10/13/21, 3:46 PM blob:https://www.fdms.gov/06e2c8c2-f5f6-4c7d-97d8-7e7a4aef4454 SUNI Review Complete Template=ADM-013 As of: 10/13/21 3:46 PM E-RIDS=ADM-03 Received: October 12, 2021 PUBLIC SUBMISSION ADD: Tam Tran, Sandra Figueroa, Mary Neely Status: Pending_Post Tracking No. kuo-xln8-es5w Comment (13)

Publication Date: Comments Due: October 12, 2021 8/25/2021 Submission Type: Web CITATION 86 FR 47525 Docket: NRC-2020-0234 Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Comment On: NRC-2020-0234-0144 Virginia Electric and Power Company; Dominion Energy Virginia; North Anna Power Station, Unit Nos.

1 and 2 Document: NRC-2020-0234-DRAFT-0155 Comment on FR Doc # 2021-18255 Submitter Information Name: Danielle Schefer Address:

Arlington, VA, 22207 Email: dmjohn2003@yahoo.com Phone: 7036159307 General Comment The NRC should require a new Environmental Impact Statement which includes a thorough examination of geologic risks. (This has not been done since the 2011 earthquake.)

A new assessment of Severe Accident Mitigation Alternatives (SAMA) should be conducted by Dominion. (The last SAMA occurred in 2001.)

Harvesting and testing of components of the North Anna reactors to determine if they can operate safely for 80 years.

A new assessment of the structural integrity of the Lake Anna damn which holds the water for cooling the reactors.

An updated plan for the safe storage of the increasing radioactive waste stored at the power station.

A full public hearing on the license application which allows the public to speak and considers independent expert testimony.