MONTHYEARML21189A1532021-07-0808 July 2021 Request for Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses Project stage: Request ML21187A0972021-07-0808 July 2021 Late Filed Allegations (Lfa) Process Project stage: Request ML21203A2762021-07-21021 July 2021 COL Docs - Acceptance Review of Southern Nuclear Operating Companys Request for Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses (EPID No. L-2021-LLE-0034 Project stage: Acceptance Review ML21281A2142021-10-0101 October 2021 VEGP Units 3 and 4 Supplement to Exemption from Operator Written Examination and Operating Test for Unit 4 Project stage: Request ML21279A1912021-11-22022 November 2021 Draft Vogtle Electric Generating Plant Units 3 and 4 - Request for Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses Project stage: Draft Approval ML21279A1852021-11-22022 November 2021, 23 November 2021 VEGP Unit 4 Exemption Request from Operator Written Examination and Operating Test Project stage: Request ML21279A1922021-11-23023 November 2021 Draft Federal Register Notice Regarding Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses Project stage: Draft Approval 2021-11-23
[Table View] |
|
---|
Category:Letter
MONTHYEARML24032A0252024-02-0505 February 2024 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026-2023009 ML24010A0712024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports and Recordkeeping and Suspicious Activity Reporting) ML24031A6102024-01-31031 January 2024 Cyber Security Inspection Report 05200026/2024401 - Public ML24029A0592024-01-30030 January 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report Enclosure 2, GAE-NRCD-RF-LR-000002 P-Attachment, Rev. 0 ML24016A1132024-01-30030 January 2024 Correction of Unit 1 Amendment Nos. 96 and 190 and Unit 2 Amendment Nos. 74 and 173 Adoption of Standard Technical Specifications Westinghouse Plants NL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R232024-01-29029 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 IR 05000424/20244032024-01-26026 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000424/2024403; 05000425/2024403 NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23347A2092024-01-17017 January 2024 Voluntary Requests for Data, Information, And/Or Observation ML23279A0042024-01-17017 January 2024 Amendment No. 194 to Remove Combined License Appendix C NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) ML23317A2072023-12-22022 December 2023 Issuance of Amendments 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-1448 ML23335A1222023-12-19019 December 2023 Safety Evaluation Regarding Implementation of Mitigating Strategies Related to Order EA-12-049 (EPID L-2023-LRQ-0002) - Letter ML23353A1702023-12-19019 December 2023 LAR-22-002, TS 3.8.3 Inverters Operating Completion Time Extension Letter ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23338A2182023-12-0606 December 2023 Project Manager Reassignment NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 ML23318A4582023-11-14014 November 2023 Integrated Inspection Report 05200025/2023003 ML23312A3502023-11-14014 November 2023 Integrated Inspection Report 05200026/2023003 ML23306A3552023-11-0808 November 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 052000/262023008 ML23268A0572023-11-0707 November 2023 Issuance of Amendments 194 & 191 Request for License Amendment Relocation of Technical Specification 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003) IR 05000424/20234022023-11-0606 November 2023 Security Baseline Inspection Report 05000424/2023402 and 05000425/2023402 IR 05000424/20230032023-10-27027 October 2023 Integrated Inspection Report 05000424/2023003 and 05000425/2023003 ML23291A1512023-10-18018 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 0520026/2024401 ML23263A9852023-10-12012 October 2023 Issuance of Amendments Nos. 221 and 204, Regarding Technical Specification 5.5.11.C, Acceptance Criteria for Charcoal Filter Testing ML23283A0472023-10-0808 October 2023 Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0745, Refueling Outage 1R24 Steam Generator Tube Inspection Report2023-09-22022 September 2023 Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23254A2032023-09-13013 September 2023 Initial Test Program and Operational Programs Inspection Report 05200025/2023013 ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report ML23234A2352023-09-0808 September 2023 Request for Withholding Information from Public Disclosure Notification of Full Compliance of Required Action for NRC Order EA-12-049 Mitigation Strategies for Beyond-Design-Basis External Events IR 05000424/20230912023-09-0505 September 2023 Plan Units 1 and 2 - NRC Investigation Report 2-2022-006 and Notice of Violation - NRC Inspection Report 05000424/2023091 and 05000425/2023091 ML23234A3002023-09-0101 September 2023 NRC Integrated Inspection Report 05200026/2023003 ML23243A0092023-08-31031 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 & 4 (Report 05200025 2023005 & 05200026 2023005) NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2) ML23243B0252023-08-30030 August 2023 Exam Corporate Notification Letter (210 Day) IR 05000424/20230052023-08-29029 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2023005 and 05000425/2023005 NL-23-0666, License Amendment Request: Remove Combined License Appendix C (LAR 23-008)2023-08-28028 August 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-008) 2024-02-05
[Table view] |
Text
November 22, 2021 Mr. Brian H. Whitley Director Regulatory Affairs Southern Nuclear Operating Company Inc.
3535 Colonnade Parkway, Bin N-226-EC Birmingham, AL 35243
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT UNITS 3 AND 4 EXEMPTION FROM WRITTEN EXAMINATION AND OPERATING TEST FOR UNIT 4 OPERATOR LICENSES (EPID L-2021-LLE-0034)
Dear Mr. Whitley:
The U.S. Nuclear Regulatory Commission (NRC, the Commission) has granted the enclosed exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR) 55.31, How to apply, paragraph (a)(3) and 55.33(a)(2), Written examination and operating test, for the Vogtle Electric Generating Plant (VEGP) Unit 4. This action is in response to Southern Nuclear Operating Company, Inc.s letter dated July 8, 2021 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML21189A153), as supplemented by letter dated October 1, 2021 (ADAMS Package Accession No. ML21281A214), regarding a request for an exemption from the requirements in 10 CFR 55.31(a)(3) and 10 CFR 55.33(a)(2) on behalf of 72 licensed operator candidates that have already successfully completed a written examination and an operating test on a standard AP1000 plant, which has been accepted by the NRC for licensing on VEGP Unit 3.
10 CFR 55.31(a)(3) requires each applicant for an operators license to submit a written request that the written examination and operating test be administered to the applicant. This written request must come from an authorized representative of the facility licensee by which the applicant will be employed. 10 CFR 55.33(a)(2) states, in part, that the Commission will approve an initial application for a license if it finds that the applicant has passed the requisite written examination and operating test in accordance with 10 CFR 55.41 and 55.45 or 55.43 and 55.45. The written examinations and operating tests determine whether an applicant for an operators license has learned to operate a facility competently and safely, and additionally, in the case of a senior operator, whether the applicant has learned to direct the licensed activities of licensed operators competently and safely.
The exemption is authorized by law, will not endanger life or property, and is otherwise in the public interest. The granting of the exemption is based on Enclosure 1 of the July 8, 2021, letter, as supplemented by the enclosure of the October 1, 2021, letter. Enclosure 2 of the July 8, 2021, letter is superseded by the enclosure of the October 1, 2021, letter. The NRC staff did not review Enclosure 3 of the July 8, 2021, letter, Sample NRC Form 398 Personal Qualification Statement - Licensee. The exemption is effective immediately and is valid only for the 72 licensed operator candidates identified in the enclosure of the October 1, 2021, letter.
B. Whitley A copy of the exemption is enclosed. The exemption has been forwarded to the Office of the Federal Register for publication.
Sincerely, Signed by Santos, Cayetano on 11/22/21 Cayetano Santos Jr., Project Manager Vogtle Project Office Office of Nuclear Reactor Regulation Docket Nos.: 52-025 52-026
Enclosure:
Exemption cc: Listserv
ML21279A185 - Package *via email NRO-008 OFFICE NRR/VPO:LA NRR/VPO:PM NRR/DRO/:BC NAME RButler CSantos (c) CCowdrey*
DATE 10/07/2021 10/6/2021 10/8/2021 OFFICE NRR/VPO: BC OGC/NLO NRR/VPO:D NAME VHall* JWachutka GBowman*
DATE 10/8/2021 10/27/2021 11/22/2021 OFFICE NRR/VPO:PM NAME CSantos (s)
DATE 11/22/2021