ML21258A295

From kanterella
Jump to navigation Jump to search
Revised License Termination Schedule - Docket No. 50-238; License No. NS-1; N.S. Savannah
ML21258A295
Person / Time
Site: NS Savannah
Issue date: 09/14/2021
From: Koehler E
US Dept of Transportation, Maritime Admin
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
Download: ML21258A295 (7)


Text

-~--

0 U.S. Department of Transportation Maritime Administration Office of Ship Operations 1200 New Jersey Ave., SE Washington, DC 20590 Ref: 50.82(a)(7)

September 14, 2021 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555

SUBJECT:

Reference Docket No. 50-238; License No. NS-1; N.S. SAVANNAH Revised License Termination Schedule (a)

Letter from Mr. Erhard W. Koehler (MARAD) to U.S. Nuclear Regulatory Commission (NRC), dated December 11, 2008, Submittal of Post Shutdown Decommissioning Activities Report, Revision 1 (b)

Letter from Mr. Erhard W. Koehler (MARAD) to U.S. Nuclear Regulatory Commission, dated March 31, 2011, Submittal of Decommissioning Funds Status Report for CY 2010 and updated Governmental Statement of Intent for Decommissioning Financial Assurance

( c)

Letter from Mr. Erhard W. Koehler (MARAD) to U.S. Nuclear Regulatory Commission, dated April 30, 2021, Notice of Management Contract Award In accordance with 10 CFR 50.82(a)(7), the Maritime Administration (MARAD) hereby provides a schedule update to the one originally provided in the PSDAR, Reference (a) and later revised in STS-1_34, Decommissioning Funds Status Report for CY 2010 as Enclosure 1 to Reference (b).

The purpose of this letter is to notify the NRC that following the award of contract on April 1, 2021 (Reference c), the License Termination Schedule has been revised as shown in Enclosures 1 and 2.

This letter contains no commitments.

If there are any questions or concerns with any issue discussed in this submittal, please contact me at: 0:

(202) 366-2631, M: (410) 776-8268, and/or e-111:ail me at erhard.koehler@dot.gov.

  • Enclosures

~~-*----~

~

,/e,t~:...__-----.,,.

Erhard W. Koehler Senior Technical Advisor, N.S. SAVANNAH Office of Ship Operations (new 7/23/21)

Docket No. 50-238; License NS-1; N.S. SAVANNAH Revised License Termination Schedule September 14, 2021 Enclosures

1. Revised PSDAR Section 5, Schedule of Planned Decommissioning Activities
2. Revised PSDAR Appendix B, Decommissioning Project Schedule.

2

Docket No. 50-238; License NS-1; N.S. SAVANNAH Revised License Termination Schedule September 14, 2021 cc:

Electronic copy NSSESC NSS SRC MAR 610,612,615 Hardcopy, cover letter only MAR-600, 640, 640.2 Hardcopy w/ all enclosures MAR-100, 640.2 (rt)

EWK/jmo USNRC (Ted Smith, Katherine Warner)

USNRC Regional Administrator - NRC Region I MD Department of the Environment (Eva Nair) 3

0 U.S. Department of Transportation Maritime Administration Office of Ship Operations Docket No. 50-238; License No. NS-1; N.S. SAVANNAH 1200 New Jersey Ave., SE Washington, DC 20590 to Revised PSDAR Section 5, Schedule of Planned Decommissioning Activities Revised PSDAR Section 5, Schedule of Planned Decommissioning Activities 4

Docket No. 50-238; License NS-1; N.S. SAVANNAH Revised License Termination Schedule September 14, 2021 5.0 SCHEDULE OF ACTUAL AND PLANNED DECOMMISSIONING ACTIVITIES This section is revised and replaced in its entirety. Through numerous reports and correspondences since 2008, the progression ofNSS decommissioning activities has been documented. The intent of this revisiqn is to summarize the work accomplished, and to frame the remaining planned work activities. The Appendix B Decommissioning Project Schedule is also revised and replaced in its entirety. Although PSDAR Rev O was withdrawn in January 2007, this new version of the schedule reverts to the format contained in Rev 0, which displayed the schedule based on the three major project phases.

The work activities associated with the three actual project phases correspond to the following sections of PSDAR Rev 1: a) Phase I encompassed the SAFSTOR Preparations of Section 3.1 and DECON Preparations of Section 3.3.1; b) Phase II encompasses the Performance of DECON Activities described in Section 3.3.1; and c) Phase ID encompasses the License Termination work described in Section 3.3.3.

From 2008 through 2018, NSS was maintained in staffed protective storage in Baltimore, MD.

In May 2017, MARAD received appropriations to support Phase I decommissioning activities. Phase I commenced formally on October 1, 2017, effective with the start of FY 2018. This phase was expected to complete at the end of CY 2019. In fact, it did not formally end until March 31, 2021. The major delay factors included the following: a) MARAD's Supplemental Environmental Assessment was completed six ( 6) months late; b) the Phase I drydocking start was pushed out six ( 6) months based on the late EA and other factors; c) the drydocking availability was extended from two (2) to six (6) months and the shipyard did not complete all of the Phase I shipwork planned; and d) the COVID-19 Pandemic Emergency. MARAD suspended DECON activities from March 31 through late June 2020, and thereafter constrained DECON activities by limiting the total number of onboard personnel. Phase I production work was completed upon acceptance of the Decommissioning HV AC system in March 2021.

  • The Phase I schedule of actual major activities and milestones is shown in Table 5-1 and in Appendix B.

In March 2018, MARAD received appropriations to support the balance of its decommissioning and license termination activities (project phases II and ID). Phase II commenced formally with the award of the decommissioning services contract on March 27. The schedule of planned Phase II and ID major activities and milestones is shown in Appendix B.

5

U.S. Department of Transportation Maritime Administration Office of Ship Operations Docket No. 50-238; License No. NS-1; N.S. SAVANNAH Revised PSDAR Appendix B, Decommissioning Project Schedule Revised PSDAR Appendix B, Decommissioning Project Schedule 1200 New Jersey Ave., SE Washington, DC 20590 '

6

Docket No. 50-238; License NS-1; N.S. SAVANNAH Revised License Termination Schedule September 14, 2021 ID TaskName 1 NS SAVANNAH DECOMMISSIONING PROJECT 2

91 10 11 12 13 Phase 1-DECON Planning and Engineering DECON appropriations.

NRC issued license Amendment 15 that anows dismantling and disposal of waste.

Installed 0-0eck Containment Vessel door.

DECON Bridge Contract Supplemental EA and FONS!.

Dismantlement in RCAs outside the Reactor Compartment Performed site characterization.

Orydocking (Philadelphia, PA).

Removed and stowed buffer seal charging pumps.

Performed DECON infrastructure and outfitting work.

DECON-L T Support Contract 14 Phase II - Industrial Dismantlement Activities 15 Complete preparation for decommissioning activities (electrical, mechanical, etc.).

16 Peform sman bore piping and minor component interference removal.

17, Remove Containment Vessel major equipment (Including Neutron Shield Tank, CROM Tower, Pressurizer, etc.).

18 19 20 Remove, package, ship and dispose of Reactor Pressure Vessel and Head Remove balance of contaminated components and structures.

Perform remaining decontamination activities.

21 Package, ship and dispose of radioactive waste materials.

22 -*Phase Ill -License Termination 23, 24\\

25 26

s.

NRG confirmatory surveys and review of FSS packages.

  • -I i i

l i

I I

Duration 2051 days r l I

640days 94 days 54 days 264 days 58 days 121 days 40 days 392 days 1006days I..

Start i

Fm,sh May 2017 - May 2025 May 2017 - Mar. 2021 i May 2017 and Mar. 2018 J Apr.2018 I

I Aug. 2018 I

I Oct 2018 - Mar. 2021 I I

Apr.2019 I

Jan. 2019 - Dec. 2019 I I I Jul. 2018 - Feb. 2020 I !

Sep. 2019 - Feb. 2020 '

Dec. 2019 May 2019. Mar. 2021 Mar. 2021 - Mar. 2026 0510312021 06/2812023 I

05103/2021 0911412021 0911512021 1210212021 12/0312021 1212212022 0511912022 08111/2022 1212012022 06113@23 0411812023 0611312023 12/0312021 0612812023 05/03/2021 05108/2025

! 585 days 05103/202f !08131r.l023 i

! 313 days I 09/01/2023 I 11/13/2024 i 486days 03107/2023 02/12/2025 228 days 06/1112024 05/0812025 2017 i

2018 I

2019 2020 I

2021 l

2022 I

2023 j

2024

/

2025 I

1st f:!.alli_?_11_(f_ !!!lffJ 1_st Haff j_?~~ t:'lilf j_1_st f:!_aff i_2n_d Ha1U_1_st _H~_lfJ?!'d Hlilf! 1st H_aff i?11_cf__t:'li~l 1.s~ Ha~]?_ll_d !:faff L1 st H_a_lfJ2~_(1_11a"-J1 ~t Ha".[ 21l_d H_alf i 1_st 11aJ..!l?..~7Ha~

~

I I

I

. I I

I I

I I I

I -'

~,

i I-I I

I I

I I

I

  • 271 1 day

.05108/2025 I 0510812025 NRC termination ofti~ense.

-~-I o_f_th_e-LTP_. ___

......_ __._<_)-'-__

...::..;....LC..c.....c.c.c..=.=-, __________ ~

________ -------~-----~--------*-_:*_--_--_--_--_--

1

-_-_-1'.i::, _____ ~

submit Final Status I

7