From:
Park, James To:
mayor@cityofjal.us; scobb@hobbsnm.org; Charles.wolf@co.winkler.tx.us; andrews@swcd.texas.gov
Subject:
U.S. Environmental Protection Agency notices the receipt of NRC"s Final Environmental Impact Statement for Interim Storage Partners, LLC"s license application Date:
Friday, August 13, 2021 11:03:00 AM The U.S. Environmental Protection Agency (EPA) has published a notice in the Federal Register confirming its receipt of the U.S. Nuclear Regulatory Commissions (NRCs) Final Environmental Impact Statement (FEIS) for the Interim Storage Partners, LLC license application for a consolidated interim storage facility (CISF) for spent nuclear fuel and Greater Than Class C radioactive waste in Andrews County, Texas. The EPAs notice is accessible using the following link:
The NRC staff made the FEIS publicly available on July 29, 2021. The FEIS is accessible using the following direct link: https://www.nrc.gov/docs/ML2120/ML21209A955.pdf, and from the NRC public webpage for the ISP CISF application at https://www.nrc.gov/waste/spent-fuel-storage/cis/waste-control-specialist.html.
An NRC licensing decision concerning the proposed CISF is expected by the end of September 2021. A licensing decision cannot be made until 30 days after the publication of EPAs Federal Register notice.
If you have any questions about this matter, I can be reached at James.Park@nrc.gov or by phone at 301-415-6954.
Thank you, James Park, Project Manager U.S. Nuclear Regulatory Commission