ML21243A316

From kanterella
Jump to navigation Jump to search
Reissue of North Anna Power Station Units 1 and 2 (Report 2021005)
Date released: 09/01/2021 Download: ML21243A316


Mid-Cycle Letter Revised Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2021005 and 05000339/2021005)
ML21243A308
Person / Time
Site: North Anna Dominion icon.png
Issue date: 08/31/2021
From: Stewart Bailey
NRC/RGN-II/DRP/RPB4
To: Stoddard D G
Virginia Electric & Power Co (VEPCO)
References
Download: ML21243A308 (5)
Updated Inspection Plan for North Anna Power Station, Units 1 and 2 - (Report 05000280/2021001 and 05000281/2021001)
ML21239A005
Person / Time
Site: Surry Dominion icon.png
Issue date: 08/26/2021
From: Stewart Bailey
NRC/RGN-II/DRP/RPB4
To: Stoddard D G
Virginia Electric & Power Co (VEPCO)
References
Download: ML21239A005 (5)