Category:Letter
MONTHYEARIR 05000373/20243012024-10-31031 October 2024 Initial License Examination Report 05000373/2024301 05000374/2024301 IR 05000373/20244042024-10-23023 October 2024 County Station – Security Baseline Inspection Report 05000373/2024404 and 05000374/2024404 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000373/LER-2023-001-01, Air Circuit Breaker (Acb) Mechanically Operated Contacts (MOC) Switch Failed to Actuate2024-10-0909 October 2024 Air Circuit Breaker (Acb) Mechanically Operated Contacts (MOC) Switch Failed to Actuate ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000373/20244012024-09-27027 September 2024 County Station – Security Baseline Inspection Report 05000373/2024401 and 05000374/2024401 ML24263A2062024-09-19019 September 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for LaSalle County Station - Holtec MPC-68MCBS ML24260A0492024-09-16016 September 2024 Operator Licensing Examination Approval - Lasalle County Station, Unit 1 and 2, September 2024 RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000373/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Lasalle County Station (Report 05000373/2024005; 05000374/2024005) IR 05000373/20244022024-08-28028 August 2024 County Station - Cyber Security Inspection Report 05000373/2024402 and 05000374/2024402 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 05000373/LER-2024-004-01, Emergency Diesel Generator Auto-Start and Load Due to Loss of System Auxiliary Transformer2024-08-22022 August 2024 Emergency Diesel Generator Auto-Start and Load Due to Loss of System Auxiliary Transformer IR 05000373/20240022024-08-13013 August 2024 County Station - Integrated Inspection Report 05000373/2024002 and 05000374/2024002 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000373/20244202024-08-0505 August 2024 County Station - Security Baseline Inspection Report 05000373 2024420 and 05000374 2024420 05000373/LER-2024-003-01, Supplement to Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded2024-07-31031 July 2024 Supplement to Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification RS-24-064, Nuclear Radiological Emergency Plan Document Revisions2024-06-28028 June 2024 Nuclear Radiological Emergency Plan Document Revisions ML24178A2522024-06-27027 June 2024 County Station – Acknowledgement of Response to NRC Inspection Report 05000373/2024001 and 05000374/2024001 and Disputed Non-Cited Violation 05000373/LER-2024-004, Emergency Diesel Generator Auto-Start and Load Due to Loss of Station Auxiliary Transformer2024-06-19019 June 2024 Emergency Diesel Generator Auto-Start and Load Due to Loss of Station Auxiliary Transformer RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations 05000373/LER-2024-003, Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded2024-06-0606 June 2024 Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded IR 05000373/20240102024-05-29029 May 2024 County Station - Commercial Grade Dedication Inspection Report 05000373/2024010 and 05000374/2024010 ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes 05000373/LER-2024-002, Reactor Protection System Half Scram Due to Motor Generator Set Electric Power Monitoring Assembly Output Breaker Trip2024-05-17017 May 2024 Reactor Protection System Half Scram Due to Motor Generator Set Electric Power Monitoring Assembly Output Breaker Trip RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24131A1512024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 IR 05000373/20240012024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000373/LER-2024-001, Core Operating Limits Report Thermal Limits Exceeded2024-04-26026 April 2024 Core Operating Limits Report Thermal Limits Exceeded ML24108A1562024-04-15015 April 2024 Updated Final Safety Analysis Report (Ufsar), Revision 26 and Fire Protection Report (Fpr), Revision 11 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24071A2122024-03-12012 March 2024 County Station - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000373/20230062024-02-28028 February 2024 Annual Assessment Letter for Lasalle County Station, Units 1 and 2 (Report 05000373/2023006; 05000374/2023006) RS-24-014, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-02-22022 February 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors ML24018A0682024-02-0909 February 2024 Issuance of Amendment Nos. 262 and 247 Revised Design Bases of Lower Downcomer Braces IR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 ML23354A2902024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0028 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23360A6082023-12-27027 December 2023 County Station Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000373/2024010 and 05000374/2024010 ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 05000373/LER-2023-002, Turbine Stop Valve Limit Switch Failure Due to Lubricant Degradation2023-12-0404 December 2023 Turbine Stop Valve Limit Switch Failure Due to Lubricant Degradation 2024-09-06
[Table view] |
Text
Mr. David Rhoades Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
LASALLE COUNTY STATION, UNITS 1 AND 2 - NOTIFICATION OF AN NRC BIENNIAL LICENSED OPERATOR REQUALIFICATION PROGRAM INSPECTION AND REQUEST FOR INFORMATION
Dear Mr. Rhoades:
In a conversation on August 19, 2021, between Mr. B. Bartlett, Senior Operations Engineer, the NRC lead inspector for this inspection, and Mr. D. Blair, Manager, Operations Training, final arrangements were made for the U. S. Nuclear Regulatory Commission (NRC) to inspect the licensed operator requalification program at the LaSalle County Station. The inspection is planned for the week of October 18, 2021, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations and annual operating tests as necessary to support the NRC's inspection program needs. To assist in minimizing the impact that the inspection has on the site and to ensure a productive inspection, we have enclosed a request for documents needed for the inspection.
Please furnish the items listed in the first group of the attached enclosure, needed to support the in-office inspection activities, to the NRC by October 6, 2021. Please have the items listed in the second group of the attached enclosure available for the inspectors during the onsite portion of the inspection activities. Mr. D. Blair has been advised of this request.
Thank you for your cooperation in this matter. If there are any questions regarding either the inspection, or the material requested in the enclosure, please contact me at 630-829-9753 or via e-mail at Bruce.Bartlett@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.August 25, 2021 This letter and its enclosure will be available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Bruce L. Bartlett, Senior Operations Engineer Operations Branch Division of Reactor Safety Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18
Enclosure:
REQUESTED INFORMATION TO SUPPORT LICENSED OPERATOR REQUALIFICATION PROGRAM AND LICENSED OPERATOR PERFORMANCE INSPECTION (IP 71111.11) cc: Distribution via LISTSERV Signed by Bartlett, Bruce on 08/25/21
D. Rhoades
Letter to David Rhoades from Bruce L. Bartlett dated August 25, 2021.
SUBJECT:
LASALLE COUNTY STATION, UNITS 1 AND 2 - NOTIFICATION OF AN NRC BIENNIAL LICENSED OPERATOR REQUALIFICATION PROGRAM INSPECTION AND REQUEST FOR INFORMATION
DISTRIBUTION:
Jessie Quichocho Aaron McCraw RidsNrrDorlLpl3 RidsNrrPMLaSalle Resource RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Jamnes Cameron Allan Barker DRPIII DRSIII
ADAMS Accession Number: ML21237A512 Publicly Available Non-Publicly Available Sensitive Non-Sensitive OFFICE RIII:DRS/OB NAME BBartlett:mb DATE 08/25/2021 OFFICIAL RECORD COPY REQUESTED INFORMATION TO SUPPORT LICENSED OPERATOR REQUALIFICATION PROGRAM AND LICENSED OPERATOR PERFORMANCE INSPECTION (IP 71111.11)
Please provide the following information on a CD/DVD, if possible, by October 6, 2021.
- 1. One complete version of a biennial requalification written examination administered during the training cycle.
- 2. Ten (10) job performance measures (JPMs) and four (4) simulator scenarios associated with an annual requalification operating test required by Title 10 of the Code of Federal Regulations, Part 55.59(a)(2). The JPMs and scenarios to be reviewed should include those that will be observed during the onsite portion of this inspection, with any remaining JPMs and scenarios selected from other weeks within the same training cycle.
- 3. Complete versions of the reference materials used to develop the administered written examinations and operating tests. (Refer to ES-201 Attachment 3, Reference Material Guidelines for Initial Licensing Examinations, for additional examples and clarification.)
- 4. A list (or lists) of licensee-identified issues associated with licensed operator errors or other licensed operator performance problems, which have occurred in the actual plant/main control room since the last biennial requalification program, their associated corrective actions, and if these issues were incorporated into requalification training.
(These issues are likely documented in condition/problem identification reports, licensee-conducted audits and assessments, and in industry operating experience reports, etc.)
- 5. Facility licensee procedures for licensed operator requalification training and examination, including examination security procedures.
- 6. A schedule of the licensees examination activities during the on-site inspection week.
Please have the following information available for U.S. Nuclear Regulatory Commission review on October 18, 2021.
- 1. Spreadsheets and/or test outlines which show the usage of written examination questions, JPMs, and simulator scenarios.
- 2. Licensed operator pass/fail statistics for any U.S. Nuclear Regulatory Commission-required requalification examinations that have been completed.
- 3. An overall schedule of the facility licensees requalification program since the last biennial inspection (cycle weeks, training topics, etc.).
- 4. A list and descriptions of any examination security problems since the last biennial inspection (likely documented in training department condition/problem identification reports).
- 5. Records for licensed operator requalification training attendance, licensed operator performance in requalification, licensed operator remedial training, individual licensed operator medical records, and records for maintaining an active license and license re-activation.
Enclosure
- 6. Simulator testing, maintenance, modification, and performance records. Simulator corrective action records, including lists of open/closed simulator deficiencies, and corrective actions taken.