Dispositioning of Degraded Performance Column Effectiveness Review Recommendations
ML21209B001
Person / Time
Issue date: 09/17/2021
From: Masters A
NRC/NRR/DRO/IRAB
To: Christopher Regan
NRC/NRR/DRO
Alex Garmoe, NRR/DRO/IRAB 415-3814
References
Download: ML21209B001 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 17, 2021 MEMORANDUM TO: Christopher Regan, Acting Director Division of Reactor Oversight Office of Nuclear Reactor Regulation FROM: Anthony D. Masters, Chief /RA by e-mail /

Reactor Oversight Process Assessment Branch Division of Reactor Oversight Office of Nuclear Reactor Regulation

SUBJECT:

DISPOSITIONING OF DEGRADED PERFORMANCE COLUMN EFFECTIVENESS REVIEW RECOMMENDATIONS The purpose of this memo is to document the recommendations that the agency will take action on in the near term regarding the effectiveness review of the Degraded Performance Column (Column 3) of the Reactor Oversight Process (ROP) Action Matrix. On March 30, 2021, an effectiveness review of the ROP Degraded Performance Column of the Action Matrix was completed and documented in a report available in ADAMS as Accession No. ML21069A154.

The review was conducted as part of the ROP self-assessment process prescribed in Inspection Manual Chapter 0307. Several recommendations were documented in the report following a thorough data-driven assessment review.

The recommendations documented in the report were:

  • Make clarifying revisions to IP 95001 involving inspection of multiple White inputs and the scope of inspection objective 01.02
  • Conduct an updated cumulative effects review of ROP changes implemented since 2015
  • An assessment to determine whether the assessment program would be improved by elimination of the Strategic Performance Area and Cornerstone limitations to GTG issue aggregation, and whether such a change should be pursued, since current program structure can allow up to six White inputs in Column 2.

Upon review of the recommendations in spring 2021, the Division of Reactor Oversight elected to move forward with clarifying revisions to IP 95001 and to schedule an updated cumulative effects review of ROP changes, potentially within the structure of the ROP self-assessment program. A revision to IP 95001 to address objective 01.02 has already been issued and staff is currently working to schedule the recommended cumulative effectives review. A decision was made to not move forward with a review or consideration of the Strategic Performance Area and Cornerstone limitations on GTG assessment input aggregation at this time. There may be value CONTACTS: Alex Garmoe, NRR/DRO/IRAB Anthony D. Masters, NRR/DRO/IRAB 301-415-3814 770-846-4740

C. Regan 2 in reviewing this item at some point in the future, but staff resources currently would be better spent on changes already being pursued. The effectiveness review report with its recommendations and supporting data remains available for consultation should any efforts to review or revise the Action Matrix or assessment program be considered in the future.

C. Regan 3

SUBJECT:

DISPOSITIONING OF DEGRADED PERFORMANCE COLUMN EFFECTIVENESS REVIEW RECOMMENDATIONS DATED: SEPTEMBER 17, 2021.

DISTRIBUTION:

CRegan AMasters AGarmoe ADAMS Accession Number: ML21209B001 *via e-mail NRR-601 OFFICE NRR/DRO/IRAB NRR/DRO/BC NAME AGarmoe* AMasters*

DATE 8/26/21 9/17/21 OFFICIAL RECORD COPY