ML21187A317

From kanterella
Jump to navigation Jump to search
Well Permit Request, Ri Phase II Work Plan
ML21187A317
Person / Time
Site: Westinghouse
Issue date: 01/21/2021
From: Joyner D
Westinghouse
To: Kuhn K
SCDHEC, BLWM, State of SC, Bureau of Land and Waste Management, State of SC, Dept of Health & Environmental Control
Trefethen, JA
References
LTR-RAC-21-08
Download: ML21187A317 (3)


Text

Westinghouse Electric Company Nuclear Fuel Columbia Fuel Fabrication Facility 5801 Bluff Road Hopkins, South Carolina 29061 USA SCDHEC, BLWM Direct tel: 803.647.1920 Kim Kuhn Direct fax: 803.695.4152 2600 Bull Street e-mail: joynerdp@westinghouse.com Columbia, SC 29201 Your ref:

Our ref: LTR-RAC-21-08 January 21, 2021

Subject:

Well Permit Request, RI Phase II Work Plan Mrs. Kuhn:

Please find attached for your consideration a request by AECOM to install temporary and permanent wells to support the RI Phase II Work Plan.

Respectfully, Diana P. Joyner Principal Environmental Engineer Westinghouse Electric Company, CFFF 803.497.7062 (m)

Cc: N. Parr, Environmental Manager J. Ferguson, EH&S Manager J. Grant, AECOM Project Manager ENOVIA Records Enc.: AECOM Well Permit Request, File # 51377, dated January 21, 2021

© 2021 Westinghouse Electric Company LLC All Rights Reserved

AECOM (803)254-4400 101 Research Drive (803)771-6676 Columbia, SC 29203 January 21, 2021 Ms. Kimberly M. Kuhn, Project Manager State Voluntary Cleanup Section Division of Site Assessment, Remediation and Revitalization Bureau of Land and Waste Management 2600 Bull Street Columbia, S.C. 29201

Subject:

Columbia Fuel Fabrication Facility Well Permit Request Richland County, S.C.

Consent Agreement CA-19-02-HW File # 51377

Dear Ms. Kuhn:

Westinghouse Electric Company. Inc. (Westinghouse) Columbia Fuel Fabrication Facility (CFFF),

AECOM Technical Services, Inc. (AECOM), and South Carolina Department of Health and Environmental Control personnel met virtually on Thursday January 14, 2021 to discuss multimedia sampling results collected to date as part of Phase II of the Remedial Investigation (RI). One of the discussion topics during this virtual meeting was RI Phase II groundwater screening data.

The discussions resulted in the parties agreeing to the following actions:

To convert the temporary well installed in boring L-43 to a permanent monitoring well (to be designated W-102),

The locations of 10 additional permanent monitoring wells (W-103 through W-112), and The locations of 11 potential additional temporary groundwater screening points (L-48 through L-58).

The locations of the monitoring wells and groundwater screening points are displayed in the attached Figure 1. Temporary wells previously approved on December 3, 2020 under permit MW-12628 will be used for seven of the groundwater screening points. In summation, CFFF and AECOM request well permits for 10 permanent wells and 15 additional temporary wells.

Should you have any questions regarding the information provided in this letter, please do not hesitate to contact me at (803) 740-1604.

Sincerely, Jeremy Grant Project Manager Attachments: Figure 1 - Proposed Groundwater Screening and Monitoring Well Location Map SCDHEC_Well Permit Request Letter_1-21-21.doc

Legend Surficial Aquifer - Upper Zone Monitoring Well Surficial Aquifer - Lower Zone Monitoring Well Black Mingo Aquifer Monitoring Well Proposed Surficial Aquifer Monitoring W-Well Location - Upper Zone Proposed Surficial Aquifer Monitoring W-Well Location - Lower Zone Proposed Surficial Aquifer Groundwater L-Screening Location - Upper Zone Proposed Surficial Aquifer Groundwater L-Screening Location - Upper and Lower Zones Proposed Surficial Aquifer Groundwater L-Screening Location - Lower Zone Staff Gauge Location Ditch Culvert Dike Location Mill Creek Flow Direction Mill Creek Property Line SCRDI Bluff Road (Superfund Site)

Top of Bluff Inferred Top of Bluff Bottom of Bluff Inferred Bottom of Bluff Secondary Bluff Area EL East Lagoon Upper Sunset NL North Lagoon Lake South Lagoon SL SAN Sanitary Lagoon Lower Sunset WL1 West Lagoon I Lake WL2 West Lagoon II Upper Sunset Dike 0 300 600 Lower Sunset Feet Dike 1:7,200 Map Projection: NAD 1983, South Carolina State Plane, FIPS 3900, Feet Datum: North American 1983 Mill Creek 101 Research Drive Canal Columbia, SC 29203 T: (803) 254-4400 F: (803) 771-6676 Proposed Groundwater Screening and Monitoring Well Location Map WESTINGHOUSE COLUMBIA FUEL FABRICATION FACILITY HOPKINS, SOUTH CAROLINA PROJECT NO. PREPARED BY: DATE:

60595649 CCS January 2021 FIGURE 1 Path: M:\EnvDataViz\Westinghouse\mxd\2020_OctoberSemiAnnualRpt\fig_1_SiteMap01202021.mxd