EN 55223 Upodate - North Anna 10CFR Part 21 Interim Report P21-03302021-IR
ML21152A279
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 05/28/2021
From: Bolt T
Paragon Energy Solutions
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
55223, P21-03302021-IR
Download: ML21152A279 (1)


Text

Date: 5/28/2021 To: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 Fax Number (301)816-5151 10CFR Part 21 Notification: P21-03302021-IR

Subject:

Interim Report for Failures of Size 1 and 2 Freedom Series Full Voltage Reversing Starters In accordance with Title 10 of the Code of Federal Regulations 21.21(a)(2), Paragon Energy Solutions is submitting this interim report for the Size 1 and 2 Freedom Series Full Voltage Reversing Starters that have experienced failures at Dominion North Anna Station.

Paragon is submitting this Interim Report since this condition is currently under evaluation but will not be completed within 60 days.

Paragon is in communication with EATON, the OEM for the starters/contactors to determine the extent of condition. The evaluation is expected to be completed by June 30, 2021.

Reference:

P21-03302021, Rev. 1 - NRC Event Number EN 55223 Note: It was determined that Dominion - Millstone should not be included in the list of affected plants.

Millstone will be removed from the list in the final revision of P21-03302021.

Please contact me with any questions or comments.

Sincerely, Tracy Bolt Chief Nuclear Officer Paragon Energy Solutions 817-284-0077 tbolt@paragones.com Paragon Energy Solutions 7410 Pebble Drive

  • 76118 817-284-0077
  • Fax 817-590-0484 Page 1 of 1