ML21133A049

From kanterella
Jump to navigation Jump to search
0 to Updated Final Safety Analysis Report, Appendix 6A, Subcompartment Differential Pressure Considerations, Table of Contents
ML21133A049
Person / Time
Site: Limerick  
Issue date: 04/29/2021
From:
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML21138A803 List: ... further results
References
Download: ML21133A049 (3)


Text

LGS UFSAR APPENDIX 6A 6A-i REV. 13, SEPTEMBER 2006 APPENDIX 6A -SUBCOMPARTMENT DIFFERENTIAL PRESSURE CONSIDERATIONS TABLE OF CONTENTS 6A.0 INTRODUCTION 6A.1 BIOLOGICAL SHIELD ANNULUS SUBCOMPARTMENT MODELING PROCEDURES AND ANALYSIS 6A.2 DRYWELL HEAD REGION SUBCOMPARTMENT ANALYSIS 6A.3 REFERENCES

LGS UFSAR APPENDIX 6A 6A-ii REV. 13, SEPTEMBER 2006 APPENDIX 6A -SUBCOMPARTMENT DIFFERENTIAL PRESSURE CONSIDERATIONS LIST OF TABLES Table Title 6A-1 Reactor Primary System Blowdown Flow Rates and Fluid Enthalpy -

Recirculation Line Break 6A-2 Recirculation Outlet Line Break Blowdown Mass Flux Time History 6A-3 Reactor Primary System Blowdown Flow Rates and Fluid Enthalpy -

Feedwater Line Break 6A-4 Feedwater Line Break Blowdown Mass Flux Time History 6A-5 Head Spray Line Break 6A-6 Compartment Volumes Used in Reactor Vessel Shield Annulus Subcompartment Analysis 6A-7 Flow Area and Coefficients Used in Reactor Vessel Shield Annulus Subcompartment Analysis

LGS UFSAR APPENDIX 6A 6A-iii REV. 13, SEPTEMBER 2006 APPENDIX 6A -SUBCOMPARTMENT DIFFERENTIAL PRESSURE CONSIDERATIONS LIST OF FIGURES Figure Title 6A-1 Reactor Shield Annulus Arrangement 6A-2 Reactor Shield Annulus Subcompartment Model Schematic 6A-3 Pressure Transient in Reactor Shield Annulus Following Recirculation Outlet Line Break at the Nozzle Safe-End 6A-4 Pressure Transient in Reactor Shield Annulus Following Feedwater Line Break at the Nozzle Safe-End 6A-5 Force Transient on Reactor Vessel Following Recirculation Outlet Line Break at the Nozzle 6A-6 Force Transient on Reactor Shield Wall Following Recirculation Outlet Line Break at the Nozzle 6A-7 Force Transient on Reactor Vessel Following Feedwater Line Break at the Nozzle 6A-8 Force Transient on Reactor Shield Wall Following Feedwater Line Break at the Nozzle 6A-9 Drywell Head Arrangement 6A-10 Head Spray Line Break Geometry 6A-11 Pressure Transient in Drywell Head Area for Head Spray Line Break